MRP - Unfix Fixed Schedule Lines with partial receipt

Dear Experts,
I am facing a problem that I haven't been able to solve using previous postings in the forum nor reading OSS notes.
I have a Factory PL01 that needs some raw materials that are bought and received in a distribution center DC01 located in another city.
Procurement data in material master MRP views:
In PL01, this Raw materials have external procurement with special procurement key "transfer from DC01"
In DC01 this Raw materials have external procurement witho no special procurement key (standar purchase order)
To make things easier we have an LU Scheduling Agreement and also maintained source list to generate automatic schedule lines after running MRP.
This is working ok.
My problem comes here:
When I create the delivery for schedule line (VL10G) the receipt becomes fixed in PL01. Lets say theorical quantity is 20.000 on schedule line but finally supplier can only deliver 18.000 to DC01 and DC01 can only transfer 18.000 to PL01.
in MD04, plant PL01 There will be a fixed pending quantity of 2.000 for the schedule line that will not be overwritten by MRP runs.
I would like to "Unfix" this fixed quantity but I can't. I read previous postings and many people say it's not possible and that quantity should be adjusted manually in schedule line to delete the fixed receipt.
Does anybody knows how to manage this? Can the remaining quantity of schedule line be unfixed? If not: Is there a more efficient way than adjust one-by-one the schedule lines ?
Please throw me a light about this.
Best Regards,
Sebastián Ligueros

Sorry I cant help you in your question but, i think you can help me in  my.
I need to use MRP to creade the schedule lines for an schedule agreement LU but even when the Info record is set, plants  are set witht the vendor and customers, MRP is not creating the Schedule lines automaticaly.
Do you remenber what things are required to do it?
I also set the source list with the Schedule Agreement and put it as relevant to MRP (2).
Any help will be great thanks.

Similar Messages

  • MRP Out Put  Schedule lines date format to month

    Hi Friends,
    I am working on SAP4.7 Version.
    I have maintained all the relavent MRP datas in material master.
    Like MRP type - PD,
    Lot Size- MB ( Monthly Lot size).
    I have created planned independent requirement in MD61 monthly wise for that material.
    I have given Schedule agreement number in Source in List with MRP indicator - 2.
    I am running MRP for a material with MD02 with MRP parameter Delivery schedules -3 (Schedule lines) .
    The MRP running succesfully and creating delivery Lines with delivery dates.
    But the requirement by the client is..
    The delivery lines should be generated in month wise.
    How to convert the schedule lines generated in day format to Month format in MRP run out put?
    While creating schedule lines with ME38. we have option to select the day format / month format/ week wise?
    But the MRP out put always generated in date wise?
    Any one knows what changes i should make?
    Guide me ..
    Thanks & Best Regards
    Giri

    Hai Boss
              Can you throw some light , how you set default mrp indicator month wise with the help of ABAPER.
    My client requirement also same like you. Yours is month, mine is week. Pl help me out.
    regards
    ssp

  • Schedule Lines with Firm

    Hi Gurus,
    I have an Issue in Schedule lines. Delivery schedules lying with in the firm zone has firm indicator 1(Firm zone) in ME33l. The same schedule line shows in MD04 with * Symbol as firmed. In some of the cases Delivery schedules push out from the Firm Zone does not have a Firm Indicator in ME33l but it is firmed in MD04 with * symbol.In which table & field I can Identify the Firmed schedule lines with * symbol in MD04.Please Help me.
    Regards,
    Senthil.K

    Delivery schedules lines are populated when MRP is Run.
    symbol indicates that you have done manual intervention in the purchase order mentioned.
    In MDO4 you can see * symbol
    Ganesh kumar

  • Schedule lines with no ordered quantity

    If a schedule line is not confirmed because of non-availability of stock on the customer requested delivery date, it creates another schedule line with confirmed quantity and new delivery date.  How can we link these two lines so that we know that the lines with no confirmed quantity has other schedule line with confirmed quantity.  Any response is appreciated.

    Hi Rajeev,
    It is the SAP standard behavior. Regarding the requested delivery date you entered, the system will check if it can be met, if yes, only one schedule line with confirmed quantity. if not, the system will use the forward scheduling to calculate a new earliest delivery date. then the second schedule line is generated with confirmed quantity. You can see all these lines at the sales order item schedule line view.
    Also you can find the information in table VBEP.
    Regards
    Jean
    Please reward points if helpful.
    Message was edited by:
            Jean Chang

  • Schedule lines with null quantity deleted from EKET

    Hi All, I would understand if there is a logic that deletes schedule lines with null quantity from EKET.
    Sometimes it happens and sometimes not and I can't find the reason. I thought that it could depend from the transaction used (ME38 or MD43) but it's not so.
    thanks
    L

    Hi,
    This functionality was implemented after OSS Note was applied with release 4.0B.
    191898 - ME38: Delivery schedules w/ scheduled quantity zero

  • Collectively schedule line with quantity

    Dear all
    How to see collectively schedule line with quantity in SAP
    Rgds

    It can be seen if you have created a scheduling agreement, where in you have JIT schedule and normal Forecasting schedule lines.

  • MRP Run error " Schedule Lines not generating properly"

    Hi Folks,
    I am facing a typical issue with MRP Run.
    Every time when I am running the MRP for a particular material I have made settings such that Schedule lines to be generated by maintaining the Source list and MRP relevancy as 2 in source list. Also I have fixed the vendor. Now my problem is I am getting Schedule lines for first run and Combination of Purchase requests and Schedule lines or only PRs for the next MRP run.. This is keep on repeating in such as way that the planning is shifting as said above for subsequent MRP Run.
    Note that the initial settings during MD02 remain same for all run.
    I want only schedule lines to be generated but not PR.
    Pls advise and provide input where the wrong might be.
    Quick responce would be appreciated.
    Regards
    Shash

    Dear shash,
    Check with What are the MRP control Parameters values which you are using for the MRP run.
    In MD02, For Deleivery schedules run with value 3 - That's -  Schedule lines.
    The other options are     1  No schedule lines
                                       2  Schedule lines in the opening period.
    check with this & revert back.
    Regards
    Mangalraj.S

  • Number  of the Open PO and Fixed Schedule line

    Hello All
    I need a report which show us how many open Purchase Order line do we have in the system..
    And also I need another report which show us How many fixed schedules do we have in the system.
    Is it possible to get theese information by using standart transection or do I need any speacil report  for that?
    Thank you for your support

    Hi sredar,
    Use the T-Code ME2N.U will get all open POs in particulat plant orporg or mat or vendor .if u know any one of these u will get all po list with that combination.
    Reward me if helpfull
    ASHOK

  • Why GR performed on MRP generated delivery schedule line (unconfirmed)?

    Hi Gurus,
    Need some advice from you all, I have a scenario here which MRP generated the delivery schedule lines for material A on 10.08.2011 - 124 KG.
    User review the MRP result and didnt confirm the line, but she added in manual line on 11.08.2011 - 124KG.
    On 11.08.2011, warehouse performed GR on the delivery schedule lines. It's found that GR was actually updated into the delivery schedule line generated by MRP (10.08.2011) and not the manual line confirmed by user. (11.08.2011).
    User is questioning now why the GR able to be performed on MRP generated line which had not been confirmed? Any guru can share with me the fact and good note regarding this on MRP? Thanks!
    Michelle

    Hi,
    Since we are talking here about schedule lines, these are open for GR when the delivery schedule is send to the vendor.
    In your case you had a quantity open for 10/08/2011 generated by MRP, then the user added manually another line on 11/08/2011. After this the user will have transmitted the delivery schedule which makes that both the items where marked as transmitted and thus open for GR.
    Now when the goods come in the system will post against the first open schedule line that is found until this is fulfilled and then switch to the next open line at the moment of GR. So this is why the GR was put against the MRP generated schedule line as this one was the one with the earlier date.
    Regards,
    Peter

  • MRP To Generate SCHEDULE LINES for Scheduling Agreement

    Hi
    I have followed the below steps but still the Schedule lines is not generated for scheduling agreement.
    1Maintain MRP views 1,2,3,4 for the material in material mste.(MM01)
    2. Maintain Purchase Info Record for the vendor plant & material combination.(ME11)
    3. Create Scheduling agreement using ME31L
    4. Maintain source list for the material & the scheduling agreement # and Line item set the MRP relevant indicator 2 (Necessary ?) ME01
    During Run MRP for the material.the below details entered///
    Processing key NETCH Net Change in Total Horizon
    Create purchase req. 1 Purchase requisitions in opening period
    Schedule lines 3 Schedule lines
    Create MRP list 1 MRP list
    Planning mode 1 Determination of Basic Dates for Planned
    Run MDBT or MD02 but still doesn't create the schedule lines......Anything else missing.
    MRP1:
    MRP Procedure: PD
    MRP Group: 0000 (External Procurement only)
    Lot Size: EX (Lot For Lot)
    MRP2:
    Procurement Type: F
    Sched Margin Key: 000
    MRP3:
    Avilablity chec: 02 (Individual requirement)
    MRP: 4
    Nil

    Raj,
    Source List a Mandatory for Scheduling Agreement, if you want to create automatic Scheduling line.
    Plz use (2) in MRP RELEVENT tab in ME01 (Source List).
    rest of the thing is ok, make sure a material master(MRP 2 VIEW) in that view you have to give a planed delivery days. it is must.
    HOPE IT WILL WORK
    Regards:
    Poision

  • MRP create more Schedule Lines than target quantity

    We already follow the OSS note 83343, we create a Schedule agreeement and validity date is the same as the Source List and Quota arrangement, also the Target Quanity is the same in the quota arrangement in the maximun quantity and Maximun release qty fields.
    After maintaining that data, we run the MRP as follow:
    Processing key          NETCH               Net change for total horizon
    Create purchase req.    2                   Purchase requisitions in opening period
    Delivery schedules      3                   Schedule lines
    Create MRP list         1                   MRP list
    Planning mode           1                   Adapt planning data (normal mode)
    Scheduling              1                   Basic dates will be determined for plann
    After that, still in teh schedule agreement was created more schedule lines that the quantoty is bigger that the target quantity in the sched Agreement.
    What else we miss??

    Thanks for your not help.
    That I can investigate is the quota arrenagement is incorrect but for some reason the QA is not working.

  • Schedule lines with no confirmed qty

    The client needs schedule lines generated with no confirmed quantity please assist if itss possible
    Regards
    Maddy

    Hi,
    you will have to create a project for the enhancement object ATP00001 through CMOD.... You can also explore the possibility of activating the availability check which will also set the confirmed quantity to zero.
    Regards,
    Murali

  • Schedule line with qty 0

    Hi
    When i enter qty as 0 in VA32  transaction , that schedule line disappears from the screen . i want to restrict this . i.e as soon as qty is made 0 then user should be prompted with a error message and control should go the line for reentering the qty.
    I have tried to find out the enhancement spot where this deletion is done , but still could not.
    Please help me with the procedure.

    Hi,
    Goto MD04, here you will find that whatever Goods Movements (inward & outward), based on the input selected at Material
    Master-> Sales: General/Plant Data.
    '02' Individual - Each Sales Order/PO(STO) from Sales. and Production order/PO for material inwards at respective Plant & material.
    '01' Daily - For respective day
    'KP' - It will show you nothing. (confirms quantity without checking any other requirements)
    Thank You,
    RB.

  • A new schedule line with net price zero but custom duty non-zero value

    Hello,
    I have a special requiremnet in MM scheduling agreement, for a specific type of scheduling agreement, I am copying a schedule line to a new schedule line. The new schedule line should have all the pricing and duty values from the old schedule line, except the net price of the new schedule line should be zero.
    I am able to make the net price zero in the new schedule line, but not able to copy the custom duty values from the old schedule line. Since my netprice is zero in the new line, it automatically set all other follwoing duty values also to zero.
    Say example a scheduling agreement: A has two line:
                                                                                    Condition Type           %                    Total Value
    scheduline line 1 -  with pricing values                  PB00                                                  200  USD                                                                               
    Cond1                         5                       10  USD
                                                                                    Cond2                        10                      20  USD
                                                                                    230  USD
    expectedd result i the new schedule line
    scheduline line 2 -                                                  PB00                                                  000  USD                                                                               
    Cond1                         5                       10  USD
                                                                                    Cond2                        10                      20  USD
                                                                                    30  USD
    I am trying to overwrite the condition values using the FM RV_CONDITION_COPY, but  I am not getting the desired result.
    Please let me know if you have any solution to my requirement.
    Best Regards,
    Amarjit Singh

    Hello Colleague;
                                                                                    In Standard the schedule lines cateogory CV is activated for 'Req./Assembly' and 'Availability'.                              
    Please, make this adjust and re-test you process.
    Regards
    Ruy Castro

  • Force one schedule line with BAPI_SALESORDER_CREATFROMDAT2

    Hi,
    How can I force the BAPI BAPI_SALESORDER_CREATFROMDAT2 to create sales order with only one schedule line for some itmes ?
    Remark : <i>I don't want to change the customer parameters</i>
    Regards

    If your schedule line category is relevant for availability check - it means that you can't say in advance will it be confirmed or not and how many sched.lines it's going to have, you can estimate by "order simulate" but it doesn't mean that your real order will fully match to simulation.
    If you are not doing any availability check (your materials are always available) - then your item will get current material availability date... but stil the number of schedule lines will depend on whether or not your required delivery date can be met taking into account pick/pack time, transit time (route), calendars of shipping point, route & customer.... and you can't force one schedule line in this case unless you change your required date to a proposed delivery date based on simulation.

Maybe you are looking for

  • MB5B Report..!!1

    MB5B Stock showing Minus on Particular date ( issue is more than receipt) we are having the practice of posting consumption entry (201) post dated..whether system is  checking Current stock OR Stock on that date.

  • Can't sync Outlook 2010 calendar using DM 6

    Hi, This is my first time on the forum. I have searched for similar issues and tried some suggestions, but am still having issues. I get "BlackBerry Desktop Software has encountered a problem and needs to close" error message trying to sync to Outloo

  • I cant register my mc book air,its asking purchase date and i dont remember and dont have any receipt

    i cant register my mac book air in my profile.it is asking purchasing date which i dont remeber and dont haveany receipt.

  • My imac does not start up

    My imac does not start up. It shows a white page with apple sign .

  • ISE AD group issue

    Dear Team, I am going to deploy cisco ISE (1.2) at one of our customer sites. I am able to join the ISE with Active directory and users are able to authenticate with their Domain login ID. Problem:-  I am not able to retrieve/See the acitve directory