MRP with Subcontracting (Urgent)

Hi,
I have a scenario of Subcontracting in an Automobile Industry. The planning plant is I005 and the BOm is as follows -
Final Assy 'FA' (FERT) {Assembly done on subcontract basis by subcontract Vendor A005)
-- Sub Assy 01 'SA1' (HALB) - {Assembly done by Subcontract Vendor D025}
-- Sub Assy 02 'SA2' (HALB) - {Assembly done by Subcontract Vendor A005}
--- Component 01 'C1' (HALB) - {Component required in both SA1 and SA2 and procured by plng plant I005}
--- Componenet 02 'C2' (HALB) - {Component required in SA2 only and procured by plng plant I005}
--- Component 03 'C3' (HALB) - {Component required in SA1 only and procured by plng plant I005}
The clients requirements are as follows -
1. Want to put plan for FA as PIR in MD61 for 3 months as monthly plan.
2. Take Run on monthly basis in plant I005
3. After MRP run the system should do the following things -
   -- In net requirement calculation the system should take material provided stock and I005's unrestricted stock.
   -- System will create subcontract PO for SA1 to vendor D025 and FA to A005
   -- system will not create subcontract PO/PR or Sch Line for SA2 but it should plan for C2 for subcontract vendor A005.
  -- System should take care of Material Provided stock for D025, A005 and un restricted stock of I005 for Component C1 and club the total required quantity and make monthly schedule line in SA as per Source List maintained.
  -- the system should create Sch Line for C3 as monthly schedule line for SA per maintained in Source list
I made few settings as follows but the results are not as per my expectations.
1. For FA - Procurement type - F and Spl Proc Key - 30 and planning strategy 10 and MRP type - PD
2. For SA1 - Procurement type - F and Spl Proc Key - 30 (Subcontracting) and MRP type - PD
3. For SA2 - Procurement type - F and Spl Proc Key - 60 (Phantam in planning) and MRP type - PD
4. For C1 - Procurement type - F MRP type - PD
5. For C2 - Procurement type - F MRP type - PD
6. For C3 - Procurement type - F MRP type - PD
7. Maintained Source list for C1, C2 and C3 with valid sch agreements and MRP relevency indicator "2"
8. Running MRP monthly for plant I005 and with NETCH, Sch Line - 3
Can anyone please guide me with the correct settings I need to make to map the requirements.
Thanks and Regards,
Amol Rathore

What I have under stood from your BOM is -
Level    Item       ProcType   SpKey          Vendor                
1          FA         F               30                A005
1.1       SA1       F               30                D025
1.2       SA2       F               30                A005
1.1.1    C1          F                                  Some Vendor
1.1.2    C3          F                                  Some Vendor
1.2.1    C1          F                                  Some Vendor
1.2.2    C2          F                                  Some Vendor
Please clear whether this BOM is correct or not?
cheers
kapil

Similar Messages

  • Please help with subcontracting scenario............

    Hi All,
    Can anyone please help me in dealing with subcontracting scenario with scrap taken into account. Please provide the screen shots from BOm creatio to challan closing. the requirement is urgent. please help me. all replies will be suitablly rewarded.
    regards,
    vvr sharma

    Sub Contracting Cycle
    (1) You have a material that can be procured externally, and you have maintained BOM with components. Any waste generated and received during subcontracting process can be maintained as component with negative quantity. 
    (2) You create a subcontracting PO (PO with Item Category L). You can also maintain Purchase Info Record for Subcontract category for material and subcontractor. 
    (3) You make a transfer posting to issue components for SC PO. Material is sent to subcontractor.  As material remains under your ownership, system does not make any value entry. But quantity is shown as "Material Provided to Vendor" 
    (4) You receive finished material against SC-PO. You also specify components consumed in manufacturing of finished goods. Additionally, if you have negative components in BOM, now you'll also receive subcontracting by-products. There are three events, so three accounting entries are generated: 
    DR FG Stock/ SC By-Product Stock 
    CR Change in Stock (FG/ SC By-Product ) 
    (for finished goods received) 
    DR Subcontracting Charges 
    CR GR/IR Clg 
    (for moneys payable to Subcontractor) 
    DR Consumption (Components) 
    CR Change in Stock (FG/ SC By-Product ) 
    (material provided to Vendor is now charged to expense) 
    (5) You do the IV for SC Invoice, and the process is complete. 
    Process of Subcontract in MM
    Sub-contract business process: 
    You want to buy material from the supplier (processed material/ assembled item) , but for some reason (quality of certain item / price ) you will give some component to vendor . 
    Vendor shall process the item / use the item provided & supply the final item. 
    SAP process: 
    1.Create the finished goods material code. 
    2.Maintain the BOM for the material. 
    3.Create PO with item category as "L" . 
    4.Issue material to vendor with movement type 541 
    5.Receive the material against the PO with movement type 101. 
    6.MIRO to account for vendor's invoice for the service charge& material used by him. 
    Can anybody tell me how a process has to be given to subcontracting?
    Suppose, I have 3 operations  1)weaving 2)dyeing 3)cutting & packing 
    if no 2 process (i.e Dyeing) has to be given to subcontracting, what process should i follow ?
    The following process to be followed for subcontracting. 
    1. Item code(material master) to be created at the stage of before dyeing. 
    2. Item code(material master) to be created after Dyeing as subcontracted item.(F30) 
    3. Bill of material to becreated for the material(2) calling for material(1) 
    4. Inforecord and source list to be created for material(2) with the corresponding vendor 
    5. PO to be released for material (2) 
    6.Along with PO the material(1) to be issued to vendor 
    7.On receipt of material when GR is made the stock with vendor will get updated. 
    How to Create a Subcontract Order?
    To create a subcontract order, proceed as follows: 
    Enter the material you want to order and the item category for subcontracting (L) in the order item. 
    Press ENTER to display the screen for component processing. 
    Enter the components that the vendor requires to manufacture the product. 
    Please note: 
    – You do not need to enter the date required for the components. This date is proposed by the system when you press ENTER. 
    It is calculated as follows:
    Delivery date of the item - Planned delivery time
    – If you do not want the quantity of the components to be changed if the order quantity of the end product is altered, set the indicator Fixed quantity (column F). 
    – You can determine whether the components are available on the date required by selecting Edit -> Availability check. 
    If you entered a bill of material as the material in the subcontract order, the components are created automatically. 
    If you want to determine the components in the bill of material at a later date (for example, if the bill of material is subsequently changed), choose Item -> Component -> New BOM explosion. The existing components are deleted and redetermined in the bill of material. 
    Save the purchase order. 
    When you print the purchase order, the components are printed per order item
    Subcontracting - Key Points
    Special Procurement Process.
    Item category: L
    Order type: NB
    In info record vendor should be maintained as subcontractor.
    Vendor (Subcontractor) receives the components used to manufacture a finished product directly from your company or through third party.
    Your company should place a purchase order for the finished product.   In this manually you can enter the required individual components or it can be determined via the explosion of BOM (if exists).
    Stock check at vendor level: ME2O
    Company stock check: MMBE
    GR for individual components through movement type: 501 or 561 (if with out PO or without reference).
    GI to subcontracting vendor: through movement type 541.
    GR from sub contracting vendor: through movement type: 101
    Movement type 543 is displayed to cancel the material cost account.
    If the subcontracting order has to be generated through materials planning,the special procurement key has to be set in MRP 2 screen.
    - To create the Subcon Info Record : Tcode ME11 - Info Category - Click Subcontracting
    - To create Material BOM : Tcode CS01
    - With the Info and Material Setup, you can then create the Purchase Order in Tcode ME21N
    Hope this is helpful.
    Regards
    Ravi

  • MRP with subcontractor stock

    Hi SAP Experts,
    I have a question about MRP.
    Can we work MRP with subcontractor stock?
    Let me explain, the MRP could not to generate new planning orders if I have subcontractor stock. For example:
    In MD04 transaction
    MtlRes 100- units
    MtlRes 100- units
    MtlRes 100- units
    SubcSt 300 units
    If I have this situation, the MRP run could not to generate planning orders because the subcontractor stock recover the quantity.
    This problem (almost) drive me crazy. I really appreciate any help.
    Thanks in advance.

    Dear Demetrio                                                                               
    Please note that the logic for subcontracting was changed as of release   
    4.0A.                                                                     
    As of release 4.0 the net requirements calculation for components to be   
    provided in subcontracting takes into account that the provision stock    
    can only be used to cover the corresponding requirement of material       
    provided. The provision stock that is already available from a            
    subcontractor (vendor) can only therefore be used to cover the            
    requirements of material provided at this subcontractor.                                                                               
    The system uses only the stock that has not been assigned to a            
    subcontractor as unrestricted-use stock to cover all requirements.                                                                               
    For further information about this issue please consider the below QA. With the modification of note 170597 the old logic can be achieved. Please notice that it is a modification note.
    1. Question
    Why does the MD04/MD05 display an own segment for subcontracting as of Release 4.0B and how does the materials planning work with this new logic?
    Answer
    The logic regarding the subcontracting was changed as of 4.0. This is explained in detail in the release notes for 4.0A:Planning of the components to be provided for subcontracting
    Material Requirements Planning -> Planning Execution -> Material Requirements Planning: Planning of the components to be provided for subcontracting
    2. Question
    Why does the third-party order processing for subcontracting work differently as of Release 4.0B?
    Answer
    The (Pseudo) Third-Party Order Processing for parts provided together with the own segment for subcontracting results in problems and can result in inconsistencies. This is described in detail in Note 214298.
    As of Release 4.5A you can implement the third-party order processing with subcontracting MRP areas (refer to the corresponding documentation).In addition you can use a modification to reset the system to the behavior before 4.0A, refer to Note 388479. As of Release 4.7, BAdI 'MD_SUBCONT_LOGIC' allows this without a modification.
    3. Question
    Why does the discontinued part for subcontracting not work?
    Answer
    You cannot divert requirements of material provided to the follow-up material. The reasons are described in detail in Note 43636, section 6.
    4. Question
    Why does the system not display the requirements of material provided in the storage location MRP area, as expected?
    Answer
    Requirements of material provided (subcontracting requirements, material staging requirements) never reach a storage location MRP area, because later you cannot post the withdrawal from this MRP area.
    The withdrawal of the components (to be provided) during the goods receipt for an SC procurement proposal occurs always from the stock with subcontractor, which is managed - from the viewpoint of the inventory management - on plant level and has no storage location reference.Refer to Note 503497 for details.
    5. Question
    Why does a requirement move from the subcontractor segment into the plant segment and is covered there although it appears already to be covered in the subcontractor operation segment by a receipt element (Pseudo third-party order processing for the subcontractor)?
    Answer
    The corresponding receipt element must standardly always be within the rescheduling horizon. This is required (due to technical reasons) even then when the input itself does not have to be rescheduled, so that the net invoice can deliver consistent results for the subcontractor segment together with the rescheduling check.
    If the receipt element occurs after the requirements date, the corresponding element must participate in the rescheduling check (Transaction OMDW).
    Regards
    Soundar

  • MTO - make to order with subcontracting

    Hi Gurus,
    i have a question . I want to realize a process MTO with Subcontracting
    Could you tell me how can i customize this process?
    Best Regards
    Emre

    u2022     Create material in MM01
    u2022     Create BOM in CS01
    u2022     Have routing in CA01
    u2022     Create sale order in VA01
    u2022     MRP Run in MD50
    u2022     Check planned orders in MD04
    u2022     Convert component planned order to PR
    u2022     Convert component PR into PO for external procurement in ME21N
    u2022     Create subcontract PO with reference to PR via ME21N
    u2022     Transfer goods to subcontractor with movement type 311E
    u2022     Create excise challan J1IFQ
    u2022     Receive the goods from subcontractor via MIGO
    u2022     Execute J1IFQ for reconciliation
    u2022     Update the challan via J1IF13
    u2022     Convert finished material planned order to production order
    u2022     Issue to production with movement type 261 via MB1B
    u2022     Confirm production order via CO15
    u2022     Receive goods against production order
    u2022     Order settlement for production order in KO88
    u2022     Create delivery in VL01N
    u2022     Create billing document in VF01 / VF04
    thanks
    G. Lakshmipathi

  • Each time I start Firefox it says: "URGENT! Your version of Firefox is no longer protected against online attacks. Get the upgrade - it's fast and free!" I am using ver. 3.6.13 and upgrading "successfully" only stays on 3.6.13 with same URGENT message.

    Each time I start Firefox it says:
    "URGENT! Your version of Firefox is no longer protected against online attacks. Get the upgrade - it’s fast and free!"
    I am using ver. 3.6.13 and upgrading "successfully" only stays on 3.6.13 with same URGENT message.

    Your UserAgent string in Firefox is messed up and needs to be reset. <br />
    [http://en.wikipedia.org/wiki/User_Agent]
    type '''about:config''' in the URL bar and hit Enter <br />
    ''If you see the warning, you can confirm that you want to access that page.'' <br />
    Filter ='''general.useragent.''' <br />
    Right-click the preferences that are '''bold''', one line at a time, and select ''' ''Reset'' ''', <br />
    Then restart Firefox

  • MRP with Inventory module and not Warehouse module

    Hello,
        We have a very simple inventory and phsical warehouse. We do not need the Warehouse Module with it's complexities, but we would still like to run an MRP to generate Purchase Reqs, etc.
        Does anyone know if we can have MRP with no Warehouse Module?
             regards

    Bill
    Welcome to SDN
    The answer is Yes. You could run MRP without warehouse module implementing. As you know MRP is based on planning of materials.
    Hope this helps
    Thnaks
    sat

  • Without MRP, with BOM explosion

    Hi,
    I'm new to SAP and learning SAP SCM. I would like someone to brief me on what the following lines imply, especially 'without MRP, with BOM explosion'.
    "dependent requirements must be determined for materials that are planned in SAP ECC. So, you assign the MRP type “X0” with MRP procedure “X” (“without MRP, with BOM explosion”) to the materials planned in SAP SCM."
    Thanks,
    Krish

    Hi,
    Without MRP , with BOM explosion - means the dependent requiremens are created for this materials from APO.
    The MRP will not run in APO. Only the dependent requirements will be created from APO. The MRP for this materials will be executed the ECC or R/3 system to create planned order anb purchase requisitions.
    Thanks and regards
    Murugesan

  • MRP with LOT SIZE as "MB"(Monthly Lot Size)

    Dear All
    When I am Running MRP with  LOT SIZE  as "MB"  (Monthly Lot Size)
    System Is raising Planned Order,
    My requirement is instead of Planned Orders I need system to raise Purchase Requisition
    Regards
    Chaitanya

    Hello ,
    It is because of the procurement type "X" in MRP 2 view of material master . IF you change it to "F" , your problem will be solved
    Regards
    Ramesh

  • Scheduling agreement with Subcontracted material

    Hello Gurus,
    There is scheduling agreement with subcontracted material.
    While maintaining the schdule with ME38  , I want to make the warning message of "Please create components"   ME114 as error message.  I went into configuration and set this message as " E" . But still while maintaining the schdule with ME38 , I am getting this message as Warning only and not error message.
    I would like to know is there any other setting other what i did?
    Please help me
    Thanks in advance

    Thank you for your reply.
    By going into the T code OBMSG , and doing the needful config., still result is not achieved.
    Please guide

  • Third party sales along with subcontracting.

    Dear Experts,
    Currently in our company we are having a scenario for third party sales along with subcontracting. the scenario is as explained under.
    Company
    A                                   B                                  C, D, E (vendors)
    A raises a PO to B for the purpose of procurement of material X and services Y .
    B generates a Sales Order against A's PO and performs procurement of material X
    from vendor C. C delivers the goods directly to A and invoices B.
    Now here the requirement is that material X is common in company A & B and I need to maintain
    the consumption and valuation of material X in both company codes.
    How is this done.
    In context to the above scenario;
    Now the material which has been delivered by company C (vendor) to Company A;
    again this company A gives the same material X (which now becomes raw material or spares)
    to B as free issue  for the purpose of project.
    Through normal Third Party sales order created in company B; the system issues me the following message

    Hi,
    Actually the scenario is that company A & B both are different but wish to interface their operations
    in order to achieve speedy transactions. If both were under same company umbrella then intercompany would have been possible. But in this case these are two different companies all together.
    thank you for your response.
    Regards
    Vivek
    Edited by: Vivek A. Chokshi on Jan 9, 2009 6:09 PM

  • How to Run MRP with requirement Plan Number

    Dear all,
    I am working for the process of MRP Run .But customer requirement is that "To Run the MRP with requirement Plan Number"
    If you are aware of this scenario ,please provide the solution.
    Thanksin Advance

    Go to MD61
    Select the Radio Button Rqt Plan Number
    Write the plan number eg. "test1"
    now you get the next screen
    Here you can enter the materials like
    first line Testmat1 -qty 100   150 ....
    2nd line Testmat2 -qty 150    100
    like that
    So the difference between MD61 with Material and Rqt Plan number is
    Material means we give requirement for only one material
    But for Requirment plan number , w.r.t one Rqt Plan number we can maintain requirement for multiple material
    same material with same period we can maintain requitement for Different Requirement Plan number
    This is reducing effort of client of data entry and for different sales Regions for the same material through "Rqt Plan No" they can differentiate the rqt
    MRP run run it for PLANT or multiple plant with Scope of Planning
    thanks
    Pl award points if useful
    K.Prabakaran

  • Posting invoice for SC order with freight - URGENT!

    Hi,
    I'm getting differences in accounts for invoice only for freight with subcontract order.
    I should get this lines in invoice for an invoice more expensive than the previous GR (let's forget taxes by now):
    KBS total of invoice
    FR1 in the amount expected by GR
    FRE for the additional payment
    BSX to value the stock according to fre
    BSV to clear fre
    all FRE, BSX and BSV should be the same, but they aren't. FRE is greater than BSV that is the same than BSX.
    Do you have any clues?
    Regards.

    This is being adressed by SAP development team for canadian provinces taxation.

  • MRP with account assignment

    any one can clear my doubt. I can run MRP with item category( ex L, B, K etc). but i don't know how to run MRP with aaccount assignment ( ex with K, P, Q etc)

    Hi,
    You can run MRP for your material but it won't calculate with PO with account assignemnt since the goods received against that PO won't be kept in stock - MRP calculate with stock levels.
    BR
    Csab

  • MRP areas with subcontracting

    Hi,
    Details:
    1) we have BOM like A is the finished product and under A -B and C are the compnents.
    2) we have created the mrp areas and assigned in the materials master for all the materials.
    and   created the  purchasing info records as well.
    B and C will be procure from from vendor1 and will supply to vendor 2.
    Vendor2 will use  the B and C materialsand to make the Finished material A and supplies to plant.
    So i defined subcontracting for A material.
    I have created the scheduling aggrement for B and C material with Vendor1 and A with vendor2.
    After MRP run schedule lines are creating for B and C materials only and PRs is creating for A material in place of schedule lines.
    To create the schedule lines for A material is there any config settings to be done.
    My requirement is schedule lines to be created for A,B and C materials.
    Suggest me how to solve run the scenerio.
    Waiting for responce.
    Thanks
    Chindam

    Hi Chindam,
                      Check whether you had maintained source list if so the schedule lines will be created automatically when trigger a MRP run.
    regards,
    patil

  • MRP for subcontracting

    hi thr ,
    here we r using planing strategy 10 .we have BOM like HALB A conatains ROH B
    and that ROH B is send outsidefor subcontracting for cutting operation .
    when i am taking planning run it is not generating DepReq for ROH B .
    i have maintained spl procurement key 30 in HALB A in MRP 2 view .
    why it not linking the ROH material .
    and what r the setting to be mainatained for such scenario .
    routing for the HALB contains only one operation Cutting and we have maintained PUR info record in the Routing for the same .
    plz guide for the same above .

    Ajay,
    Routing is not required as you are subcontracting HALB A (as mentioned by you only one operation representing external processing).
    1. Maintain HALB A - Special Procurement - F & 30
    2. Maintain BOM for HALB A with usage 1 - Production and status relevant for all. See that your BOM is within the valid date range of the required date. Here component ROH B should be assigned.
    3. Maintain Inforecord of Subcontracting type for HALB A.
    With this run MRP you should get Subcontract Req generated for ROH B.
    In your present case you have maintained external operation, which will get triggered only during creating/release of Production order. I think you will be having a planned order only for HALB A, please convert it into production/process order and check, then system will create subcontract requirement.
    Regards,
    Prasobh