MRS  Auto Scheduling  Network Order

Has any one in the forum implemented or know how to achieve Automatic Scheduling of Demand  (Network Order/ Network Activity ) created through PS (Project Systems) in the MRS tool. ?  Using Service Orders, this is a configurable item, with a BAdI for changes if necessary. But this does not apply to Network Orders. I am considering various options, but would like to know if this could be done without modifying an SAP standard program. Options tried out include calling FM ; /MRSS/API_ASSIGNMENT_CRE,  this however fails to  assign the demand in the planning board, although it would assign demand in debug mode. I have equally tried  Recoding and creating a BDC, but the Resource fields are not captured in the recording.  Any hint would serve.
Regards
Oppress

Have you tried automatic scheduling on the network itself?  In PS you can configure the network to auto schedule if the dates are changed.  You may find that making changes to the dates in the network from MRS causes the network to reschedule itself.
mike

Similar Messages

  • ATO Model -Auto Scheduling

    If you closely see ,The Auto scheduling for the ATO Models are not supported by oracle .
    Once you configure the item using configurator and click on finish ,When it returns to OM ,I expected the Schedule ship dates populated ,But this did not happen
    anyone faced the same issue ? have done workaround etc ?

    It is supported by Oracle.
    Check if "OM: Autoschedule" profile option is set.
    If not, check if the transaction type setup for auto-schedule or you have set the autoschedule selection to Yes or No via Tools > Autoschedule in the Order Management entry form.
    Hope this helps,
    Sandeep Gandhi

  • Auto schedule pick an instrument multiple dmm

    hi
    I am trying to use the test stand auto scheduler
    I have a test setup with 2 DMMs of the same model. I don't really mind which DMM I use for measuring a voltage since they will be connected to the DUT via a matrix switch.
    I have written a sequence which will be re-used over and over on multiple DUTs and it requires access to a DMM.
    Can test stand automatically pick a free DMM and switch it through to the test point I need? or do I need to specify which DMM I want to use?
    Any ideas?

    A lot of these questions will become answered as you become more familiar with TestStand.
    However, let me see if I can try to answer them here:
    Each VI is set up to call the different DMMs.  So that is not a problem.  The key is knowing which one to call.  This is done using the Preconditions and Pre Expressions for each of the steps.  You can see that the preconditions are set to look at the acquired resource.  This way you know which step to call.  Also you could set the switching for those steps to use the correct paths through you switch matrix as well.  This is where it gets tricky though because you have to make sure that a path for DMM1 will never conflict with a path for DMM2.  Because if they do then you cannot have 2 DMMs.
    If you look at the Use Auto Scheduled Resource step for the DMM section you will notice that it identifies 2 resources.  By the very nature of how autoscheduling works when you declare 2 like that only 1 has to be used in order for that testsocket to satisfy that section.  Any of the resources scheduled in the auto scheduler are actually "soft" resources.  This means that they just exist in software.  Even though you have hardware physically out there the soft resources are just used to lock so threads don't tromp on each other. 
    TestStand knows that the DMM is available because another thread has released that soft resource.  And then the testsocket just grabs whichever one is available.
    The NI TestStand Reference Manual should help you out.  There is a section on page B-25 which talks about Auto Scheduling.
    Also, not sure if this example helps out either:
    http://zone.ni.com/devzone/cda/epd/p/id/6528
    Hopefully this helps.   It's kinda hard to explain I wish there was more documentation out there for this.
    Let me know if you still need further clarification.
    jigg
    CTA, CLA
    teststandhelp.com
    ~Will work for kudos and/or BBQ~

  • Delivery date calculation in auto scheduling

    Dear All,
    We have maintained planned delivery time , gr processing time in mm master as well infor records.
    We are running MRP and auto scheduling and updating schedule lines through MRP.
    System updating schedule lines and the delivery date also. what is calculation of delivery date in this case ?
    also system updating 3 lines with different delivery date ..why ? why not one line ?
    vijay

    no solution.

  • Auto Create service order from incoming email

    Hi,
    We have a requirement that we want to create service order with a default transaction type automatically from an incoming email. Also we want to route this service order to a specific service group on creation an above.
    How can we handle this? I know we can create a rule policy with an action to auto create a service order. My question is how do we set up that this service order is of a particular transaction type and has the default routing to the specific service group..
    Thanks
    Dan

    Hello Dan,
    You can specify the transaction type (for ERMS auto-created Service Orders/Tickets) via IMG configuration. In transaction CRMC_ERMS_SM_PROF you select the DEFAULT service manager profile and open the folder "Indirectly Called Services". Then you can specify the transaction type for each of the relevant service IDs: AH_CREATE_SO and AH_CREATE_SR.
    Best regards,
    John

  • Running a Batch File using Auto Scheduler in HFM?

    Hi,
    Can we execute a batch file or run a macro or execute a VB script using the auto scheduler in Task Automation in HFM??
    Abhishek
    Edited by: user10378700 on Sep 30, 2008 7:18 AM

    I'm having difficulty running a batch script the way you describe.
    One line of code in c:\test.bat:
    echo Hello >c:\test.log
    This works just fine.
    However, for the life of me I cannot get this to work through Task Automation.
    I have the Application as Hub.
    The Action as Execute.
    The Command as c:\test.bat.
    When I select the task and click on Run Now, I get a message that the taskflow has initiated successfully. However, nothing fires on the server. I cannot see this process in Running Tasks (it would run quickly).
    Any hints?
    I have not found this subject to be...overdocumented.
    Regards,
    Cameron Lackpour

  • Problem: Scheduling Process Orders.

    Hi,
    I have a problem in PPPI with scheduling in Master recipe and with the process order in CM25. Can you help me?
    In Master Recipe:
    I create a capacity category 0025 to display for a resource the setup formula and Processing formula in the Scheduling Tab (as the capacity category 0001 - I also tried to let the capacity category 0001 be used in application C - Master recipe and didn´t work).
    In OP40, I created and assigned in applications to C Recipes
    Afterwards, I ordered the views in OP13.
    When im creating a resource, i prove the formula and i have no problem. But when I assigned it to the recipe and the recipe to the production version to make a process order, neither the master recipe or process order schedules the order.
    When I create a resource with a capacity category 0008 (standard) the scheduling works just fine in the process order.
    Scheduling in CM25:
    Also when Im trying to schedule the order in CM25, I see two lines of the same order (i guess are the 2 phases 0010 and 0020), is there anyway to just see the second to avoid misunderstanding?
    Thanks in advance!
    AM

    Dear,
    For FIFO you can use the Characteristic  LOBM_LFDAT for FIFO if is LOBM_VFDAT then in plant storage data 1 view maintain the SELD then assign these Characteristic to class in CL02 then assign this calss to material master.
    Then craete sort rule in CU70 withCharacteristic  LOBM_LFDAT or LOBM_VFDAT
    then assign it to serch strategy in MBC1 or COB1 with selction criatoria.
    In OPL8 assign this serch procedure.
    Then create the order and check the result.
    Regards,
    R.Brahmankar

  • Problem with scheduling planned orders in MRP

    There is a problem with scheduling planned orders in MRP. SFG is assigned to the BOM of FG. No inhouse production time maintained in the material master of SFG & FG. routing maintained for both . In OPU5 scheduling & capacity reuiremnts tickmarked for detailed scheduling. Scheduling level - via detaied scheduling. Scheduling type - backward. Adjust basic dates , adjust dep. req. to order start set. In MD02 , scheduling is via ' lead time scheduling'.
    My problem is the start date & time & finish date & time is same for planned orders of FG & SFG in the detailed scheduling tab of the planned orders. (Duration is same because of same capacity requirements on the same work centre. But how is the finish date same for both SFG & FG?)
    (Capacity requirements are being generated.)
    What could be the problem ?

    Dear,
    By scheduling the routing and maintain lot size dependent time in material is best practice and result of scheduling will be consistent.
    If you want SFG before FG you need to define lead time offset in BOM or need to maintain the floats before production.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • How to delete Open/WIP Projects/Network Orders/WBSes using program PSARCHP1

    Hi,
    We have multiple open or WIP projects/Network orders. Program PSARCHP1 is used for this purpose. Can anybody suggest how to delete all these projects/networks that are open/WIP.
    Regards,
    Rakesh Kumar

    I think it's not possible to remove for the data base in sap. However you can delete the records for the tables which is not suggetable. which server do you want to do this??
    if developement yes you can delete the table records.
    As per my experiance we should not delete the table records because it's linked many tables and diff modules in sap.
    I hope it's help ful.
    give the points.
    Regards,
    Raman

  • Bapi or RFC for Scheduled production orders?

    Hi experts,
    I need to extract a list of the Scheduled production orders (for a specific plant)for integration purpose. Does anyone know if there is any BAPI or RFC for this purpose and could anyone tell me which one could be used.
    I noted that a similar topic "Retrieving production orders and material stock out R/3 system" posted Jan 16, 2006 has been discussed but the outcome was only that standard BAPI / RFC should be available for retrieving the production orders but there was no BAPI or RFC mentioned.
    Best regards,
    Niklas

    Hi,
    I found that the following BAPIs can be used with some parameters.
    BAPI_PRODORD_GET_LIST
    BAPI_PRODORD_GET_DETAIL
    Thanks
    Pavan

  • CN22 - Print Shop Floor Papers for Network Orders

    Hi All,
    We are printing shop floor papers for network orders - the printers are setup, configuration is working fine.
    However, there is a sporadic error: when we select "Print" and then "Save" in CN22, the system pops up a window with the list of all network activities. However, for some reason, the first time this is done, only a few network activities appear on the list. If we close the pop up, then select "Print" and then "Save" again, the whole list appears. Has anyone encountered this before? I looked through OSS, but couldn't tell if any of the notes would be applicable to resolve the issue.

    Hi,
    I just went through the same problem. Don't know if it is still open.
    In customizing under "Project System"->"Structures"->"Operative Structures"->"Network"->"Printing in Networks" you will find entry "Recommendations for printing and print control". There it is stated that the number of time tickets or number of confirmation slips entered for the activity is greater than zero.
    Check in transaction OPS0 if you have set the number of prints greater than zero in menu point "List control for transactions (double clic on the entry).

  • Manual reservation creation for Network order

    Hi ,
    I am trying to create manual reservation (MB21) for network (movement type 281), I am getting error message "Manual reservation for order category 20 is not allowed".  Whether it is possible to create manual reservation for network order by any other way or by config change?

    Dear,
    Check : OSS notes 305231 and 43924
    Also check: http://www.sapfans.com/forums/viewtopic.php?f=8&t=37714
    Regards,
    Syed Hussain.

  • Auto Scheduling

    Hi Guys,
    Auto Scheduling in PP, did any one came across this?

    Hi,
      In scheduling, the system determines start and finish dates for the procurement elements of materials that are produced in-house and for materials that are procured externally.
      Go thro this link .This may help u...
    http://help.sap.com/saphelp_47x200/helpdata/en/f4/7d3f9344af11d182b40000e829fbfe/frameset.htm
    - Thaila Shree

  • URGENT: API to Schedule Sales Order Line

    Hi,
    Could anybody share me API to schedule sales order line? Actuaaly I need to release sales order by API but first need to do scheduling for lines.
    Thanks,

    Hi;
    Please check Hussein Sawwan greatest post about similar topic:
    API
    Fixed Asset API
    please also check:
    Api's in EBS
    Re: Api's in EBS
    http://sairamgoudmalla.blogspot.com/2009/05/script-to-find-oracle-apis-for-any.html
    Hope it helps
    Regard
    Helios

  • ICal server set auto schedule for users

    Does anyone know how or if it's possible to set the auto accept state for a user?
    Using calendarservermanageprincipals you can do it for locations for example and you can --get-auto-schedule for a user, but when you try to --set-auto-schedule for a user it says it's not allowed. Anyone know of a workaround or if it's possible?
    --sysdev

    Nevermind, figured it out. you can manually edit the database these values are set in. /CalendarServer/Data/resourceinfo.sqlite

Maybe you are looking for

  • Word 2013 and documents with more than 400 pages

    Hi, we have the Problem that Word 2013 need terrible long to load or save documents with a large number of pages (>400). Ther are no Images or Links inside the document nor are there references to any templates. The File size is not so large, its abo

  • Open in Organizer View?

    I seem to remember something in Photoshop Elements 3.0 or before, where one could set a preference or something to have the program always open in Organizer view (or Editing view, if one preferred). Is there something like that in Elements 4.0? (Some

  • Illustrator PDF saving as an InDesign PDF

    Strange... I have CS5.  Just recently, when I try to save an AI document as a PDF, it looks like everything works correctly, but the resulting icon on my desktop shows ID (pdf).  When I click on it, it says InDesign can not open the document because

  • Why does Photoshop Lightroom keep crashing and never opens?

    I downloaded the latest version of LIghtroom, but when I try to open it, it crashes. It starts to open with opening with the yellow aspen photo, but it immediately crashes. I have tried it several times. Any help out there? Thanks.

  • Database Career Questionnaire

    I'm doing a survey for a school research project on the database career field. It would greatly help me if someone in the field would take the time to answer the following (very basic) questions. 1. What is your name? 2. Please describe your job titl