Hi Gurus,
i have a question . I want to realize a process MTO with Subcontracting
Could you tell me how can i customize this process?
Best Regards
Emre

u2022     Create material in MM01
u2022     Create BOM in CS01
u2022     Have routing in CA01
u2022     Create sale order in VA01
u2022     MRP Run in MD50
u2022     Check planned orders in MD04
u2022     Convert component planned order to PR
u2022     Convert component PR into PO for external procurement in ME21N
u2022     Create subcontract PO with reference to PR via ME21N
u2022     Transfer goods to subcontractor with movement type 311E
u2022     Create excise challan J1IFQ
u2022     Receive the goods from subcontractor via MIGO
u2022     Execute J1IFQ for reconciliation
u2022     Update the challan via J1IF13
u2022     Convert finished material planned order to production order
u2022     Issue to production with movement type 261 via MB1B
u2022     Confirm production order via CO15
u2022     Receive goods against production order
u2022     Order settlement for production order in KO88
u2022     Create delivery in VL01N
u2022     Create billing document in VF01 / VF04
thanks
G. Lakshmipathi

Similar Messages

  • Is it possible to make an order with danish keyboard and documentation

    Hallo
    I need a computer with danish keyboard so my question is
    Is it possible to make an order with danish keyboard and documentation
    Jesper Nielsen

    You can give each track its own artwork. iTunes will normally display the artwork of track 1 in album listings. The individual track art will show in the small window at the top of the screen when playing, or the artwork panel of the mini player, or the now playing window on a device. Try it and see.
    tt2

  • Make To Order With Credit Check.......

    Dear Expert,
    Could i know about Automatic Credit Check-Static and Make to Order with Credit Check...
    Thanking you,

    hi
    in simple credit check it considers only the current sales order with the value assigned to the customer
    but in automatic credit check we have two types
    1. Static: it compares the value assigned to the customer with the value of open sales orders + value of open delivery documents + value of open billing documents + value of billing doc's posted into accounting but for which we have not recieved the payment..
    2. Dynamic : the way of calculation is the same as static but the difference is we have horizon in dynamic credit check
    Example:  in static all the open doc's will be considered for credit check
    but in dynamic if i give the horizon as 2 months
    sales orders for which the delivery date falls after two months will not be considered
    similarly delivery doc's whose billing date is after 2 months will not be considered..
    etc
    even though its a make to order it will be processed using doc type OR
    you assing the credit group to the sales doc
    that is suffecient
    hope this helps
    regards
    ravi

  • Make-to order with production in alternative plant

    Hi,
    We are thinking about implementing a scenario with Make-to Order production for our products, but with production in alternative plant (special procurement type 80).
    For example, sales orders will be directed to plant A, but production should take place in plant B - and using a make-to order strategy (in our case planning strategy 50 - planning without final assembly).
    Is there any problems with our approach, making it not feasible to implement? Is it even possible in SAP to combine MTO with special procurement key 80 (production in alternative plant)?
    Is there any other issues that can be foreseen with using this type of production strategy?
    Thanks in advance,
    Lars

    Hi,
    The production strategy which you are going to use is very fine.
    As per me there is one concern. Example you have created a sales order in Plnat A, in plant A that FG is handling through Special procurement 80, then in the MRP run system will be creating a planned order in Plant B without running MRP in plant B. In MD04 screen you can see planning plant as Plant A. In plant B, u r converting this planned order in to Production order and executing the production. While doing the GR against the production order, the goods receipt will happen directly in Plant A.
    This is the one problem (Accountability)  you can face.
    Regards,
    V. Suresh

  • Make to order with Prod version with object depedency

    I m using 2 production version. In both case BOM & Routing having object dependency. Its make to order scenario. How can I select prod version in costing as well in configuration in sales order. Because by default its taking first version for both configuration & costing.How??
    And if I select second version in sales order, in prod order it should automatically take second version. How??
    Thanks
    varun

    Hello Varun,
    If you have two valid production versions for a part then by default system take the first available production version. You have give some selection criteria through quota arrangement.
    In ck11n you have the option for selecting the vesion in the quantity structure tab so i think there will be no problem for costing.
    For selection of production version in the production order you have work with planning strategy 82. Or incase of MTO (strategy 20) run MRP from MD50...your assigned production version in sales order will be planned.
    If helpful rewards your points
    Regards
    TAJUDDIN

  • MTO(Make to Order) SD Configuration

    Hi ,
    Our client want to implement Make to Order scenario.
    Can anyone pl guide about the configuration required in SD?
    Thanks in advance.
    Pallavi

    Hi,
    1) You need to have a material with item category group 0001 = MTO (Normal Item)
          In MM01, basic data tab, Gen.Item category field 0001= MTO , 0002 for configurable material
    2) In MTO availability check - checking group is 02 (individual requirement) in General/Plant tab.
    3) Create an order VA01 there you will see item category as TAK, schedule line as CP, and requirement type as KE
         In VOV7 TAK  Billing relavence is A and pricing is X.
         In VOV6 for CP the movement type is 601
    4) MB1C to initialize the stock with special stock indicator E (means 561E)
    5) MMBE to check the stock if it has been created or not.
    Lastly do the delivery picking and billing.
    Regards,
    Sridhar

  • Individual purchase order with subcontracting material

    Hi all,
    I've implemented a individual purchase order in a sale order by means of 'TAB' category item. The material has been set as 'subcontracting'.
    When I create the sale order, a purchase requisition is automatically created with M imputation and special stock 'E'.
    Once I create, the purchase order with reference to purchase requisition, I set 'L' category item. Then I save the purchase order.
    In order to simplify the flowchart, the vendor has enough stock to manufacture the required material.
    Then, Tx. MIGO, stock input with reference to purchase order.
    For the FERT material --> movement 101 E + is set.
    For the component --> movement 121 E - is set.
    How can I obtain 121 'O' - movement for components in order to decrease SC vendor stock?
    Thank you very much in advance for your support.
    Best regards,
    Alberto Ramos.

    Dear Charlie,
    Thank you very much for your response. As you comment, I made a mistake with the number of movement. Certainly the movement for raw material consumption is 543.
    I have executed the flowchart you describe. In your case, an independent subcontracting purchase order is done. This flowchart works correctly (with the results you comment. Actually the raw consumption are related to mov. 543 O -).
    The problem is when purchse order is related to a sales order. That is:
    1. Sale order TA with only one position material A. Category item 'TAB'.
    2. Material master for material A --> MRP 2 view --> Special procurement field: 30 - Subcontracting
    3. An automatic purchase requisition is created (thanks to 'TAB' category item, schedule line, ...)
    4. Tx. ME21N --> I create a purchase order with reference purchase requisition:
        4.1. Account assignment category field is set to 'M' from sales order / purchse requisition
        4.2. I manually set Item category field to 'L' for indicating subcontracting (I don't force this to be 'L' from sales order / purchase requisition because I need to use the same flowchart for subcontracting and not subcontracting materials)
    5. Tx. MIGO
        5.1. For Fert material the system executes mov. 101 E +  (as in your description)
        5.2. For raw materials the system exectures mov. 543 E - ( instead of 543 O -). I would like to obtain the reduction of subcontracting stock, because this material is in my center but povided to SC manufacturer.
    Should I do a 'Subsequent adjustment' by means of Tx. MIGO the movement are:
      - FERT material 121 E - (depending on adjustment)
      - Raw materials 543 E - (again 'E' instead of 'O' which is the result I would like to obtain).
    I will very much appreciate your comments.
    Thank you again,

  • Make-to-Order with Different Plant

    Hi Experts,
    I'd like to know how to implement business scenario of make-to-order but delivering plant (in Sales Order) is different with manufacturing plant (in Process Order). My client has material locking problem (huge batch records) so that my client wants to create new plant for delivering plant in order to minimize material locking problem. Is this scenario possible?
    I have set parameter 'Share Lock' but it does not work to solve material locking problem. Batch level is set in material level.
    Hope anyone can give me tricks or experience.
    Best regards,
    Heydarul Humam

    Hi,
         In OID2 -> In Application area O , For same order type assign different shop papers ..,
         After doing config in OID2 , In Application area O , these shop papers wil be be avaialble for assigning to planning plant, planner group in OID3 .. , here assign each of these shop papers to different planning plant ..,
    Now in IW32 system checks combination of order type to planning plant and defaults shop papers while printing ..
    Note :-  Here , If a particular shop paper is not assigned to an order type in OID2 , then u cannot default in printing via IW32 .for that order type and any planning plant ..
    check it up
    regrds
    pushpa

  • Make to order with jit

    dear all,
    I have heard this in most automobiles they yes make to order jit concept.
    what are the configurational changes that happen in this jit
    can somebody send differntn scenarios of pharma and automobile industry would be more useful

    hi
    in simple credit check it considers only the current sales order with the value assigned to the customer
    but in automatic credit check we have two types
    1. Static: it compares the value assigned to the customer with the value of open sales orders + value of open delivery documents + value of open billing documents + value of billing doc's posted into accounting but for which we have not recieved the payment..
    2. Dynamic : the way of calculation is the same as static but the difference is we have horizon in dynamic credit check
    Example:  in static all the open doc's will be considered for credit check
    but in dynamic if i give the horizon as 2 months
    sales orders for which the delivery date falls after two months will not be considered
    similarly delivery doc's whose billing date is after 2 months will not be considered..
    etc
    even though its a make to order it will be processed using doc type OR
    you assing the credit group to the sales doc
    that is suffecient
    hope this helps
    regards
    ravi

  • How to do The scenario of Make to order with inquiry and quotation?????????

    Dear All
    Now I am implementing a make to order scenario, what we have is a scenario described as below:
    The customer sends an inquiry to my client requesting a quotation for manufactures some goods then we have to check the cost and time to manufacture this goods then send him back a quotation so the customer can send the purchase order then I can start creating my sales order.
    I want the solution for that as I am not able to know the price in the inquiry stage so I am not able to send him a quotation as I donu2019t know the cost and the delivery time yet
    Thanks in advance
    Regards
    Jacopo Francoise

    Your steps are correct -- Please see (How to Modify or Create Notifications in Different Languages? [ID 1258834.1]) for details.
    For the NLS language, just type in the new language and see if you can view it properly (or save it to the database and see if you can view it from the application then).
    If the language is not set properly, you would get an error as the ones addressed in these docs.
    Error While Connecting To Database Using The Workflow Builder [ID 577905.1]
    Workflow Builder Cannot Load Objects From Applications when the NLS_LANG is Non-American [ID 179987.1]
    220:Unable To Set NLS_LANGUAGE Error In Workflow Builder [ID 728330.1]
    No Japanese Words In Oracle Workflow Even After Installing Asian Languages [ID 444067.1]
    Thanks,
    Hussein

  • How to make Sales Order with this condition

    Condition is as follows
    I have already sold an item say A to customer at Rs 30 lacs, INR. Now a new upgrade has been released say B costing Rs 50 lacs, INR. Now how to book Item B, with return of item A, and charge the customer who has already bought item A, only the differential amount, ie Rs 20 Lacs INR (Rs 50-30 Lacs, INR)
    Come back guys quickly.
    Regards
    Adarsh Krishna

    Hi Adarsh,
    Is this the new revision of Item A? then you can follow retrobilling. If this is a new item, then you have to book a new order and adjust the invoice.
    Steps for retrobilling:
    1) enable the retrobilling parameters in the system parameters
    2) Change the price list of the item A in the price list to the new price.
    3) go to retrobill workbench, reference the old order i.e shipped and you get a new order booked, now you can go and change the item here in the lines.
    You can receive the item A back through RMA.
    Pl try it out and let me know.
    Regards,
    Prasad

  • I would like to order prints of my albumns. How can I make one order with all the pictures II want

    I have an older version of Mac and iPhoto on my 3 year old desk top. I simply want to place an order for specific pictures within multiple albumns. all I seem to find is a way to order each picture indiviually. Am I missing something? thanks

    Make an album of the photos you want to order. Photos can be in multiple albums.
    Regards
    TD

  • Make to Order with assembly processing

    Hi, can anyone advise why the item category 'TAK' is greyed out if there's a production order linked to the item?  This is not the same if i hv a 'TAB' item cat where there's a PR linked to it.  Why izzit different?
    Thanks
    Peter

    MRP 4 view "2" was missing in individual/Collective reqmts.

  • Make to Order and Individual Purchase Order ( MTO & IPO)

    Hello Gurus,
    1. Can anyone let me know what is Make to order (MTO)and Individual purchase
        order (IPO) and the Differences between both?
    2.  What is the purpose of MTO and IPO and where it is used.
    I would be thankful if anyone can provide me the meaning of both.
    Prashant V.T (PVT)

    Hi Prashant,
    MTO : Make to Order means the Production of the Material starts after getting the sales Order.
    Means once the Sales Order raised for any particuler customer then based on that order production / procurement takes place, and the stock what ever produced will be restricted for that Order only. The Stock cant be used for any other orders.
    where as IPO is different.
    IPO : Individual Purchase Order is like Third Party Sales but with a difference. In Third Party Sales, after getting the Sales Order a Purchase Order is raised to vendor and vendor will supply directly to the customer, and the Ordering compnay will raise the Invoice to the customer once the customer received the stock from vendor.
    IPO is similer but the difference is vendor will send the stock to the company instead of direclty sending to the customer. And the actual compnay will take the stock and do the delivery / shipping/ invoice to the customer.
    MM T.codes MIGO, MIRO plays crucial role in these type of scenarios.
    Hope this gives you some idea.
    REWARD IF HELPFUL.
    Regards,
    Praveen

  • Make to order /make to stock

    hi
    plz. tell me the detail process flow of both the scenarios i.e. make to order and make to stock with TCODES.

    Hi
    The difference between MTO and MTS is
    MTO--> Make to Order Production is the process where the  prodcution order is triggered from a Sales Order. Ex: The Prod process will start only after receiving the sales order from the customer. In this case the product could be customer specific only (Variant)
    MTS--> MTS scenario can be accomplished by the following settings
    Need to use strategy group 20 in material master MRP view-Stretgy group 20 is assigned to strategy 20
    Strategy 20 is assigned to Requirement type KE (Individual customer requirement)
    Requirement type KE is assigned to requirement class 040 (Indiv.cust.w/o cons.)
    Requirement class has all the parameters where we can define Prodcution order type that will be used to create th prod order. The above link needs to be established.
    Also the MTS can be achieved using Sales Order schedule line catagory which will be assigned to Requirement type/class. Item category is assigned to Reqtype/class and the Item category is maintained in the material master.
    You can use any of the baove config settings.
    For MTO --> you just need to have all PP cycle settings in place nothing special needed as it is a plain PP cycle.
    Please let me know if you need any more specifics or have any perticular questions.
    SAP online documentation has also all the details that you need
    Thanks
    Deepak

Maybe you are looking for

  • Ipod not to be a detachable hard drive

    now i know what my problem is... how do i get my computer to not recognize my ipod as a detachable hard drive? i want it to recognize it as an ipod again.

  • Did not find needed xsi:type attribute on element anyType

    The followings exception is thrown when using the access a web service using the proxy jar. The return xml contains <debts xm:bind="debts is return.safaccount.debts"> <anyType xm:multiple="debt in return.safaccount.debts">{debt}</anyType> </debts> de

  • Develop a program on pocket PC

    Hello I'm develop a program on pocket pc. I think i'll use j2me to develop one. But I don't have any exp on pocket pc or j2me on it. Q. Can Java run on pocket pc? If yes,what is the requirements?(addition d/l or setup any program?) Q. I had an exp on

  • Weird issues with pasted screenshots

    I am using Photoshop CS6 on Windows 8 desktop, i am connecting using Remote Desktop to a Windows 2008 server and taking a screenshot (all desktop apps, no Windows 8 apps involved). After taking the screenshot i can paste it into a simple program like

  • Check Network/IP in script