MTO-Process order convertion problem

Dear all
For MTS ; I am able to convert the planned order in to process order (order type PI01)
For MTO:  I am not able to convert planned order in to process order (same order type)i got the following below error on create process order screen
"Technical status 000000000000 is not available
Message no. CC852
Diagnosis
An internal error has occurred. There is a data inconsistency. The system cannot find the parameter variant data.
System Response
The system does not allow processing to continue.
Procedure
Inform your system administrator. If the error cannot be corrected, contact the SAP Hotline directly."
Kindly help

I have already created strategy group 99 and assign same strategy group in material master  which is having main strategy 40 and alternative 20
wht i did?
I hav created sale order with requirement type KE an then run MRP then i got pl order against sales order.
Now i am traing to convert pla order to process order i got above mentioned error.
kindly help

Similar Messages

  • Process order convertion problem

    Hi All
    When I am converting the Planned Order to Process Order I am getting a error message Not able to determine the consumption account.
    Can anybody tell me how this problem can be solved.
    Is there anything I have to do in customizing
    Rregards
    Dhananjay

    Hi Dhananjay,
    check your material is been assigned to valution class in accounting view in MM02
    if it is assigned then check GL account is given properly to that valution class.
    take help of MM and FI consultant
    Thanks
    Bala
    IF useful reward

  • Process order creation problem

    I am creating a process order . while creating the process order system is throwing error as Auto batch numbering not set up for material type XXXX in plant xxxx . System is not allowing to create process order.
    How to resolve the issue.

    Check in CORW   and switch off batch creation  to isolate the problem if needed.   Also see whether you have any batch managed compoents   for which you have set master data for automatic batch determination.
    There is no setting for material types and plant for batch.  May be the error message is not correct.  What is the message number?

  • Process order release problem

    Hai All,
    I have created a process order and when i am releasing the same, following error is coming and system is not allowing to release the process order.
    Resource T-DTM100 in operation 0200 does not meet resource selection conditions
    How to solve the issue

    Dear,
    Please do check the classification of the master recipe the class maintained there?
    Also execute report RCCLUKA2 with the following parameters: Object table:      CRHD
    Class type:  019
    Please refer this link,
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/89/a42678461e11d182b50000e829fbfe/frameset.htm
    Regards,
    R.Brahmankar

  • Process Order Cacellation Problem.

    Hi PP Gurus,
    Actually we r assigning the Batch to the finished product at the time of confirmation manually.
    For one of the FG I assigned the wrong batch number and did the confirmation.
    Now i m trying to cancell the confirmation, but the system isn't allowing me to cancel the confirmation.
    What may be the Issue, is there any customization changes required?
    Please Suggest.
    Thanks In Advance.

    Hi ,
    For the current issue,whether you are recieving any errors or simply the it is terminating the transaction.please reply.
    For the importance of "Termination of Incorrect Actual Costs" and "Termination of Incorrect Goods Movements"?It is the option given by sap to manage teh error logs,as the name itself says if these 2 are activated in OPK4 individual entry tab and if any erors is goods movement and costing ,system will terminate the transaction while doing confirmation.
    if it these 2 are not activated and only actual costs and goods movemnets are checked nad if any errors are there in the process order confirmation,system will allows to check the and correct the errors in COGI (goods movement) and COFC(actual costs).
    It does not have any effect on cancellation of process order confirmation.this will have effect only during confimation.
    Hope it helps

  • Process order conversion problem-sto

    Dear all,
    We are using STO scenerio  with strategy 20,  requirement comes in depots ,depots will be created sale order and then run the MRP in depots system will create PR against sale order in depots and pass the requirement to manufacturing plant  and sytem will create planned order against SO in manufacturing plant
    when i am traying to covert plannned order to process order system has given me below error "Technical status 000000000000 is not available
    Message no. CC852
    Diagnosis
    An internal error has occurred. There is a data inconsistency. The system cannot find the parameter variant data.
    System Response
    The system does not allow processing to continue.
    Procedure
    Inform your system administrator. If the error cannot be corrected, contact the SAP Hotline directly.
    For MTS (strategy 40 ) - above scenarion working fine
    kindly help

    Hi,
    Please check the status of the material wether internal or external procurement. I have one doubt on that?
    regards,
    Murali

  • Process order Closing problem..

    Hi...
    When i try to close the process order using CORM...i m getting error as......
    "Unprocessed future change recs for order  prevent del. flag/completion"
    Plz can anybody help me on this issue...
    Also now if I try to cancel the order using CORS...i get error as...
    "Activity lot size dependent duration cannot be entered"
    Regards,
    Ameya k.

    Hi
    This program can be used to clean open prod orders.
    please read below documentation:
    The program CORUPROC can be used to post preselected processes for
    confirmations.
    The following processes can optionally be preselected:
    o   Automatic goods receipt
    o   Backflushing
    o   Calculation of actual costs
    The program CORUPROC is normally used in periodically dispatched
    background jobs. However, it can also be started online.
    If the program is used in a background job then this is only by
    specifying a variant to make possible the parametrization of the program
    CORUPROC.
    The following parameters are possible:
    o   goods movements
        -   automatic goods receipt
        -   backflushing
        -   Incl. incorrect goods movement: Not only preselected but also
            incorrect goods movements that are usually processed with
            transaction COGI are are selected and processed. The indicator
            "Automatic goods receipt" and "Backflushing" are also taken into
            account.
    o   Determination of actual costs
    You can define further parameters for controlling the program flow in
    Customizing using the transaction OPKB. The following parameters are
    involved:
    o   Number of parallel processes: You can use this entry to restrict the
    number of simultaneously processed portions. If no number exists the
    system calculates the number of the maximum available work processes
    on the application servers that are available. The number of
    parallel processes along with the parameters "Maximum number of
    items in material document" directly affect the total number of
    active locking entries in the global locking table.
    Application server group: Using this entry the system can post goods
    movements in parallel to a predefined group of application servers.
    The RFC groups can be maintained using the menu options "Tools ->
    Administration -> Administration -> Network -> RFC destination, RFC
    -> RFC groups".
    Maximum number of items in material document: You can use this entry
    to specify the number of goods movement items used to create a
    material document. If the entry is missing then a maximum of 100
    goods movements are copied to a material document. This entry is
    necessary since with a large number of items the accounting document
    cannot be posted.
    regards
    Srinivas

  • Reprocess Process Order

    Dear Experts
    Please explain step by step procedure for Rework of a Process Order .
    Problem is related to rework of an order, where payment has been completed and the material is returned and some rework has been done and returned to customer free of cost, but this is not reflected in PP module, How it is possible?
    Regards
    Ragesh

    Hi,
    For rework of a process order you can create a process order without material by entering
    Recipe group,Recipe,Plant & Process order type.
    For further details refer the link
    <a href="http://help.sap.com/saphelp_47x200/helpdata/en/89/a42daf461e11d182b50000e829fbfe/frameset.htm">Creating Process Orders Without a Material and With a Master Recipe</a>

  • Problem of Missing parts during the Process Order release

    Hi
    For a Make to Order strategy, I have run MRP for a sales order which resulted in planned order for the material. But when I try to convert the Planned Order to Process Order, I am getting error Parts are missing during the availabilty check even though the components are available in the stock.
    But when I create a Process Order manually, I am not facing the problem of missing parts as stock for components are available in stock.
    Please advice why I am facing the problem with Planned Orders which are created via MRP.
    Regards
    Brijesh

    Dear all,
    If we set the Individual requirement (1) in MRP4 view of the material master for the component, the system will not consider the plant stock and it will give the message like Parts are missing during the Process Order process even though the plant stock is exists for the component.
    So I would like to where in customization you define this?
    --> To not consider the plant stock if individual req is set (1)
    --> To consider the plant stock if collective req is set (2)
    Kindly advice,
    Regards,
    Brijesh

  • Problem in Process order confirmation ( while doing batch splitting)

    Hi All
    In our Industry we have sceneraio
    we create Internal order and assign internal order to sales order
    Once MRP run take place
    Planned order created and converted to process order
    Process order released
    once we try to do confirmation of process order
    example suppose process order header matl qty : 8
    and in final confirmation while Goods receipt(101) of Fert
    we do batch splitting (example 4 batch : each qty : 2)
    but some time system not allows to do Goods receipt (movement type101)
    system gives "Error confirm order not allowed"
    please need urgent help
    Thanks in advance
    Sunil Singh

    Hi Sunil,
    During your first confirmation you must have activated "Final confirmation" Indicator, probably this is blocking from further confirmation.
    Please check whether current system status of the order contains "CNF" if so, please cancel the previous confirmation and then redo confirmation with "partial" button active. Final confirmation should be activated only when it is the last confirmation for the order.
    Hope this will resolve the problem, reward your points....
    Regards,
    Prasobh

  • MTO-Need to block (Not to Change)plant in sales order after process order

    Hi All,
    We are creating MTO sales order and requirement has been forwarded to MRP. Planning person is creating process order and will start their work. Sometime sales person change the plant in the existing sales order. Say for ex: changing the plant from 1000 to 1001. But requirement is already been transferred to 1000 plant. After changing the plant in sales order again the same requirement transferring to 1001 plant for planning. So based on this, 1001 plant also started producing the material. Here the problem is both the plants are producing for the same requirement. Now I need to control the this problem. Is there any way to control in std sap? if possible which way we can control? Please share your ideas.
    Thanks in advance,
    Babu

    hi
    use user exit
        MV45AFZZ
    FORM USEREXIT_FIELD_MODIFICATION    
    here you write the logic
    when production order  exit that line item plant is not changeable ,

  • MTO Process MRP Problem

    Hi,
    i am working in MTO Process. Bill of material all Created. MRP Run. after some material added in bill of material . second time MRP  RUN.Plant order not created for second added material.
    what is the problem .
    plz, Advise me.
    Regards,
    JJ

    Hi Uday,
    New material maintained for MRP View. and Check it .first mRP running and Added the New material.second time MRP run .
    But not Plant Order created.
    Edited by: JayamJevan s on Jul 16, 2009 1:50 PM

  • Re: Error while making a Process order in MTO scenario

    Hi All,
    I am having a secnario, where I am using MTO scenario. I want that the sales order should trigger the process order.The components in the BOM for the FG material .
    1. Raw material: procured from outside: Stock & value relevent.
    2. This one is non valuated one :procured from outside: Stock &  Non-value relevent.
    Now when I create a sales order, I can see a plan order in the MD04 scree for this FG . But on drilling down this plan order I can only create the PR for the 1st component only ,for the second component I cant create anything.
    The second item should be non valuated & stock relevent.
    Please help me in this regards,
    Vivek

    I have taken help from some other threads to resolve this issue.

  • Problem in process order creation.

    Dear Sir/ Madam
                             i am facing a problem while process order creation.
    the problem is:
    Error when calculating cost for order ATFEDEC11  "see log Log is deleted when saving
    Do you still want to save?"

    Hi,
    The log for production order preliminiary costing is not saved. Therefore, once the order is saved, there is no log available anymore (this is by the way a question of PP; none of the logs is saved).
    Hope that helps...
    Regards,
    Declan

  • Problem during Process Order creation

    Hi,
    I have problem while creating Process Order.
    I have maintained all the basic data required to create the process order.
    When I Release the order, I am able to create the control recipe also, but PI sheet is not generated along with it. System gives the message "No PI maintained in customising for CRD for which control recipe is to be generated "
    If I maintain the same, then system is unable to create the control recipe.
    What may be the problem here? What i can do to rectify this situation?
    Pavan

    Hi Pavan,
    1. Maintain PI in SPRO of process management
    2. Assign this PI to one of phse in master recipe
    3. Plz check wheather ur created Control receipe destination or not.
    4. if not then maitain the same in Spro.
    5.Check the ordre type dependent parameter i.e COR4 from SPRO
    see the Control recipe gerated in REL phse else maintai the asme in production scheduling profile.
    if possible plz send the sctren shot fir the same to
    [email protected]
    Regards
    Siddhesh