MTO & Production Order Cost estimate

Hello
We have MTO with Production Order cost estimate for valuating invendtory.But the value of GR is not matching with Production Order cost estmate though strategy is "2"-with which its valuated.The estimate does not have any majaor itemisation except Activity cost-which is unchanged.How do i find the the value with which GR is done.AN order cost estimate no is saved in EBEW.WIll this give me trail of the itemisation with values & how can i get the trail.

Hi SR,
- Value GR is not match with the order, here are my basic question
> Are you using material in the standard price or moving?
> Are man days estimated is same with the actual GI?
If there is different than cost estimation would not be the same with the actual GR.
- Find the the value with which GR is done, I'm not sure about the question here & correct me if I'm wrong.
If you want to search whether GR is done or not you should check by the Order in module PP
- How can i get the trail, if you want to get the trail over cost and until sales order in placed, I think it has to be a custom program
Hope helps

Similar Messages

  • Production order cost estimate

    Hello,
    what is prodcution order cost estimate.

    SR,
    Production order cost estimate is the estimate of all the costs likey to be incurred on the completion of the production oreder.
    Following is the way described how tp do this in SAP.
    Creating a Cost Estimate for a Production Order Without Quantity Structure
    Choose Accounting-> Controlling->Cost Object Controlling->Product Cost by Period->Planning->CO Production Order->Create/change plan.
    Enter the order and choose ENTER.
    The dialog box Copy cost estimate appears. The system proposes a costing variant through the planning profile. Choose a costing variant.
    If you want to copy costing items using the reference and simulation costing functions, enter either a base planning object or the material and control parameters for a cost estimate without quantity structure.
    Enter the lot size that you want to use for costing, and choose ENTER.
    The system displays the list screen of the cost estimate without quantity structure.
    Enter the costing items.
    Save the cost estimate.
    If you have entered a costing sheet and (if applicable) an overhead key in the master record of the production order, the system calculates the overhead and assigns it to costing items of item category G. You cannot plan the costs for a production order using a cost estimate without quantity structure if the production order is linked to a run schedule header.
    Hope this helps you.
    Rgds
    Manish

  • MTO Production order planned cost

    Hello
    We have a MTO production order.Need to know plan cost of order.But unable to get in COEP or other csoting tables.Any other table where we can get the data.
    Thaks in advance.

    Hi,
    Check COSP table it is for planned cost.
    Regards,
    Sreekanth

  • Production order costing issue in MTO with variant configuration

    We have an urgent issue to be resolved in production order costing in MTO scenario.
    We have two level configuration with configuration passed from parent to children. The parent has many configurable materials as child(semi finished BOM items) and BOM items of these child has again different raw materials(3 level BOM with last  level being all raw materials) . The production order for parent  created with reference to sales order.
    While costing production order of parent, total planned  price is displayed as zero as we have maintained price control std price for all configurable materials(parent & child) with zero price being configurable materials.Configurations are correct in production order material and BOM components(configurable materials). BOM item selections, Item quanties are also correct.
    Sales order costing is working fine and rolled-up correctly as per costing settings. We have looked at costing configuration for production order and did not find anything unusual.
    Kindly suggest possible reasons for not showing costing result in production order as per configuration copied from sales order  or any possible configuration or master data likely missing ?
    Thanks in advance.
    Kind Regards
    Ganeshan Kalembeth

    Dear  GANESHAN KALEMB,
                           Kindly open production order in change mode and reschedule order, cost order, check material availability and check capacity availability.
    after doing this in main menu goto  > log > overview > see error list if there is any, let me know, your problem can be solved.
    Thanks
    Muhammad Ashfaq

  • Sales Order Cost Estimates -- Versions?

    In our MTS plant we are creating cost estimates each month with different version numbers so they can easily be compared to review cost changes.
    This concept in our MTO plant is (of course) a problem.
    We would like to create a dummy sales order and on each line list a KMAT and build an "average" configuration.  We use variant config, so the sales order bom is built automatically.  It also costs automatically.  We would like to save this cost estimate and compare it with a cost estimate of the same configuration next month.   I do not have an option for version CK51n, nor do I see a Costing Date in KEKO table.  Either of these items for MTS would create a second cost estimat and allow comparison.
    Is there a way to compare Sale Order Cost Estimates across periods?
    Any other suggestions as to how to obtain the required data??
    Thank you for all suggestions!!

    Any one think of a solution?
    thanks

  • Sales order cost estimate with GIT account

    Hi,
    Business introduced Goods - in - Transit (Balance sheet account), so PGI will always post to GIT and Invoice it will get reversed.
    For one of the Configuratble material (MTO) scenario we need the Sales order cost estimate to get the Planned cost.
    When i try to execute the sales order cost estimate it says cost element doesnot exist for GIT GL (WHich is right).
    But with maintaining the GIT how to achieve the sales order cost estimate.
    I tried to create CE category 90 for GIT, in Cost estimate am getting error CE 90 not supported for Cost estimate.
    Kindly help this is kind of urgent req for us
    Thanks,
    Sudha

    Hello Ashley
    Yes, if you have done your settings correctly, especially Requirements class set up  (see the documentation link),  then the cost estimate will flow to a condition type in Pricing, usually EK01/EK02 conditions. These conditions are used to calculate sales prices (PR00) in cost-plus (mark-up) scenarios.
    Link: http://help.sap.com/erp2005_ehp_04/helpdata/EN/90/ba6da4446711d189420000e829fbbd/frameset.htm
    However Profit margin  as calculated in a sales order comes from VPRS condition  (which is based in Material Master) and is the difference of net value and VPRS condition value in normal circumstance.
    Hope other more knowledgeable experts will weigh in.

  • AFS grid value/valuation type not picked in sales order cost estimate

    Hi Experts,
    We have different valuation types in the material master. This is part of the AFS, where each grid value is a valuation type. While making a sales order cost estimate and in one sales order item, we have 3 grid values (valuation types), system is costing only for one grid value and that too for the entire quantity. This way the costing is wrong as different grid values have different BOMs and routings.
    Is there any specific setting to have the grid value to be picked up in the sales order cost estimate? Or am i missing some setting? in general product costing settings or AFS product costing settings?
    Best Regards
    Vimal

    Hi,
    Do you mean "sales order costing", please  if so then please ref. the link:
    http://help.sap.com/saphelp_46c/helpdata/en/90/ba6da4446711d189420000e829fbbd/content.htm
    Regards
    DSR
    Edited by: D.Srinivasa Rao on Nov 25, 2011 8:19 AM

  • Settelment of (MTO) Production order to sales order.

    HI ,
    Can any one tell ,
    When we settle Production Order in MTO to Sales order
    What are the Accounting Documents Generated, Wheter system will generate Controlling document or Accounting Document.
    I have done the Process, But i m getting CO document.
    If it is wrong Pls tell me settings wht i m missing.
    Also Pls let me know the importance of settleing the MTO Production order to Sales order.
    Becos when i settle it there is not reflect on Sales order as System is generating Co document.
    Regards,
    Pavanidlur

    Dear PAVANIDLUR,
    Normally its generated automatically; by because here the Production Order and the Sales Order are the Cost Objects.
    Settlement Entry:
    FI:
    WIP Balance Sheet Acoutnt ...............Dr
            to WIP Balance Sheet Account
    CO:
    Production order witll be Credited
    Sales order witll be Debited.
    Dear experts correct if i m wrong;
    Regards.
    Raj

  • Product cost v/s Production Order cost

    Hi all Guru's,
                            Can any one help me in understanding difference between product cost and production order cost in SAP.
    Will give full marks for helpful answer.
    Thanks,
    Abhishek
    Edited by: ABHISHEK AGRAWAL on Jan 29, 2008 9:46 AM

    Dear Abhishek,
    Standard Cost Estimate or Material cost Estimate is nothing
    but the standard cost for the Inhouse Manufactured materials
    (FERT) = Raw Materials Cost + Activity(Operation Cost)
    Cost+Overhead Cost if maintained for the Company code.
    This cost will gets stamped in the material master in Costing2
    view,under Current Planned Price field.
    This cost will be the Planned Cost of the Production order and
    after confirmation of the order the actual cost and the variances
    for the production order can be viewed.
    So the Production order cost is for the order quantity say for
    Eg: for a quantity of 100.
    The cost(variance) will be settled against that production order
    after confirmation and TECO status.
    I hope this will be helping you.
    Regards
    Mangalraj.S

  • CATS vs. Sales order cost estimate

    Hi Gurus,
    If I sent some hours to the sales order item thru CATS, can I have them in the sales order cost estimate?
    Thanks
    g

    Thanks.
    So the one way to have CATS hours in sales order cost estimate is somehow squeeze these hours into the sales order BOM, init?
    What is the best way to do? Plan it in the routing and put the actual hours thru CATS into the production order? Or some other way?
    Regards
    g

  • User Exit or BADI on saving of Sales order cost estimate (CK51N)

    Hi,
    Can any one share with me what are the User Exit or BADI that gets triggered on saving of Sales order cost estimate (CK51N).
    Regards,
    Bijay

    Hi
    Check the link
    Need Enhancement Spot or BADI for transaction ck51n
    Regards
    Sanil

  • Sales order cost estimate

    hi,
    While saving the sales order cost estimate its getting the GL account from GBB-ZG0.
    as we assigned Balance sheet account its asking the cost element.
    can you please explain what is link to get the gl from GBB-ZGO, can we change this to pick from GBB-VBR.
    Thanks,
    Sudha

    Hi,
    Are you are working with unvaluated special stock ?  In this case, the system is looking for a consumption account via the account assignment category. For example if you are using requirement class ZPJ which uses account assignment category Q. In account assignment Q, you entered account modification VBR. Therefore, the system is looking for an account via the keys GBB / VBR.
    regards
    Waman

  • Sales order cost estimate not happening because of GIT B/S account

    Hi,
    Requirement is to have Goods in Transit account in PGI and reverse it in Invoice no issues iwth it.
    For the same sales order user wants to get cost using sales order cost estimate.
    When i run that am getting following error
    Item 00001 : Cost element 14001212 does not exist in CO area 0010 for 10/07/2011
    Message no. KK689
    Even though i maintain the CE for Balance sheet account with Cost element category 90 its not accpeting.
    Can you please help me on how to proceed for sales order cost estimate.
    Thanks,
    sudha

    hi,
    if you give a balance sheet account in obyc , you will not be able to create a cost elementin category 01 , accordignly system will give error in sales order costing , as its not able to get correct cost element in cost planning.
    if your requirement is just to post  cogs to a balance sheet account which is goods in transit and when invoice is done cogs to be posted.
    you should actually use  revenue based RA functionality on sales order instead of assinging a balance sheet account in obyc.
    in this approach;
    - first assign a p/l account in obyc and create cost element in cateogry 01.
    - create revenue based RA and assign RA key in requirement class.
    - in OKG8 for RA category  WIPR and your ra key assign , goods in transit account and give a offsetting account which is not cost element (credit entry in offsetting account nullify debit in account given in OBYC when GIT is posted , when billing is done system will automatically post a oppsite entry in both account).
    -in OKG8 for RA category COSR give the COGS account and a offsetting account without cost element (credit entry in offsetting account nullify debit in account given in OBYC when COGS is posted).
    regards
    rajesh

  • Reg :Production order cost  report day wise.

    Dear Expert,
    1.We want a report for a particular Production order cost  day wise.
    The scenario is like this Production order is Released for 100 Qty.
    Today they confirmed only 50 Qty.
    Tomorrow they will confirm 50 qty.
    Now they want to see the cost for today confirmation and tomorrows confirmation.
    Reason being daily the Raw Material cost is changed and they want to track the variance.
    Is there any standard report we can achieve this or do we have go for development
    2. And also i need to know daily how many production orders have been released.
    Thank u in advance.

    A day is not a controlled cost object. You could write a report to look at costs gathered in a day (by reporting date), but I strongly suggest that if you need to analyze costs per day you switch to daily orders.
    You'll find then that all the standard processes work for you.

  • Sale Order Cost Estimate

    Hi,
    We have maintained Material BOM (usage 1) as well as Sale Order BOM (usage 5).
    When we run the Sales Order Cost estimate, which BOM would be picked for costing the sales order.

    Hi,
    The issue is not with respect to selection of the Sale order BOM or routing. System is correctly selecting the specific BOM and routing for costing.
    However, when we display the sale order cost estimate, when we navigate to the Qty Struc tab and double click on the sale order BOM or Routing Group, it does not take me to the specific Sale Order BOM.
    Please suggest.

Maybe you are looking for

  • Input help in variable screen

    Hi, I'm having a query on top of 0EMPLOYEE. 0EMPLOYEE has an attribute of a business unit (which has the default BEx settings of display as text) and I have a selection option variable on top of this attribute. Previously, on BW 3.x the variable scre

  • How do I remove Spyware - conduit and trovi from my MacBook Pro?  OSX Yosemite is my operating system.

    I using a MacBook Pro - OSX Yosemite, Version 10.10.  I appear to have web browser issues.  I am experiencing constant Ad Pop Ups when I surf the web.  In addition, when I open new tabs, my default page changes to "bing".  I checke the url and it has

  • Kgepop: no error frame to pop to for AND In-flux value for a pin

    Hello, I'have a big problems with my oracle forms web. Since we have make an upgarde from 10g to 11gr1 of our system, some forms crashe when we make a search from the menu bar. in the log file there are these errors: 1) FRM-93652 : The runtime proces

  • ES through xMII - Input/Output variable mapping

    Hello All, I'm new to SAP xMII Application. I'm using BLS Transaction's Web Service action to invoke Enterprise Service (ES). Can you tell me how to pass on the input parameters to the ES ? Also in which format the ES will send the response and how t

  • SNMP v3 TRAP

    Hi, We are trying to configure SNMP V3 trap on our routers and switches. I can able send V3 trap to our NMS, but it is mentioned that we need contextengine and contextname to process the trap. We have configured a simple TRAP configuration without au