MTO without MRP
Hi,
We are following MTO scenario in discrete manufacturing without MRP. I am creating the Production orders with
reference to Sales Order for HALBs initially, then system gives message that Sales order is not for HALB material.
I accept that message and proceeding to create Production Order.After creating the Production Orders for all HALBs is it correct to create production order for FERT with reference to Sales Order in which target quantity is displaying
What is the exact procedure to do this MTO scenario without having MRP.
Dilip
Dear friend,
The answer by JH is correct .
with strategy 82 -Assembly procesing with production order.
When you create a sales order for a material which has been assigned a strategy group 82 in MRP3 View for assembly processing, an assembly order i.e procuction order is created automatically .
i.e Creation of sales order triggers the creation of production order automatically..
thanks ans regards,
Girish.
Similar Messages
-
Without MRP, with BOM explosion
Hi,
I'm new to SAP and learning SAP SCM. I would like someone to brief me on what the following lines imply, especially 'without MRP, with BOM explosion'.
"dependent requirements must be determined for materials that are planned in SAP ECC. So, you assign the MRP type X0 with MRP procedure X (without MRP, with BOM explosion) to the materials planned in SAP SCM."
Thanks,
KrishHi,
Without MRP , with BOM explosion - means the dependent requiremens are created for this materials from APO.
The MRP will not run in APO. Only the dependent requirements will be created from APO. The MRP for this materials will be executed the ECC or R/3 system to create planned order anb purchase requisitions.
Thanks and regards
Murugesan -
PK01 Replenishment Strategy without MRP
Dear guru ,
i want to create a control cycle with a Replenishment Strategy without MRP.
The material master have MRP Type ND.
When I create a control cycle the system select strategy for kanban control with MRP.
I have verified that I must also enter storage location mrp indicator equal to 1 in order to select strategy control without MRP.
If i enter storage location mrp indicator equal to blank why the system donu2019t check only material master mrp type ?
Thanks.Not answered.
Closed. -
Automatic Purchase Requisition using Reorder Point without MRP Run
Dear Freinds,
My client wants Purchase Requisition should be automatically created as soon as the stock falls below reorder level without MRP run.
Is this possible? if possible then what are the settings required.
Thanks
Prashant AtriDear,
It is not possible in standard SAP.
What is the problem to take MRP run?
You can take the MRP run in background through MDBT so system will create automatic Purchase Requisition using Reorder Point.
Hope clear to you.
Regards,
R.Brahmankar -
Hi Experts,
Is it possible to carry out MRP, without maintaining MRP views and Planning file entries (Manual) for a material?, Please explain!!
Thanks and Regards,
Suresh.Hi,
Is it not possible to rum MRP without MRP views extended for the materials.
For running MRP system requires some key parameters like :
Procurement Type
Lot Size
Rounding Profiles
Reorder level / point
MRP Type
MRP Group
..........etc
As all these fields are available in MRP views only it is not possible to run MRP without extending MRP views for the Materials.
Hope this will help you.
Regards
Rdahk mk -
Generating a production order through projects, without MRP run?
Hi to all
Is it possible to generate planned orders and further proceed to production order through projects WITHOUT MRP run?
Regards
suryacreate the production order in CO01 and assign WBS element in the assignment tab of the order.
whether it ll solve ur purpose....
ashis -
Process order required for each sales order without mrp run
Hi, it is mto scenario. wants system to create a process order for each sales order without running mrp. please advise is it possible? if possible please guide what settings need to be done. Thabk you.
HI
You can create production order with reference to sales order using t code CO08.
Check and revert
Regards
Anupam Sharma -
Shipment tracking without MRP relevance
I have a Shipment with associated Deliveries. The deliveries are based on Schedulung Agreements, which have Confirmation Control keys assigned.
I have to mark the confirmation control key as being relevant for Tracking to get the tracking available on the Shipment. The problem is that I also have to mark the confirmation control key as MRP relevant, which means that everytime I update the tracking of the shipment, MRP and the demand gets affected.
What I want to do is track the shipment as an internal information only, using the standard functions and not have MRP affected.
When I try to set it an error is displayed that does not let me save.
As far as I can find there is nothing in the SAP Help, nothing on the notes and nothing here in the SDN.
Can you please assist me in setting this or finding a easy standard solution.
Your assistance would be appreciated.
ThanksHi,
Would you know if/which user-exit or any other functionality can be called during MRP runs to manipulate the data at delivery schedules?
I was trying eg. 'EXIT_SAPMM06E_013' or 'EXIT_SAPMM61X_001' but without success.
Regards,
Dominik Modrzejewski -
Hi,
i am working in MTO Process. Bill of material all Created. MRP Run. after some material added in bill of material . second time MRP RUN.Plant order not created for second added material.
what is the problem .
plz, Advise me.
Regards,
JJHi Uday,
New material maintained for MRP View. and Check it .first mRP running and Added the New material.second time MRP run .
But not Plant Order created.
Edited by: JayamJevan s on Jul 16, 2009 1:50 PM -
KANBAN - Reorder request to vendor without MRP
Hello Kanban Gurus,
Have any of you helped set up Kanban processing in SAP especially with Warehouse Mgmt.
My client is asking about this u2013 and what they really want to know is they understand that when kanban is triggered for an inventory item to send a re-order request to the vendor u2013 this can be done through email u2013 etc u2013 but how is the trigger activated especially if MRP is not being run for the kanban material in question.
Please reply ASAP.
Thanks in advance
GeorgeHi,
The trigger is the change in Kanban status, from FULL to EMPTY.
With the proper external procurement strategy and normally in the context of a scheduling agreement, a delivery schedule line is created and transmitted to the vendor.
Regards,
Mario -
Scheduling Agreements without MRP
Hi !
I have a depot scenario wherein the organization doesnt have MRP runs configured.
Can we by any way configure Scheduling Agreements for customers, the basic purpose of which will be automatic creation or otherwise proposal of creation of deliveries on the required delivery dates, based on the available stock of materials?
Thanks and regards,
Shamik.This is correct !
Regards
Bhavesh Mistry -
Maintaining a component without MRP view in a BOM
Good Day everyone!
Can i set the system so that it gives me an error or warning message that the component i am maintaining in a BOM does not have an MRP views yet?Reden Manguerra ,
in standard SAP its not possible. may be plant specific material status can help up to ceratin extent to check material with category L in BOM is doesnt have relevant status release for engineering.
you need to check this.
or
you need to develop this function your self.
Regards
Ritesh
Edited by: R S D on Jun 19, 2009 2:28 PM -
Hello,
Can anybody explain how the procurement process is done where company is not running MRP periodicaly?Hi,
Basically MRP is the process which compares the requirement with the available stock and if there exists any shortfall will raise the procurement proposals.
How ever based upon the requirement for the material one go for manual creation of the PO based upon the PR created and procuring the material using the PO and made available this material by making the GR.This is the usual normal process.
Regards, -
MTO without Variant Configuration
Dear Experts,
while creating planned order.
Sales order does not allow make-to-order production
Message no. 61155
Diagnosis
The sales order entered is not to be included in make-to-order production.
System response
Account assignment can only be carried out with sales orders created with a requirements type for make-to-order production.
Procedure
Enter a sales order that is to be included in make-to-order production.Hello,
This is most probably link to Requirement Class / Requirement Type / Item Category config & assignmeht.
Refer the below thread:
Sales order does not allow make-to-order production
Hope this helps..
Thanks,
Jignesh Mehta -
Availability check without MRP
Hi all,
we have trading goods scenaios. There is no production dept. But we do have maintain all stocks maintain / procured from vendors. however when a customer come and asks the particular material at the same time availability should be carry out and substituon materials also(popup same FFFC) plant wise, storage location wise i want to carry out av check at one shot means at the legacy system they want to maintain like that only. so how i can proceed. pls help me in this regard.
Thanking You,
BabuHi,
1. Maintain the checking group in the material master in the sales view.
2. Also check the required configuration for the ATP is all there.
3. Once when you have the sales order enter you can to the ATP check inthe sales order item level and do the confirmation.
4. If you want to handle the substiution , then enter the material determination
5. In material determination activate the ATP Check
Reg
Dsk
Maybe you are looking for
-
One day the phone just got stuck on ios6 screen then once unlocked it said plug into iTunes. Once I did the phone will not allow me to complete a restore. At the last stages the phone will cut off. I have asked a friend to have a look and he thinks i
-
iCloud and my iPhone sync okay but my second Mac does not sync with iCloud. What's wrong?
-
Help with Spry Framework positioning not appearing correctly on pc's
I just created a gallery using the spry framework and finally got it working for me on all the browsers I have on my Mac. The problem is that on my clien'ts pc the gallery div tags end up moving up to the upper left corner and I'm not sure why. The
-
How can I get read only files out of the trash?
Either by deleting them, or moving them out. I have to click continue about 170 times just to get through the files to empty the rest of my trash.
-
How to freeze fields on standard Tcodes.
Dear SAP Guru Can any one plz let me know how to freeze the fields on standars T-codes, as i want our end users to use only particular fields on standard tcodes in SAP Thanks in Advance Bhushan