Multi counter plan schduling start date

Dear Experts,
Anyone can clarify the following points to provide proper support to client.
1. we have created multi counter plan with cycle set contains of different target counter readings with logical condition OR.
2. Now users are recording the counters via measuring documents.
3. we are mannually scheduling the above M.Plan. System is deriving the order start date on its own. we want to know the basis behind deriving the order start date? userrs wants starting date on its own, can system will support with ant exit?
4. what is the significance of annual estimate reading in the measuring point? how it help to derive the planned start date of M.Order?
5. users also wants that, system should check measuring documents on its own while creating measuring documents and should result the order if it crosses the limit of the cycle set mentioned in the M.Plan. Is it possible to support the scenario?
Thanks in Advance,
Krishnamurthy

Krishnamurthy,
3) Do a manual call of the Maintenance plan, this would be the easiest way, instead of using exits
4) For performance based MP,The [calculated planned date|http://help.sap.com/erp2005_ehp_04/helpdata/EN/3c/abb1ec413911d1893d0000e8323c4f/frameset.htm] depends on the counter reading at the time of planning, and the estimated annual performance that has been defined for the counter.Hence it is important that you enter measurement readings for the counter,e even-though the reading has not changed.
5) With respect to your last question, That functionality is accomplished through Condition based maintenance functionality. You will have to use the user exit to generate a order when the reading falls outside pre-determined values.
Regards
Narasimhan

Similar Messages

  • Creating multi counter plan using LSMW

    Hi,
    I am trying to create multi counter plan (transaction IP43) using LSMW. I am using direct input object 0460 for creating it. Object has IBIPMPLA structure as header. How can i pass multi counter data in it ? Problem is line item level values like 'Maintenance cycle' (ZYKL1) are at header level structure IBIPMPLA.
    Anyone has cretaed multi counter using this object, please help me with it.
    Thanks,

    Hi,
    creating multi counter plan using LSMW
    Try this link,
    http://www.sapfans.com/forums/viewtopic.php?f=7&t=217834&p=1059434
    It will helps to you.
    Regards,
    Sekhar

  • Planned order start date & finish date

    Dear All ,
    I am running MRP for finished material ,
    But i am getting Planned order start date & finish date are coming same (todays date ). But when i am converting the order then proper scheduled dates are coming .
    Why for the Planned order the scheduled dates are not coming ?
    Regards

    Hi Venky,
    Pls try to understand how MRP works
    After MRP planned orders are created for the requirement(in house)
    In the planned order stage -basic dates are deteremined
    For the determintaion of basic dates system check the in house production time/replenishment lead time maintained in the material master
    For your requirement you maintain lot size dependent in house production data in the work scheduling view & check
    You have to key in data in set up time,processing time ,base qty etc
    Hope it is clear
    Rgds,
    SVP

  • SNP Planned Order start date in past

    Hi
    After SNP run, for the past requirements it is giving avaiablilty data as today but the planned order start date is in past. Now this order fails in CIF as the production version in R/3 is valid from today.
    In the strategy profile we have backward+reverse with infinite scheduling. In this case the start date should be todays date for past requrirements... am I correct?
    Regards
    Abhishek Rai

    Hello Abhishek,
    We are also facing the same issue. Did you find any solution to this issue?
    We are on SCM 7.0 with EHP1.
    Thanks,
    Mangesh

  • Multi-Counter Plan with multiple Equipments

    Hello,
    We would like to track maintenance costs at Equipment level.  In multi-counter maintenance plan, is there a way to enter multiple equipments in one mainteance plan?
    Thanks a lot,
    Venu

    Dear Venu,
    In multi counter plan, only one equipment may be assigned, as correctly observed. However, you may assign the same equipment with different task list, depending on the cycle set, so that maint order is generated with required operations applicable for that cycle.
    Eg: Cycle set 1   100Hrs/1month
                          2    500Hrs/3Month
                          3    1000Hrs/6 Month
    Create task lists as per above cycle sets and for each cycle set assign the same equipment, but with different task lists.
    This reduces the number of maintenance plans for a given equipment. This is particularly useful for vehicle management, where the running KM and time are the common counters.
    James Prabaharan

  • SNP Planned order START date should be displayed in DATA VIEW

    Hello Guru's
    I have a very complex requirement. It is as follows
    We are using heuristics and capacity leveling for our requirement. We generally see the planned orders in the SNP view but here additional requirement is that we have to see the start date of the production planned in the date view, ie the client would like to know when the actual production starts and wants to see the quantity produced on the first day in the date view.
    In capacity view,we can observe the resource load which is the start date of the production planned, this load is in percentage now do i related that into quanitity and even if we do related that percentage in quantity then how do i see it the SNP data view plan.

    Hi Sriuppa,
    you can use receipts view /sapapo/rrp4 transaction where you can see receipts. This transactions offers you the selection based on  product,source,target,dates,resource and you will get the list of orders.
    Secondly ,if you right click in the receipts cell,select display details,it will show you order details at the bottom of the data view.
    Please let me know if it helps
    Thanks
    Amit

  • Problem-planned order start date in the past

    I use PP-PI - After MRP run, planned order was created and has exception message "06-start date in the past" its make me wonder because before this problem occur we already tested many time and never found this message(06). then i check in OPPR- field "start in past" is blank, OPPQ- field "Start in past" are not check, OPUZ-Scheduling Type is backwards and field "Start in the Past" is blank, OPU5-Scheduling Type is backwards and field "Start in the Past" is blank.
    do any guru know why system not use forward scheduling when found that start date in the past? or have any config of other module which may lead to this issue?
    thank in advance.

    In OPU5,
    Check the setting for correct MRP group which is assigned in  material master or in the SPRO node
    Production >Material Requirements Planning>MRP Groups-->Define MRP Group for Each Material Type.
    check and come back

  • Planned order start date is in the past

    Hi Experts,
    I am running MRP with lead time scheduling (2) at my production plant. The planned orders are generated against the requirements but the start date of the planned order is in the past. I have not mentioned anywhere in the configuration allowing the scheduling in past. I cross checked plant parameters, MRP group, settings for determining basic dates & scheduling parameters and every where start in the past check is blank.
    Since the planned order basic dates are calculated based on in house production time in material master, I maintained the lot dependant times in work scheduling view (Set up & processing time with base qty). But system is not considering this in MRP run. But its considering the lot independant inhouse prod time maintained in work scheduling view in MRP.
    Is there any other check to be maintained or system limitations? Your expert view on this please.
    Appreciate an early reply.
    Thanks & Regards
    Prathib

    Check OPU5
    S Anil

  • Cycle sets in Counter plan

    How is it possible to create two cycle sets in one plan. I create one counter plan with one cycle set and save. Plan no is generated. Then how can i create a second cycle set for same plan no as the system is designed for Internal numbering of plan.
    Please explain me the real use of cycle set in multi counter plan. where it is used and when . for what purpose and steps on how to create two cycle sets for one multiple counter plan.
    Thanks in advance
    Murad shaikh

    Hi ,
    Check your config setting as given below
    Plant Maintenance and Customer Service> Maintenance Plans, Work Centers, Task Lists and PRTs> Maintenance Plans> Configure Special Functions for Maintenance Planning.
    The check box should be ticked.
    This allows the maintenance of multiple cycle sets in one plan. Thus you can define different cycle sets, and thus cycles, for calculating the dates within a plan. You can use the assignment between cycle sets and the maintenance item to control that only certain maintenance items generate a call object for certain dates. In the simplest case, a cycle set such as A - B - A - B can be defined. "A" leads to a small inspection and "B" leads to a big inspection.
    Also check below link
    http://help.sap.com/saphelp_di471/helpdata/EN/c9/fccf28f79611d4961300a0c93029cf/content.htm

  • Modelling Time Dimension with Fact Table containing Start Date and End Date

    Hi Gurus,
    I have a time dimension with Year till Date. I have a fact table which consists of Start Date, End Date, Person ID, Department ID.
    How do i design Time dimension with fact table the below scenario
    In the dashboard i have start Month and End month as prompts.
    In the report i need to display Count(Person ID) > Start Date and < End Date along the trend.
    For instance, i have selected Jan-2009 as start date and Apr-2009 as End Date, then i need to display Count(Person ID) of Jan-2009, Feb2009, Mar-2009 andApr-2009.
    I Can not connect Time dimension with only Start Date or only with End Date to get the trend along the months.
    Please advice on the issue which i am having.

    Hi,
    Thanks for the response, Infact i tried using Complex join in physical layer. I have considered Time table joined with Fact table, and used >= and took and alias of the Time table and joined fact table using <=. When coming to BMM, i am not knowing how do i design this as if i merge the both the time dimensiona and its alias into single table, values will not be correct and if i make them as seperate columns. i can not show the trend as both are different columns.
    Can you please let know where i am going wrong.
    Thanks

  • Manual creation of PPDS Planned Orders by start date and time

    Hi,
    When an order is manually created in any ppds standard transaction the start date is calculated according to the availability date entered, the order quantity and the master data 
    Is it possible to manually create an order based on the start date and then the availability date is calculated according to the order quantity and master data?
    Thanks
    CTF

    CTF,
    You can 'forward schedule' manually created orders.
    Scheduling direction is dependent on the Strategy profile.  During order creation, you can change this.
    When on the order create screen (/sapapo/rrp5), select the strategy button at the top.  This will bring up the default strategy for your userid.  You can alter the "planning direction" to be 'forward' or 'forward & reverse' depending on your business requirements.  Selecting Save will then make this scheduling strategy your default; otherwise just hit green checkbox.
    Now the order entry screen will have 'start date' entry box.  Avail date will then be calculated.
    Best Regards,
    DB49

  • Planned order creation with PDS valid on only order start date and not finish date

    Hi All,
    We have requirement to allow creation of planned order manually if production version is valid on order start date and not finish date.  This is because lead time of order is longer. I refered OSS notes 385602. I could find out solution for this is implementation of OSS note 694140 to change validity mode at activity level to consider start date of first produce activity  in validity interval. Problem is even If I create order in APO by implementiong this note planned order is not transfered to ECC and it gets stuck with error production version not valid.
    Is there any way in ECC to control this? Any config or customization?
    Regards,
    Santosh

    Nilesh,
    I think there is a simple procedural skip happening in your business process. You are right when a planned order is created after MRP it would default assign it to the first available production version. 2options available for us,
    1. First use transaction MF50 and do the line loading and assign the quantites to the production versions/Production lines, so that the actual capacity planning is getting completed. This way you can have planned orders with both the production versions and matching to your actual line capacity.
    2. Use Quota arrangement concept, to automatically split the Planned orders during MRP for a percentage based on individual production versions.
    Now when backflush is performed S225 table is updated and Planned order qty also gets reduced.
    Hope this helps....
    Regards,
    Prasobh

  • BAPI to create SNP planned order based on start date

    Hi,
    I am looking for a BAPI to create SNP planned order based on the order start date. There is BAPI BAPI_MOSRVAPS_CREATESNPORDER which can be used to create SNP planned order based on the end date but not based on the start date.
    Also would be great if some one can share how do they create SNP Planned orders using BAPI BAPI_MOSRVAPS_CREATESNPORDER in case if GR processing time is defined in the product master and workdays for GR to be respected according to the calendar.
    Regards,
    Venkat

    Hello Mr.Venkat,
    Hope you recognize me.
    Please check out the BAdi below.
    BAdi - APO_BAPI_BUS10503 (this is the BAdi for ManufactOrderAPS  BAPI which contains the SNPorder BAPI)
    Method - CHANGE_SAVEMULTIPLE2
    In this method parameter IT_ORDER_HEAD contains Order start date input option.
    For GR time please check this (not sure if it will help).
    Same BAdi/ same method
    Parameter IV_PLANNING_MODE_USAGE contains field PLANNING_MODE.
    Value 1 for PLANNING_MODE corresponds to "Observance of parameters from the product master".
    This may make it respect the GR time in product master
    Good luck with the above
    Regards,
    Ashok

  • Define start date in SNP interactive table of planned order

    hi,
    does anyone know how to control the start date and the scheduling of planned order created in the SNP interactive table?

    Hi Arieh,
    For SNP Pl.Order the standard SAP APO behavior is to control the availability date (End date).
    To control Start date you have to convert SNP Pl.Order in PP/DS Pl.Order. Then in the PPT1, production periodic view you can change by start date if you change the strategy to Forwards.
    Regards, Marius

  • Difference in Maintenance Plan date to Order basic start date

    If i creat a strategy plan and schedule, i am getting difference in PLan date in Maint plan to Basic start date. What is making this difference. How to overcome this. I need Order start date same as PLan date.
    Plz help me frnds.
    Guruprasad

    hi
    can you explain in details with your maintenance plan with the dates.Normally your call date and plan date will be different becase of call horizon ,but the order basic start date and plan date will be equal only
    kindly revert back
    regards
    thyagarajan
    your order basic date will be when you have maintenance call is generated.kindly check
    Edited by: thyagarajan krishnamurthy on Feb 25, 2009 9:46 AM

Maybe you are looking for

  • Backup Volume cannot be mounted

    Time machine stopped working for me back in July. I've looked at every post and tried nearly everything, and I cannot get it working again. The error through the Time Machine pref pane is "The Backup volume cannot be mounted." The errors in the conso

  • XML parser error in OC4J_Portal/portalHelp - XmlPullParserException

    Hi all! I've just discovered an error in \opmn\logs\OC4J~OC4J_Portal~default_island~1 referencing org.xmlpull.v1.XmlPullParserException. The error comes in un-even time intervals. Were running OAS 10.1.2.0.2 on WIN2003 server, with the Portal&Wireles

  • Adding SAN through web-security and Creating CSR for Tomcat (CUCM 10.5) to be signed by Third Party CA

    Hi Guys, Wondering if Any one has done this or could suggest the needful, We are running CUCM 10.5 cluster and currently using self-signed certificate for Tomcat. Now, we would like to get it signed by Third party CA. Just to be clear that we are doi

  • Pre-Insert Trigger not firing

    Hi, I am using Oracle 10G DS with Oracle 11G XE. I tried PRE-INSERT Trigger with the Code given by Mr Hamid. However, its not working. Though, the WHEN-NEW-ITEM-INSTANCE works fine, I wish to use PRE-INSERT Trigger only. Can you please help me. My Co

  • How do I put dropbox on my new Macair

    The only dropbox software I can find in iTunes seems to be for phone or iPad.  I want it on my computer.