Multi Plnd Order to Single Process Order

We have implemented Process Industry in our organisation (PP-PI).
Can we convert MULTIPLE planned order to SINGLE process order ? How?
If 'No' then what is the reason behind it?
Chintan Patel

Thank you Mr. Shiva & Mr. Vittal for prompt reply.
But going furhter in the scenario as under:
1) FERT, Strategy: 20 Make-to-Order
    Ind/Collective: 2 Collective Only,
    MRP Type: M0,
    Lot Size: MB,
    Procurement: Inhouse Production
   FERT has BOM which include HALB, VERP
   HALB has BOM which include ROH & VERP
2) Sales Order Entered
    Line: 10  FERT: 600000673    Qty: 2000
    Line: 20  FERT: 600000673    Qty:      3  (free qty)
3) Run MPS by MD50 on Sales Order, Line Item 10
    Result: Planned Order for line item 10 is generated
4) Run MRP by MD41 on FERT 600000673
    Result: Second Planned for line item 20 is also generated
Requirement:
Can we obtain only one planned order for both line items as FERT are same for both lines ?
Chintan Patel, Gujarat

Similar Messages

  • 02 STO 's for a single process order

    Hi All,
    Can anyone explain me whether there any problem in getting two STO's for a single process order?
    If its a problem how to generate only one STO for a one process order?

    Hi Mallika,
    can you explain your sceanrio . i am not able to understand your requirement.....
    Regards,
    Venkat.

  • Single process order spanning over multiple days...

    Hi All -
    My scenario is as follows:
    I have a semi FG C going into multiple FGs A and B.
    Receipts for A and B create dependent requirements for C on different days of a week. It would always be 2 continous days, Monday-tues or Tue-Wed and so on.
    My lot size period type is "Days - 1." So when I run PPDS heuristic, the system creates 2 planned orders to cover the 2 different dependent requirements since my period bucket is days - 1.
    We would want only 1 planned order for semi FG C which spans over 2 days of the week. To achieve this, what I did is change the lot size period type to Week-1 ( with period factor 1) which would create a single process order on the last day of the week and have the scheduler move the order and align it with the receipt of the FIRST planned order( for A or B).
    Is there anyway we can let the system do this for us? Again the requirements can be on Day 1-2,2-3,3-4,4-5 etc...but what we would like is based on when the multiple requirements are, the system create the planned order for C on the day of the requirement of the first receipt( be it A or B).
    IF Dep Reqs are on day 2-3, the planned order for C is needed on day 2. If the dep reqs are on 4-5, the planned order for C should be on day 4.
    Any inputs will be appreciated.
    Also, is there any function in the DS planning board to "Merge" 2 orders?
    Varun

    Hi
    Changing to weekly lot size is the best option.  It seems your problem is that the process order should get over (end date) before the first requirement.  In such a case, you should also maintain a rounding value/fixed lot size in material C.  Then process order will be created before the order of A or B (The first of the two) starts.  In product view it will show a surplus on the first day and it will get consumed on the next day when B is produced.
    Another way is to avoid using period factor so that heuristic creates planned order before the requirement.
    Hope this should solve.
    Nitin

  • AFS-BW Report on Multi Store Orders (MSO)

    Hi Everyone,
    We have a Sales Doc Type "ZMSO" Multi Store Order and when exploded
    creates many "ZSSO" Single Store Orders.
    In my BW report i need to show all Unexploaded Multi Store Orders (ZMSO) Quantity and Value.
    But in my Sales Cubes i dont find Multi Store Orders, i can find Single Store Orders (ZSSO).
    I checked in VBAK and there are Multi Store Orders in this table, then why ONLY the documents with Type = ZMSO not extracted into BW.
    Have anyone had this issue ? Any reasons for why we cannot extract Multi Store Orders ?
    Thanks and Regards,
    Naveen Rao Kattela

    Hi Suman,
    follows the elementary fields and their corresponding in BW.
    Name
    Data Element
    No. of Characters
    Corresponding InfoObjects
    AFS: Color
    /AFS/BWEL_COLOR
    8
    0AF_COLOR
    AFS: Size
    /AFS/BWEL_SIZE
    8
    0AF_SIZE
    AFS: Country
    /AFS/BWEL_COUNTRY
    3
    0AF_COUN
    AFS: Stock Quality
    /AFS/BWEL_QUAL_STC
    3
    0AF_SQUAL
    AFS: Requirement Quality
    /AFS/BWEL_QUAL_REQ
    3
    0AF_RQUAL
    Hope this help you

  • How to create multi garnishment order for the same garnishment document

    Hi,
    Can anyone tell me how to create multi garnishment order for the same garnishment document. I tried to copy the entry in IT0195 but the sequence field is grayed out so it will just delete the old record. What configuration should I do to make this possible?
    Thanks a lot in advance.

    hi,
    As far as I got it.
    You cannot have multiple Garnishment order but if a need arises you have to maintain it in IT216.
    For that follow this path goto PA30->pernr->194->change->Garnishment->adjustment.
    Since like order you cannot maintain adjustment also directly.
    Regards,
    Amit
    Reward all helpful replies.

  • Copy item categories condtion copier type = firm all plnd orders

    Hi
    we have issue with copy controls we are copying from previous to succeeding document sales order pricing data is copying for return order creation, but when we are changing quantity in return order it's re-determining price as per the scale .
    If we want restrict this we have used Cond copier type = "exact copy (copying reference) but it's not solving the issue.
    But we will use "firm all plnd order " it's not changing order price, If we change quantity also. It may be  solve the issue. But we doubt we can use this are not?
    Someone could  explain the Cond copier type ="firm all plnd order " means? F1 help is not avail be here. SAP CRM 4.0
    Edited by: bindhu madhavi on Oct 3, 2011 6:04 PM

    yes I can confirm what JouLes wrote. But you can only change what I told you before.
    if you can do customizing on anything else, then you should be able to do it here too, there is no authorization object for a specific IMG area or knot. either you have authorization for customizing or not.
    Are you in a developement client? In production client it is not possible to do this customizing.

  • Old cutomer order and plnd order in MD04

    in stock/reqmt list there are some customer order and regarding plnd orders, but when i look in to the customer order the respective item is not there. and the respective planned order are not taking the reference of respective customer order.
    I want to know the cause of this and how to delete them.
    Please Help me out

    Hi
    Planned order  has customer order reference only in case of MTO ( strategy group20).
    Not able to make out with your update "when i look in to the customer order the respective item is not there".
    Regards
    YMREDDY

  • Plnd order to production order

    Hi all,
    I executed a plng run in PPDS to cover independent requirements. From product view I accessed one of the plnd order and checked conversion indicator. I am trying to convert plnd order into prod order. I refreshed product view, but no new production order number is assigned. It still remains a plnd order. Where am I making mistake?
    thanks

    Please check:
    'Transfer to R/3 In-House Production' option in PPDS Global Defaults and Settings -
    Also, you can evaluate the Application Log - if it is confirmed that APO System tries to transfer Pl. Orders to R/3 but they get stuck in Queues.
    Regards,
    Sudhir

  • Subcontracting Purchase Order from ECC sent to APO creates a Plnd Order

    Subcontracting Purchase Order from ECC sent to APO creates a Plnd Order with the same Purchase Order# in APO.
    We want to influence the source of supply for this internally APO created planned order.
    For this, I would like to know what user exit can be used, I have already looked at
    (1) BADI: SOURCE DETERMINATION
    (2) CIF INBOUND EXTERNAL PROCUREMENT on APO side.
    Any other user exits or has someone worked on this scenario.
    Thanks
    Kumar

    sources of supply for planned orders can be changed with the following BADI method:
    Definition name               /SAPAPO/RRP_SRC_EXIT
    method RRP_USEX_SOURCE_FILTER

  • Variant Configuration - Unable for converting a Plnd Order to Prdn Order

    Hi Gurus,
               Please solve this, while converting a plnd order to prdn order in variant configuration i am getting the following error is
    "you cannot make an assignment to make-to-order stock"
    for fert maintained charateristics and class and class type: 300, strategy: 25, requrements type: kek,
    configuration profile created. t-code: cu41 for bike
    I created the order from customer requirements t-code:md81
    pls guide how can i convert this to prdn order
    Edited by: venkat jsr on Jan 31, 2008 6:38 AM

    Hi Gurus,
        I followed your instructions but the error is as it is only.
    Actually when I am converting Plnd order to Production Order in stock requirement list of Configurable material, its not converting.
    the error i am getting is " You cannot make an assignment to make to order stock"
    and also i am getting the following information - the component cannot be allocated to an individual stock because make to order production and engineer to order production cannot be executed with this order
    a possible cause is that you are trying to create an order with reference to a sales order / project where an account assignment to a sales order / project is not allowed in the settlement profile that is assigned to the chosen order type this is inconsistent
    Procedure : Choose another Order type.
    Please guide what i have to do for solving the problem.

  • Converting material PO text from Plnd order to Preq after MRP run

    Hello;
    I would like to know how is it possible to convert material long text to the Preq after the planned order is converted into Preq after MRP run.
    I've checked in the text linkages in SPRO but didn't the option for copy rule for plnd orders to Preq.
    Can someone tell me if it's possible, if so how.
    Ibou

    Hi
    There is no settings in standard for this, but this can be achieved by development. SAP does not provides this functionality in standard SAP because of performance issue. Please refer to SAP note 27136 on this.
    To get the text copied, you can ask ABAP programmer to implement Badi MD_CHANGE_MRP_DATA and put a logic to read text from material and copy in PR.
    Hope this will help.
    Thank you
    Anand

  • OM: Multi-select order lines to apply hold

    We are using Standard Oracle Multi-Select order lines (Ctrl or Shift keys) to apply hold and would like to pop-up an alert when any of the selected lines is having an open delivery. Appreciate any suggestions to handle this requirement. Thanks !

    These are good links for the Apply Hold functionalities.
    What we are looking for is to alert users that any of the multi-selected lines is having an open delivery/shipper.
    Need to identify the internal Line_id multi-selected by users for validating if there is an open delivery/shipper.
    Appreciate any advise.

  • Using a 2-D array Single Process Shared Variable w/ RT FIFO for comm between a Deterministic and non-deterministic loop on an RT Target

    Our problem is that we currently use a 2D array to store CAN data on a Real-time Target. The array is 20 elements of 3 byte elements as so:
                    0              1              2
    0              [byte]   [byte]   [byte]
    19           [byte]   [byte]   [byte]
    These values are passed between a Deterministic Timed (DT) loop where they are set and a Non-Deterministic Timed (NDT) loop where they are read and passed into a Network Published Shared Variable (NPSV) for communication across the network to a Host PC. I have insrted an image for illustration, pardon the size.
    Currently to pass the data between the DT and NDT loop we are using a Global Variable (GV). To improve the system we have attempted to replace these GVs with Single Process Shared Variables (SPSV) with an RT FIFO enabled.
    To create the shared variable I simply right clicked the GV of interest and selected create Shared Variable Node form the drop downs. At this point LabVIEW presented me with a 2D NPSV within a new Library hosted on the RT Target. I then selected this new NPSV from the Project, changed it to a SPSV, and enabled a single element FIFO. This variable was initialized with a default value for the size described above and then used in our code for the DT to NDT communication, and conversion to a corresponding NPSV for sending to the Host.
    When I went to run the code I noticed that the variable was in fact 2D, however its size was only 2 elements of three bytes each, in other words only two of the row indices were populated and the other appeared as uninitialized. in addition, this data had no resemblance to the set initilazation value. This was also how the variable was presented on the host side of the network after tranfer into a NPSV.
    The peculiar part is that If I change this SPSV to a NPSV and then try to change it back, I receive an error saying the type is not supported for SPSV with an RT FIFO enabled. I have to disable the FIFO (which defeats the entire purpose) in order to successfully compile! I am unclear as to what is the bug in this case. Should I not be allowed to create the original 2D SPSV with a single element RT FIFO enabled without receiving an error? Or if this is okay how do I fix the problems associated with the variable after being allowed to create it?
    I have found the following discussion in which a user states “The only limitations for custom controls is the ability to use it with RT FIFO enabled on a network-published shared variable”. Is this also true for SPSV? I have not found any documentation explicitely stating this for SPSV, though it is stated for the NPSVs.

    Martin,
    RT FIFOs don't support Multi-Dimensional Arrays, which would corroborate the issues you're seeing.  You can break up the 2D array into 1D arrays by reshaping the array, then you'll be able to use the RT FIFO enabled variable, just set the array size to the total number of elements (20*3 = 60).
    You can also pass the 2D array via pre-allocated queue, or using a Functional Global.  We have a reference example for a circular buffer using Functional Globals here.

  • Is it possible to use all the render service in a single process?

    is it possible to use all the render service in a single process?, my requirement is to start the process by email or by workspace and the form shud be available in both pdf and html form for the users.Please suggest a way to implement this, really struggling on this.
    Please give me a step by step if possible
    Reagrds,
    Vinod

    I guess it depends on how you want to present the choice of html/PDF to the user. One way would be to render the form as HTML  for the task, and provide the PDF as an attachment. When they open the task, the form appears in HTML, but they could optionally open the attachment and submit the PDF. This would complete the task, but the HTML form would still be open in Workspace, which would probably confuse the user.
    Another way would be to create a dynamic multi-page form - page one asks the user if they want HTML or PDF. When they submit that, the HTML or PDF form is opened. I'm not sure how to implement this. Hopefully other community members  have some suggestions.

  • How to create multi-folders in a single folder in numbers

    how do you create multi-folders in a single folders. I have multi files orginized by month, but now i need to group it into a single folder by year.

    See this link:
    http://apex.oracle.com/pls/otn/f?p=31517:107
    Denes Kubicek
    http://deneskubicek.blogspot.com/
    http://www.apress.com/9781430235125
    http://apex.oracle.com/pls/otn/f?p=31517:1
    http://www.amazon.de/Oracle-APEX-XE-Praxis/dp/3826655494
    -------------------------------------------------------------------

Maybe you are looking for

  • Runtime error in ALV demo

    HI, Runtime error in the below  report as internal table IT_FIELDCAT is empty after the execution of FM REUSE_ALV_FIELDCATALOG_MERGE. Please tell me how do i rectify this error. REPORT  ZMY_ALV_COLORING_CELLS. TYPE-POOLS SLIS. DATA: BEGIN OF itab OCC

  • M-Audio Ozonic and LE7

    Hi all ... Newbie question here ... I'll cut to the chase. How can I get LE to recognize my keyboard? It has a built in audio interface and I've connected it via fire-wire. Any help would be appreciated ... I have no sound. I've signed up for Pro-car

  • Replicating partner function (VE=sales employee) from CRM to ECC

    Hello, we managed to replicate the ECC customers and contact persons to SAP CRM. Now we also want to replicate to CRM the partner functions (VE = sales employee) of ECC that are linked to the customer in the sales view. When I replicate the object cu

  • Problem with BLOB data type and acute characters

    Hi all, I have an issue related with BLOBS cols: I have table A with a BLOB column and I need to insert that data into another table B, the thing is I use dbms_lob.read() that returns data into a RAW variable and then I convert it to a varchar2(with

  • Using mates Imac internet connection?

    HI Going to my mates tomorrow, he has an imac 20 etherneted into a router and no wireless set up as yet. Question, if i take my MBPro round there to do some holiday research, can my MBP connect to his Imac somehow, and use the internet through his Im