Hi Gurus,
Is there any possibility to do multiple billings for one contract / one project from Project Level.
How can we perform for Milestone / RRB?  I appreciate with possible steps / process.
Regards
Naveen

Hi Naveen,
If i understood your query correctly, yes it is possible to do multiple billings for a single project, rather a single sales order.
As far as Milestone/RRB process is concerned, i would suggest you to go through SAP Help or search the forum. The query is very basic in nature and i am sure you will find the required answers in SAP Help.
You can revert with more specific queries once you are done with SAP Help.
Regards,
Gokul

Similar Messages

  • Multiple Agreement for Single Project

    Hi All,
    In our Implementation client generally gets multiple agreements for a single project. How to specify the Agreement Reference when we are creating an Event for billing? By the way have set up the funding option at the Project Level.
    Thanks in Advance
    Saptarshi

    Hi
    The problem you are raising has no solution by standard functionality.
    Oracle promised to solve that for the first time in release 12.1 that should be available during 2009.
    There could be customized solution which involve several parts:
    Add a DFF on the event, so user can enter the agreement number.
    Guide the user to run the GDI process for range of projects with the parameters - project number and agreement number
    Develop a billing extension called on pre-processing of the GDI and another one called on the post processing step of the GDI.
    The pre-process billing extension will put all project events that are not of the requested agreement on Hold, and any different agreement should also be "put aside in a non billable situation". The post process billing extension will release the hold from the events, and return the agreements to "normal".
    I can admit such customization is ugly and risky. However, we have done it and it is working for us on production for several years. I have presented a paper regarding that on Collaborate 2007. You may look for the paper called: "Is it possible to invoice by contract using Projects Billing", on the OAUG web site.
    Dina

  • How to integrate multiple applications for single project as single appl

    Hi,
    I'm struggling to find out about that how to combine all the applications developed by my team members.
    We all created each application having many pages, how to combine all this pages to create as a single appl.
    Can anyone please tell me how to do it?
    Thanks,
    Sundar

    My solution still stands. Search the docs.
    This presentation might assist: http://www.sagecomputing.com.au/papers_presentations/ADF%20Architectural%20Patterns%20-%20LongBeach%20ODTUG%20minus%20pics.pptx
    CM.

  • How to uploade multiple flatfiles for single transaction using BDC?

    How to uploade multiple flatfiles for single transaction using BDC?

    Hi,
    You need to upload all data files into an internal table first either using OPEN DATASET (application server files) or GUI_UPLOAD (PC files).
    Then loop at the internal table and call BDC transaction to process the data.
    Regards,
    Ferry Lianto

  • Set multiple passwords for single PDF

    Hi All,
    Do it is possible to set multiple passwords for single PDF i.e) a single PDF can be accessed using predefined passwords. It would be great if any one could can help me .
    Thanks
    Augustine

    Thank you.
    Do you mean different IDs can be used for a single PDF and can make the PDF protected.
    Regards
    Augustine

  • Multiple Alerts for Single error in interface is a design not issue with XI

    Hi,
    This is constraint of alert mechanism in XI.
    You get multiple alerts for single error,the reason is that since XI will try multiple times to process a failed message so each time it fails in its tries it will send an e-mail.to stop this the "Suppress multiple alert" box is checked but what it does is that it stops all the alerts of that specific rule until the first one is confirmed.Personally i myself (and other experts too) suggest to leave the box unchecked coz its better to get tons of mails for a specific error rather than not getting any e-mail and thereby wasting time in tracking/solving the issue resulting in revenue loss to client.
    As per above comments is it possible to write an ABAP code so that we can stop multiple alerts to be sending to inbox. I am sure if we can delete message from some table then we can stop sending multiple messages to alert inbox and to the subsequent mail id also. I am not sure how alert being generated. I know where they get logged in this table sxmsalertlogger. If someone know how it works in background please let me know the table names.
    Regards
    Ria

    Hi Gaurav,
    You can personalize the way in which you receive alerts.
    Simply choose Personalization to make individual settings for your alert inbox. You can determine a substitute who will then receive the alerts. In addition, you can choose whether alerts are sent to you time-independently or time-dependently. The default setting is that alerts are sent time-independently to your alert inbox and via e-mail when they occur. You can additionally select the communication methods FAX and SMS for time-independent alert notification.
    If you want to receive alerts only on certain days for a certain time, simply select the option for time-dependent sending of alerts and choose Create to create a new table entry. You can then choose the corresponding factory calendar, the time interval, and communication channel. Alerts that arise during this time frame will be sent in any case to your alert inbox. If you have also selected other communication channels, the alerts are additionally sent to you using these other channels. 
    This above text is from SAP help, do you think by changing anything in personnalisation i can stop multiple alerts. I have some issue with Personalisation link so was wondering would be worth to get tht personalisation issue resolved.
    Regards
    Ria

  • Partner Function Queries Multiple Partners for Single Partner function SO

    Hi Experts
    Is it possible to  enter multiple partners  for Single partner Function in SALES ORDER
    For Ex : We have created Z1 as a Partner function for Sales Executives : and Sales Executive 1 , Sales Executive 2 Sales xecutive 3 etc as sales Partners for Z1 partner Function .
      Now Is it possibe to enter for Z1 -
    sales Exeutive 1
                                                Z1----
    Sales executive 2
                                               Z1----
    Sales Executive 3............
    I would be greatful if you repond the same at the earliest
    Thanks
    Rashmi K

    Hi Rashmi,
    The requested function is possible.
    In the customizing of partner function, you could set the field Unique as blank. Then you could enter multiple partners for same partner function.
    IMG->SD->Basic functions->Parnter determination->Partner Functions
    Hope it helps.
    Thanks and best regards,
    Smile

  • Best Practices for multiple authors using single project?

    We are having many issues, particularly with moving, renaming, and multiple check out warnings.  We have a single project with many authors and it seems like RH is not designed to work that way. There is an article in the RH devnet-archive in an article entitled "Sharing RoboHelp Project Among Multiple Authors" that says"
    "At first there may be the temptation to let every author work on every file in a project.  This is certainly not a best practice. Regardless of source contraol, it is always best to designate certain authors as owning certain content-related sections, folders, or topics within a project -particulary at the folder level."
    This statement, and our experience seems to indicate that RH is not a true CMS as we had envisioned.  What are the best practices for this scenario to avoid stepping on each others toes and having problems with source control.

    I have moved this to the source control forum for the gurus there to answer.
    Meantime I must admit I read that statement the same way as you first time. However, on rereading I think what the author is saying is not that what you want cannot be done, rather it is best practice to guide authors to work in discrete areas.
    I will leave it to the author or another guru to give you a more complete answer.
    See www.grainge.org for RoboHelp and Authoring tips
    @petergrainge

  • Multiple TOCs for One Project

    Is it possible to split the topics in one help project into
    two toc (hhc) files? I have a master project that merges about 53
    chm files. Some of the slave projects are rather large and over the
    years have had several types of information added to them. The
    information in the projects are related to each other, but they
    need to be organized separately in the master TOC. Splitting the
    projects themselves is not a good solution. I would like to have
    multiple hhc files for the projects so that the topics can easily
    be inserted in their logical place in the master TOC.

    Hi,
    I am TW working jointly with another TW on a huge multifirm
    project for a same client. He is well versed in RH, while I am a
    beginner (with using RH) not with TW. He and I each produce large
    parts of what will be merged into a single huge context sensitive
    .chm file. Having experimented a bit with possibilities such as the
    ones you are exploring, I thought we could use it for our project.
    But the other TW felt we would have problems down the road.
    Just to confirm what John says. But then, I also am not
    adding anything positive by way of solution. Hope somebody else
    reacts to these two successive negative answers, and comes up with
    help for you.
    Daniel Garneau, CTM, CL
    Technical Writer, Canada

  • Tolerance Limits: Multiple Invoices for single POs, Single Invoices for Multiple POs

    Hi,
    I'm currently looking at tolerance limit configurations, primarily the DQ (Quantity) and PP (Price) tolerance keys and had a couple of questions where you have the scenario of multiple invoices or multiple POs.
    1. If I had multiple invoices for a single PO, collectively they match the quantity and price on the PO; When I enter the first invoice into SAP it will be well below the lower price and quantity limit of the PO as it is one of multiple invoices to be entered. My question is what happens to the invoices in SAP, do you still post them despite the error message and they are just blocked until collectively the invoices match the quantity/price of the PO?
    2. If I had an invoice that related to multiple POs, when entering the invoice can I link this to multiple POs?

    You don't use user exits or enhancements for this.  Use a data transfer routine and assign it to your item level copy control config.  Spilt keys are controlled by setting the value of VBRK-ZUKRI.  Otherwise, you can use multiple payers or addresses to control it.

  • Multiple values for single field

    hi
    In order to upload Purchase order details, how you handle multiple values for a single field? 
          Eg: Item field may contain no. of values for a record

    Hi,
    It is generally taken care using BDC's by Table Control, and if you are using BAPI's then there are tables for ITEMS.
    Regards,
    Atish

  • Create Multiple tasks for Single Item in List using state machine workflow in sharepoint

    Hi,
    I want to create multiple create tasks for Single Item in List based on Assigned to column using state machine Workflow through visual studio
    Here Assigned to column allows multiple users. so i have to create task for every user based on column .
    I'm trying for this but i didn't got any solution
    Please provide solution for this.

    Hi,
    According to your post, my understanding is that you wanted to allow multiple users to approve.
    There are some articles about creating parallel tasks in state machine workflow, you can have a look at them.
    http://www.codeproject.com/Articles/477849/Create-Parallel-Task-in-State-Machine-Workflow-in
    http://msdn.microsoft.com/en-us/library/office/hh128697(v=office.14).aspx
    http://social.technet.microsoft.com/Forums/office/en-US/b16ee858-4360-479a-a686-4ee35b7be9db/sharepoint-2010-workflow-creating-multiple-tasks?forum=sharepointdevelopmentprevious
    Thanks & Regards,
    Jason
    Jason Guo
    TechNet Community Support

  • Use of multiple Applications for single webdynpro component in ABAP WEB DYNPRO

    I am working on a object which have multiple webdynpro applications for single webdynnpro component.How to assign a different functionality to each application bcoz when we right click on webdynnpro component and select create webdynpro applications ,it just creates a application how so we assign diff functionality to each of them .Also in the parameter tab of the webdynpro applications ,there is a diff config id mentioned for each application.what is its relavance

    Hi Sam,
    Different functionalities for a single webdynpro component can be achieved by many ways. Among them is the use of multiple applications. Say for example if you want different views/windows to be displayed at the start up, you can achieve it by specifying at the default window, for each every webdynpro application.
    And if you want control the fields, say for example you want to display input fields as editable for one application and read only for other application, you can achieve it through application parameters. Based on parameters, in HANDLEDEFAULT method of window controller , you can specify the type of behaviour , whether it has to editable or not based on parameters and same can be used at context binding of UI properties. 
    Application configuration can be used for personalization.Web Dynpro ABAP Application Configuration. This tutorial would help you understanding the concept much better. There can be multiple application configurations for a single application.
    Regards,
    Harsha

  • Multiple MouseEvents for single click

    Hello,
    I have created a reusable component based on a JPanel.
    Our company uses my component in several Swing applications, all of which use a JFrame.
    My component has a mouse listener for mousePressed events.
    Recently a new app, also based on a JFrame, has started to use my component. In this new Swing app, my component's mousePressed listener gets called THREE TIMES for each mouse pressed.
    In all other apps, if the user presses the mouse once, I get only ONE call to my mousePressed listener.
    Looking at the stack traces into my mousePressed() method I notice this:
    In the apps where mousePressed() is only called once, the stack looks like this:
         at java.awt.Component.processMouseEvent(Component.java:5131)
         at java.awt.Component.processEvent(Component.java:4931)
         at java.awt.Container.processEvent(Container.java:1566)
         at java.awt.Component.dispatchEventImpl(Component.java:3639)
         at java.awt.Container.dispatchEventImpl(Container.java:1623)
         at java.awt.Component.dispatchEvent(Component.java:3480)
         at java.awt.LightweightDispatcher.retargetMouseEvent(Container.java:3450)
         at java.awt.LightweightDispatcher.processMouseEvent(Container.java:3162)
         at java.awt.LightweightDispatcher.dispatchEvent(Container.java:3095)
         at java.awt.Container.dispatchEventImpl(Container.java:1609)
    where as when mousePressed() gets called multiple times, the stack trace shows this:
         at java.awt.AWTEventMulticaster.mousePressed(AWTEventMulticaster.java:218)
         at java.awt.Component.processMouseEvent(Component.java:5131)
         at java.awt.Component.processEvent(Component.java:4931)
         at java.awt.Container.processEvent(Container.java:1566)
         at java.awt.Component.dispatchEventImpl(Component.java:3639)
         at java.awt.Container.dispatchEventImpl(Container.java:1623)
         at java.awt.Component.dispatchEvent(Component.java:3480)
         at java.awt.LightweightDispatcher.retargetMouseEvent(Container.java:3450)
         at java.awt.LightweightDispatcher.processMouseEvent(Container.java:3162)
         at java.awt.LightweightDispatcher.dispatchEvent(Container.java:3095)
         at java.awt.Container.dispatchEventImpl(Container.java:1609)
    Does anybody have any idea of why AWTEventMulticaster would be on the stack for one app and not for another?
    And how can I prevent getting called multiple times for a single mouse click?
    Thank you,
    Ted Hill

    You don't understand. My JPanel implements the MouseListener interface and its mousePressed(MouseEvent ) method gets called THREE TIMES on a single mouse click. Normally it should only be called ONCE.
    It seems that the app that is using the JPanel extension has somehow registered it as interested in mouse events MULTIPLE TIMES.
    I've never seen this before in Swing and was wondering if anyone else has.
    Thanks,
    Ted

  • GRC AC 10- Multiple detour for single stage path

    Hi Experts,
    I wanted to know about a possibility or view. Do you know anyway where we can have multiple detour activated(like first detour 1 then detour 2 check) for single stage.
    Actually once we click on routing rule, we get only select single detour selection option.
    Please suggest idea.
    (I would like to update that we do not want system to have multiple level of approver but only single role owner stage).
    Final solution is creating custom detour having ability to handle multiple scenario but we are looking for no custom initiator)
    Regards,
    Nishant

    Hi Nis,
    unfortunately in standard solution only one detour path can be added to single stage.
    When we had such a challenge, like you described, we simply used custom initiator and this is truly the best option to go.
    In our case we wanted to have different path (detour) for roles with special attribute an in the same time different path in case sod issue occurs. In other words we wanted to have 2 detours condition on one stage like you want to have. The option that suites our needs in the best way was to have custom initiator rule.
    Filip

Maybe you are looking for

  • IPhone won't play music imported from CDs or mp3s not downloaded from itunes

    When I first downloaded iOS 7, all of the music I had in my iTunes synched to my iPhone, but now new CDs I just imported and previous songs I imported from CDs won't synch (I've tried over wifi and usb).  When I click on songs on my phone that were f

  • Dynamic Table Selection function module

    Dear Friends,   We have got critical requirement on Custom BAPI function module :      we have to pass one field name of table and table name : Eg (Matnr and MARC).      we have to get table contents w.r.t field name of table and table : Has to displ

  • When I connect my iPad to my new Mac Pro, I can't see my pictures

    When I connect my iPad to my new Mac Pro, I can't see my pictures on iPhoto in Mac Pro under devices.I want to import my photos from iPad to Mac Book. Can you please help me? Thanks and regards,

  • GR cancellation question

    Hello All, We are working in classic scenario Server 5.5 with GR in SRM. The business case is like this: An user created a GR in SRM for more quantity than PO, the invoice is posted in R/3 now its been realized mistake. Can now the invoice be reverse

  • Why are images two-sided in Motion 5?

    I'm working in '3D mode' and I'm rotating images much like the letters on Wheel of Fortune. Except that when an image rotates beyond 180 degrees it is still visable (yet reversed). In my experience, 3D polygons are one-sided by default. Any thoughts?