Multiple Planned orders

Dear Guys,
why mrp is generating multiple ( 2 nos) planned orders
lot size is mothly lot size, Rounding profile is not maintained, mts strategy -10, mixed mrp in mrp3 is blank, Individual/coll im mrp4 view is also blank, lot size is ex
my requirment is one planned order should be generated for total quantity (pir + safety stock)
pir : 1593 nos
avbl stock is 0
safety stock : 618
after mrp
one planned order for 1600 nos
other planned order for 611 nos
pir  qty : 198 nos
avbl stock ; 275
safety stock : 278
after mrp
one planned order for 200 nos
other planned order for 1 no
kindly help me in this regard
Thanks and regards
murali

Dear,
Check the settings for MB in OMI4,
Then Lot size should be EX.
Check mrp group assigment in mrp 1 view also in OPPR?
Also check work center  overloaded at that time,it is creating another order at a different time?
Regards,
R.Brahmankar

Similar Messages

  • Multiple planned orders in MRP run

    Hi All
    I have a requirement where I need to create multiple planned order for the same material during MRP run. I understand that once I run MRP a planned order creates. If I run again for the same material, the quantity will be changed for the same planned order. Do we have any configuration so that system creates multiple planned orders for same material for each MRP run.

    Hi Adithya
    Planned orders may be changed by MRP until they are firmed. Therefore, what you need to do is to firm the planned orders after the MRP execution.
    You can use for example, transaction MD19 to mass firm planned orders after each MRP run.
    Otherwise, you can user BAdI MD_PLDORD_CHANGE to automatically firm the planned orders created by MRP.
    BR
    Caetano

  • Is there any provesion to convert  multiple planned order to one PR

    hi,,
         i want to know is there any provesion to convert multiple planned orders to one PR .let it may create as different line item in PR. if is there please let me know
    thanks in advance
    regards
    madan

    Hi madan,
    i dont think there is any way of clubbing multiple planned orders into single PR.  Like Taj suggested, you could decrease the number of planned order created thro MRP run by working on different strategies on your lot sizing key / procedure. 
    Also, i am assuming here that you want to club the planned orders of a single material into a single PR and also it is no way related to different account assignments. 
    The other way possibly u could do it is, do a Z programme and modify your MD15 transaction.  This idea is bit vague, possibly the forum could build on it.
    reg
    kiki

  • Multiple planned orders for a requirement

    Hi,
           We have PPDS MRP with NEW shelflife w/ lot size profle run for product and produces multiple planned orders for the the requirements.
    I have a requirement of 4,750 and 14,976 in the system and available stock 86,966.
    The system creates two planned orders with 34,632 and 26,771 PCs.
    Why is the system creating two order instead of one??
    The min. lot size is 1876 and rounding is 936.
    can somebody tell me what factors the system is considering??
    Thanks.

    Hi Visu,
    Which lot size procedure you are using , please check in lot size tab in Product master, it should be lot for lot.
    if it is lot for lot , please change it to by period and weekly , is it change the planned order quantity ?
    Manish

  • How to reschedule multiple planned orders ?

    Hello guys..
    The rescheduling can be done manually via transaction MDAC/ report SAPMM61P.
    MDAC gathers all parameters necessary for function module MD_SET_ACTION_PLAF. In MDAC only one planned order can be schedule.
    I want to create the report in which, the planned order number should be replaced with selection criteria for multiple planned orders. The other fields should be the same as in transaction MDAC.

    hi,
    there are two ways of doing it but both needs technical person's help:
    1. switch off back ward scheduling - find out the program which is triggering back ward scheduling and make it inactive.
    2. write a code in MV45AFZZ, SDTRM001 stating that when ever system is proposing back date at that point of time it should trigger todays date as Material Availbility Date.
    then no need to change manually to todays date.
    hope this should help you.
    please check the same with ABAPER and update the forum
    regards,
    balajia

  • Convert multiple planned orders to single production order

    Dear All !
    In our business, same component is used for manufacturing multiple items. In a sales order multiple items are booked. When we do MRP RUN, system creates multiple planned orders for each line item. We can run only one production order as for every item order quantity becomes very small and we cannot process that lot. To have a sizable lot quantity we need to combine all planned orders into a single production order.
    Can someone please help.

    Govinder,
    Define those components for collective processing. You need to define "2" - for Field Indv/Coll in MRP4 view of those material master and you can have daily/weekly/monthly lotsize defined for those items.
    Regards,
    Prasobh

  • Combining multiple planned orders into single purchase requisition

    Hi Gurus,
    could anyone please tell me how to convert multiple planned orders generated during MRP run into a single purchase requisition? Also, is there any other way of getting single purchase requisition fcreated after MRP run for a procured item which is part of multiple BOMs?
    Thanks and regards,
    Abhik

    Hi,
    Conversion of Multiple planned order to single Purchase requisition is not possible.
    But you can have a single Pur.Req for Multiple requirements.
    You can do this by:
    1. Individual/collective indicator "2" collective requirements for the Header Material so that you will get your dependent requirements clubbed together.
    2. Period Lot sizing : Daily/weekly/monthly Lot size so that system will club the entire period requirements and propose a single lot.
    3. for low value materials you can have Reorder Point planning also.
    Hope this helps..
    Regards,
    Siva

  • Convert Planned orders in single shot with a Single PR

    Hi,
    Is it possible to convert the multiple planned orders into a single Purchase Requsition with in a single transaction.
                          Existing SAP :- MD 16 >Select Planned Order>Convert to PR of a single Planned Order
    I am looking for the same like above for multiple planned orders.
                           My Requirement :-
                                      a) Materials from 001 to  030 under one MRP Controller.
                                      b) Planned Orders  001 to 030 for the above materials          
                                      c) Want to Raise a single PR for 30 planned Orders of 30 Materials.
    So please Let me know the solution/Suggestion/If it is not a best practice.
    Cheers,
    Anil.

    Govinder,
    Define those components for collective processing. You need to define "2" - for Field Indv/Coll in MRP4 view of those material master and you can have daily/weekly/monthly lotsize defined for those items.
    Regards,
    Prasobh

  • Conversion Planned Order - Purchase Requisition

    Hi Gurus,
    how can I convert one or more Planned Orders in only one Purchase Requisition?
    Thanks,
    Marco

    Hi,
    1.  convert planned order into purchase requisition individually using transaction MD14
    2.  Use  T code MD15 to convert  planned orders  Into PR collectively ( for multiple planned orders)
    Regards
    Hari
    Edited by: hari mukku on Mar 26, 2010 5:05 AM

  • Consolidation of Planned orders after CTM planning run

    Hi everyone,
    We use CTM planning engine and create planned orders for the unfulfilled demand. Since Demand is coming from various locations multiple planned orders are created at the supply location. But the requirement is that all these planned orders need to be consolidated to 1 planned order.
    How can we acheive this without disturbing the existing pegging relationships?
    For example:
    Current scenario:
    3 planned orders at location X based on the demand from locations A, B and C. Then a pegging relationship exists (Purchase Requistions) between A and X; B and X; C and X.
    Requirement:
    Above 3 planned orders need to be consolidated to 1 Planned order and still the pegging relationship to supply the demand locations should exist.
    Please let me know if anyone has similar business scenario and has working solution approach
    Thanks

    Hi,
    You can increase the lot size to club your demand requirements.  You can also try using period type lotsize to club daily, weekly, monthly requirements.
    Regards
    R. Senthil Mareeswaran.

  • Collective conversion of planned order to one production order

    Dear all,
    1. I have N number of pld ord for same material so i need to convert as production order with cumulative quantity.
    Because to reduce  Issing and confirming and receiving of number of production orders.
    2. I need to create Number of production order with diffferent material numbers  in one screen with different production order number.
    Because per day i need to create more number of production order with different material number. If i create one by one it will consume more time as well as its not practical possible for our business scenario.
    Pls let me know any standards are available in SAP.
    Regards,
    S.Suresh.

    Dear Suresh,
    You can convert Planned Orders into Production order collectively as a mass maintanance in CO41 Tcode.
    Revert if any doubt in case using above tcode.
    Further if you wish to have one production order against multiple planned orders it is not possible as per Standard SAP.
    You can convert to each planned order into individual production order not to single production order.
    If you wish clubbed production order then better you use Individual / Collective Indicator  as
    2     Collective requirements only
    Then you will get cumulative planned orders only against each material and you can convert all of them cumulatively to production orders in CO41 as a mass maintanance.
    Hope your problem resolves.
    Regards,
    Tejas
    Regards,
    Tejas

  • Regarding Planned Orders

    Hi All,
    1) If i create a Production order by converting a Planned Order,we will see the details of Planned order in the Production Order.
    Now when i want to view again the Planned order details,if i enter Planned Order number in table-PLAF, i am not able to view any details and getting message no data available. May i know the reason?. Does it mean once a planned order is converted to Production order,its data in PLAF is deleted ?.
    2) I have a Production Order with Quantity of 200 EA,and only one Planned Order number is mentioned in the Assignment Tab of Production Order.
    Does it mean that the Planned Order mentioned here is of 200 EA or does this production order is created with 2 to 3 planned orders whose total quantity is equal to 200 EA. I want to know this,because i cannot see the Planned Order details no more.
    Thanks in advance.

    1) If i create a Production order by converting a Planned Order,we will see the details of Planned order in the Production Order.
    Now when i want to view again the Planned order details,if i enter Planned Order number in table-PLAF, i am not able to view any details and getting message no data available. May i know the reason?. Does it mean once a planned order is converted to Production order,its data in PLAF is deleted ?.
    Yes, once the plan order is converted into production order, then plan order is offset ( dleted in PLAF, you can't see the plan order any more in PLAF
    *2) I have a Production Order with Quantity of 200 EA,and only one Planned Order number is mentioned in the Assignment Tab of Production Order.*
    Does it mean that the Planned Order mentioned here is of 200 EA or does this production order is created with 2 to 3 planned orders whose total quantity is equal to 200 EA. I want to know this,because i cannot see the Planned Order details no more.
    In std, you can create a production order with reference to one plan order only, you can't assign multiple plan order into single production order,
    But you can convert single plan order into Multiple production order

  • Planned order to multiple Production Orders

    Dear Gurus,
    I would like to split planned order qty and convert into multiple production orders in CO41, is there any user exits or BADI which makes it possible?
    Many Thanks!
    //Sreenivas

    try the following function module
    CO_AB_CONVERT_PLANNED_ORDERS
    CO_SD_PLANNED_ORDER_CONVERT

  • Where/ how do I set SNP to create Planned orders with multiple line items?

    Hi
    Currently our SNP is generating planned orders on a daily basis, it creates a single order with a single line item per location.
    Where/ how do set SNP to create planned orders on a daily basis to generate a single order with multiple line items per location, so therefore one planned order with multiple line items for a single location.
    Thanx
    Keegan

    Hi Keegan,
                   In SNP (APO) it is not possible to create order with multiple line items.
    But you can do some settings so that while planning system can do aggregation and disaggregation.
    But your requirment should be set on Aggregation/Dis-aggregation logic.
    Please follow the follwing links:
    http://help.sap.com/saphelp_scm2007/helpdata/en/2c/c557e9e330cc46b8e440fb3999ca51/content.htm
    Aggregation:
    http://help.sap.com/saphelp_scm2007/helpdata/en/42/f731d078e73ee4e10000000a1553f6/content.htm
    Disaggregation:
    http://help.sap.com/saphelp_scm2007/helpdata/en/a6/ebefaf32e22e468355da304cc59387/content.htm
    Please be sure that the setting of this logic will be at planning area level.
    You can't change aggregation/disaggregation logic further.
    Regards,
    Santosh

  • Multiple sales order in to one planned/production order

    hello,
    anybody pls help me. my scenario is make to order with configurable material. in this is it possible to create multiple sales order in to one planned order or production order. my client is asking this requirement. he wants to convert if the characteristics are all same sales order want to convert in to one planned or production order. pls suggest me how to do this.
    thanks & regards
    bhakta

    Hi,
    The feature for combining the Sales Orders based on the Charecteristics is available on in Industry Specific Solution - Mill Products (IS-Mill).
    Otherwise, in standard SAP you can not do that..
    "Material Variants" could be an alternative for this..
    Regards,
    Siva

Maybe you are looking for

  • Certificate for Portal and BackendSystems. What do I have to take careAbout

    Hello, I would like to buy a certificate for the secured HTTP but I don't know what I have to take care about? Where do you buy your certificates? Can I use "wildcards"-certificates for the portal and the backend-systems. Is there a good shop for buy

  • Itunes 5 CD Installshield Error?

    Hi I have just got my black nano and have put the cd rom in it says it can't install due to an installshield error. What can I do now? and is this the reason why itunes 5 wont play songs on my computer? Greg

  • OpenSSH 4.4p1 packages with PAM support for Solaris 9, 10

    As mentioned in a previous post* , I've compiled OpenSSH packages with PAM support for Solaris 9 and 10. They've since been updated to version 4.4p1, and are compiled against a static zlib (1.2.3) and OpenSSL (0.9.8c). You can find them here: http://

  • Removing icons from menu bar in webi

    Hi Bo gurus, I have a user , user donot want to see  track,filter,drill,scenario icons  in right side top of the webi report,Is there any way to achive this. Any suggestions would be appreiciated. Regards, Mahesh

  • Blob data and upgrade

    I'm going to be upgrading from Oracle 9 to 10 (or possibly 11), and we have a lot of BLOB data. Is there any thing that I should be aware of? I actually am going to do this on a new system, so I'll install 10 or 11, and then put the data over (please