Hi Experts,
I have scenario where bottleneck resources changes with time. Lets say that I have two workcenters WC1 & WC2. Operation 10 will be performed through WC1 and operation 20 will be performed through WC2. SFG1 is input material for operation10 and FG1 is output material through WC2. So SFG1 will be processed through WC1 & WC2 and output material is FG1. Operation 10 & 20 are sequential operations. WC1 & WC2 have the same scheduling time for both the operations 10 & 20
Now, WC1 runs in three shifts in May'10 and WC2 runs 2 shifts in May'10. So WC2 is bottleneck resource in May'10. In June'10 WC1 runs in two shifts and WC2 runs in three shifts so WC1 is the bottleneck resource in June'10. Simply, bottleneck resource can be either WC1 & WC2 depends on time.
So in my routing I have two operations and operation 10 contains WC1 & operation20 have WC2. Further, we created Production Version (PV) and CIFed as PPM. When converting PP/DS PPM to SNP PPM I can chose only one mode so only one work center (resource) in one PPM and another work center in another PPM. We need both workcenters in one SNP PPM.
Could any one guide to meet this scenario.
Thanks,
Naveen
Edited by: Wilian Segatto on May 14, 2010 11:54 AM

Hi Bandana,
I am trying the same but I am not able to create single Resource,
Would u plz briefly explain me what parameters u are providing,
Thanks,
Radhey

Similar Messages

  • Converting PPDS PPM to SNP PPM

    Hello,
    On converting a PPDS PPM to an SNP PPM which has multiple activities(operations).  Is there a way to generate the SNP PPM the same number of activities included in the PPDS PPM to capture one Resource for each SNP PPM.  Or it has to be converted multiple times?
    Thanks.
    Edited by: Wilian Segatto on Aug 18, 2010 3:19 PM

    Hi,
    Below is an example:
    PP/DS PPM A
    Activity 1 - Resource A
    Activity 2 - Resource B
    Activity 3 - Resource C
    If PP/DS PPM is set-up like the example above, can this be converted to 3 different PPMs for the 3 different resources in one conversion?  Or i would need to do the conversion three times to generate the SNP PPMs (examples below)?
    SNP PPM 1A    
    Activity 1 - Resource A
    SNP PPM 1B    
    Activity 1 - Resource B
    SNP PPM 1C    
    Activity 1 - Resource C
    SNP PPMs are set-up per resource to monitor utilization and capacity per resource.  Also, resources are set up per production line in ERP.
    Thanks
    Edited by: pipsquik on Aug 17, 2010 3:03 AM

  • Resource "NOT SNP RELEVANT" not working

    Hello All,
    We are having Multi mixed resources in APO. These resources do not have "NOT SNP Relevant" flag set. So they show up in SNP PPMs when we convert from PPDS PPMs.
    We now want to remove resource from SNP PPMs and hence deleted the SNP PPMs and marked the resource as "NOT SNP RELEVANT". We again converted PPDS PPM to SNP PPM but we still the resource coming in SNP PPM even after checking the flag in the resource.
    Has anyone come across this issue?
    Please advise.
    Thanks,
    Sanju

    Kumar,
    This helped solve this problem. I maintained the flag in all the planning versions and it worked fine.
    I have another PPM for a different plant and the problem here I am facing is even when the "not SNP relevant" is unchecked the Resource is not seen in SNP PPM when converted from PPDS PPM. It is a multi-mixed resource.
    I am wondering if it a setting in the resource that would be causing it to drop from the SNP PPM. Any idea what could be the possible reasons.
    Thanks,
    Sanju

  • Upload single level variable cost in SNP PPM in mass by MASSD

    Hi experts,
    I am trying to upload single level variable cost in SNP PPM in mass by MASSD by following selections:-
    Selection
    Object Type:- PPM
    Selction Criteria:-
    Component:- Plan        Attrib:- Use of Plan
    Component:- Plan        Attrib:- Plan
    Components & Attributes to be Maintained
    Component:- Plan        Attrib:- Var.Sing.Lvl Costs
    While maintaining the cost, under selection criteria, compoment: PLAN and attribute: PLAN I am unable to maintain multiple plan names.
    The single level variable cost that I have to maintain for all these plans is the same and therefore was trying to use transaction MASSD
    Can you please throw some light on how multiple PLAN selections can be done?
    Regards
    Chetan

    DEAR GURUS,
    *There is a question regarding the resoucre  consumptions  relevant to PDS in SNP,*
    ****The inputs are:****
    ****1) Base Qty= 7700 TH****
    ****2) Set Up =45 MIN****
    ****Resource consumed by operation activity is 112 207 seconds = 31,17 hours.****
    ****Unfortunately we didnu2019t understand how this figure is calculated.****
    ****Can you please help us in this****

  • Error In SNP PPM Creation . . .

    Hi All,
    I am getting following error message while converting PPDS PPM to SNP PPM. . .
    " SNP-relevant and non-snp relevant modes exist in operation "
    Please can someone let me know the solution on this. .
    Thanks in advance.
    Regards,
    PP.

    Hi,
    Please  check if any  single or multi-mixed resource has "Not SNP Rel. indicator" has  been set on the Planning Parameters tab page is in the PPDS ppm.
    Regards
    Datta

  • Getting error while trying to generate SNP PPM

    Hi Experts,
    I am getting error, while trying to generate SNP PPM fron PP/DS PPM. It says Set up matrix for resource in planning version is not define. But I checked that i havea set up matrix as well as setup group.
    Any help will be appreciated. Thanks In advance.
    Sani

    Hi Sani,
    Try running resource & ppds ppm consistency check against
    their respective transactions (/sapapo/res01 & /sapapo/scc_03)
    and check any inconsistencies found.
    Regards
    R. Senthil Mareeswaran.

  • Resource in SNP

    Hello Gurus,
    What is the relevency of the fileld maintained in the resources as (cheak mark) Not-SNP-Rel. While maintaining the resources in SNP. Or it will be maintained for single-mixed resources only and not for multimixed.
    Full points for answer
    Please Help.....
    Thank You,
    Amol Chavan
    Message was edited by:
            Amol Chavan

    Hello Harish/Ian/Patrick,
    Thank you for your responce.
               In our scenario we are maintainig 4 capacity categories in R/3 of which one is maintained for scheduling in capacity header and for rest capacity categories they have maintained as relevant for finite scheduling, and can be used by several operations for all cap. categories. Which r CIF ed to APO and showing relevant for Finite Sch. as in R/3. But here in APO they have not cheaked the  cheak box for not SNP rel.  In that case how system will or will not plan on these resources.
    We are not using CDP.
    Please brife about SNP PPM generation and this cheak box relation.
    Thank You,
    Amol Chavan.

  • Multiple Resource Planning in PPDS

    Hi Experts,
    We are running PPDS for our Production Planning. Business scenario is we have 2 PPM's , and in the PPM's input materials and Resource is different( So, we can not use different Mode) Now, when executing PPDS, system picks the PPM by which availibility date can be met, which is correct. So, if i am running PPDS for a month horizon, system always picks the same PPM always and as MRP run is infinite , system does not check the capacity of the resource also.
    Now while running scheduling heuristic ( SAP001), system schedules the orders on the resource to the full capacity and if in the time horizon orders are more than the capacity, system deallocates the orders, instead of shifting the orders to the other PPM.???
    So, in real scenario, i have one resource which is free and sitting idle and another resource is on full load and extra orders are de-allocated.
    Has anyone encountered this situation??? Please need your guidance and help.
    thanks,
    Priya

    PPDS heuristic does not consider alternate source of sulppy (PPM & PDS) , try to meet the business requiremnt with resource classification in R/3 , means single production version with multiple resource.
    I
    Lav Mishra

  • SNP PPM can't be activated

    Hi ,
    I am working in SCM 5.1 , I wanted to test the dependent demand flow in SNP heuristic run and for the same I have tried to create PPM. I have created resource bucket  & single mixed both. But when I am trying to activate the SNP PPM it gives me error "No linked PP/DS plan exists for SNP plan". IS it necessary to have PP/DS plan for SNP ppm ? Is anybody else faced the same problem in SCM 5.1 ?
    Thanks for your support.
    Best Regards,
    M

    Hi,
    are you getting some more error? like 'bucket consumption is not defined'. then you have to define the 'bucket consumption' in the resource. go to 'mode' of the 'ppm' and check resource consumption is properly defined or not.
    thanks,
    Satyajit

  • SNP PPM generation

    Hi Guys,
    I have PPDS PPM have 3 operation , in first operation there are 6 modes ,all are SNP relevant and second operation there are one mode and third operation there are 2 modes. second and third operation resources are not SNP relevant, While generating SNP PPM system gives error maximum no of mode combination exceeds.
    The requirement is only 6 SNP PPM should be generated as there are 6 SNP relevant modes are there.
    Thanks and regards
    Thamizhchelvan G

    Hello,
    With my experience SNP PPM generation can be  a tricky business. Try this out...give the max number of PPMs possible as '99' and generate the PPMs. Then have a look at the number of PPMs generated and see what its doing. It should give you a fair amnt of idea wats going on.
    Let me know how it goes
    Abhi

  • Multiple resource objects provision issue in OIM10g

    Hi Team,
    We're facing an issue regarding multiple access policy trigger for a specific resource object in OIM.
    The scenario is whenever we try to process the enablement or creation of users through flat file recon, users are created / enabled with multiple resource objects in their resource profiles.
    When we checked in User Resource Access History report, we observe that the access policy has been triggering multiple times for these users resulting in users with multiple resource objects. Amongst these one shows provisioned/Enabled and the other shows provisioning/in some cases Provisioned/Enabled.
    Please advise as this has become an ongoing issue and also has led into data mess-up.
    Appreciate your help on this one..
    Regards,
    Sagar

    The terminology sounds a little confusing to me:
    If you mean you wanna create multiple IT Resources for a single IT Resource Instance so that the user can select the appropriate IT Resource during request creation -> All good upto here. But then since the Object/Request Form attached to a resource would be the same, so any user would always see the same form fields for creationg request.
    Example: Users creating request for Oracle Database Accounts but different server locations
    If it means you just need to create multiple Resource Objects then its a straighaway standard requirement and could be handled with normal Connector Development methodology.
    Example: Users creating requests for different resources like Oracle Database Accounts & Active Directory Accounts

  • OIM 11g - Mail Notification for multiple resources

    User will be provisioned to 5 target system through access policies.So instead of sending 5 different mail notifications to the manager on the Create User task about the account creation, is it possible to send one consolidated mail about the provisioned resources in OIM 11g.

    Hi,
    How abt for the following requirement for sending single mail for multiple resources provisioned.
    We have 3 Access Policies which is defined as follows.
    1) Policy 1 -> R1,R2,R3 Resources
    2) Policy 2 -> R3,R5 Resources
    3) Policy 3 -> R1,R4 Resources
    In such a case we will not be able to put dependencies on Resources and adding a task for sending email.

  • Publish Multiple Resource Calendars Superimposed To A Web Page

    Hi, I'm hoping you can assist.
    I have succeeded in publishing a resource calendar to a web page hosted on Exchange 2013.
    In the Outlook web client it is possible for a user to view multiple resource/room calendars superimposed.
    My question is; Is it possible to achieve this view in a single published web page?
    Many Thanks
    Mike

    Hello Mike,
    Firstly, I would like to know how did you publish the resource calendar to a web page hosted on Exchange 2013.
    On Exchange, the free/busy data are stored on the users mailbox. Generally, Exchange uses EWS service to retrieve the free/busy data.
    Thanks,
    Simon Wu
    TechNet Community Support

  • Changing properties of multiple resources in one transaction

    Hi,
    Does anyone have an idea how to change a property in multiple resources in one atomic transaction. 
    There are some interesting comments regarding the use of "mass calls" in various SAP documents but not really anything specific.
    The changing of one property in multiple resources is not the problem.  This is easy.  The challenge is the operation in one transaction.   There is a ITransactionManager in the KM Javadoc but this looks like more of an internal class.
    Thanks.
    Dick

    Does this imply that the properties of these selectors can be modified simultaneously?
    Correct.

  • Mass Upload of Define Mode Combinations_PPDS to SNP PPM

    Dear All ,
    I am converting huge numbers of PPDS PPMs to SNP PPMs , I would need your support in telling me a mass upload ( program ) for defining Mode Combinations transaction .
    As such a BDC has been prepared but that takes a very long time for pushing data in this transaction .
    Thanks and Regards ,
    Prashant Kumar

    Dear Murali ,
    I have specific field values e.g. variable lot size , without PPDS Campaign , Blank Mode Combination to be selected .
    When we select the PPDS PPM no. or Product Location Combination inserting all these values in the table after execute done on the selection screen needs manual entry of all the field values .
    Data is really very huge and was wondering if there could be a quicker way out . There is more SNP PPM converted from PPDS PPM due to alternate modes of 10-15 in many of the PPDS PPMs .
    Would appreciate any further help .
    Thanks and Best Regards ,
    Prashant Kumar