Multiple ship to for POs

Is there any patch (2007 or higher) that allows multiple ship to s.
For example my customer has several doctors office's to delivery goods to. (not warehouses)
When they enter a PO, they have to keep changing the address. It doesn't allow a drop down selection for ship tos in a Purchase order.

Hi Deborah,
My question is whether you want one PO for the different locations or multiple POs for the different ship-to's. There is a 'Split Purchase Order' option in Document Settings and also on the Logistics tab in the PO transaction. Doc Settings would determine the default settings or you can use the PO field for exceptions.
The following steps is if you want to issue a PO/warehouse. You will need multiple warehouses setup and in the PO to get this result. Once that is set up:
1.  Go to Document Settings - Per Document tab (Administration / System Initialization)
2.  Select Purchase Order
3.  Select the field 'Split Purchase Order' - this will enable one PO to split into multiple ones if there are different warehouses in the same PO
With the above setup, when you add PO #10 (as an example), SAP will close PO10 (10-0) and create PO 10-1 and 10-2, etc. - one for each warehouse. The PO will pick up the warehouse address or, if none indicated, the company address. You can override the address if need be before sending/printing the PO.
If you don't want to split the PO, you can either not activate it in Doc Settings or change the option on the Logistics tab in the PO (Split Purchase Order) for exceptions.
Hope this helps,
Heather

Similar Messages

  • Multiple shipping addresses for the same supplier (depending on the symbol)

    Hello ,can we set up multiple shipping addresses for the same supplier (depending on the symbol)?
    .& How..
    Thanks

    a delivery adedress has nothing to do with a certain supplier, except you are talking about subcontracting (do you?)
    a delivery address specifies an address where you want the supplier to send the goods to.
    if it is a third party PO, then the delivery address is derived from ship-to partner of the sales order.
    in case of a standard order to stock, the delivery address is coming from the storage location address (if maintained). if no storage location address is maintained, then SAP takes the address from your plant.
    You can manually add a delivery address in MEAN transaction and then manually assign in POs delivery address tab.
    here you can as well take the address from any address already in your system (e.g. any customer or vendor).

  • Multiple Shipping Addresses for a single Ship-to-Party

    Hi all,
    How can we maintain multiple addresses for a single ship-to-party.
    The customer has 4 locations and whenever he places a order he wants the goods to be delivered to one or more than one address .How to do this?
    I tried to find it in the forum but I din't get a satisfactory answer.
    Regards,
    Ajit

    Ajit
    You may use Text for your requirment...
    Better Create a text type say Shipping Address... and assign to a sales order....
    Keep that in the Incomplete Log... so that when ever you process the sales order end user is in need to complete the Address....
    Another way is Ask ABAB er To change some field relevent to the customer as a Shipping address or may be Z field and use the same to the address..
    I have not used this check with your ABABer
    Reward if usefull
    Muthupandiyan

  • Multiple shipping address for single customer

    Dear All,
    I have a regular customer who needs to have his goods delivered to several constant locations. How can I capture the delivery address of all the locations.
    Regards
    Rasheed

    Hi Rasheed,
    Create the different ship to parties using XD01 and Account Group Ship to Party.
    Assign these ship to parties to the customer in partner functions in XD02.
    Next when you create teh sales order, you will have multiple options to chose from.
    But in each case, one Sales Order can have only one Sold to PArty and One Shipped to PArty.
    You may have to create another SO with same PO and Same Sold to PArty and Choose the next Shipped to Party option which you must have assigned in the Customer Master.
    Cheers
    Edited by: Mohammed Raheel on Jun 8, 2009 10:19 AM

  • Pros/Cons of multiple shipping points

    Are there specific pros or cons to having multiple shipping points for the same physical shipping location? I know that loading points can be used to differentiate different types of loading but are there any examples or pros/cons for why you would or wouldn't want multiple shipping points for the same physical location?
    I know SAP doesn't prevent you from creating as many as are wanted, but I'm interested more in the business process or user impact.

    Maderas,
    Multiple shipping points can have many purposes, but one purpose that I am aware of and that is currently applied at my company is for determining types of shipments.  For example, in plant "X" let's say that there are 3 shipping points:
    X1 - large orders, require 3 days of pick/pack time
    X2 - medium orders, require 2 days of pick/pack time
    X3 - small orders, typically rush orders, require same day pick/pack time
    You can set up your delivery batch jobs to print these different types of orders.  For example, you can have X1 batch job to run 1x a day very early in the morning so that pick/packers have large orders to work on and you can have batch jobs for X3 orders to run 6x per hour near the end of the day to accommodate your rush customers.
    I hope this information is helpful.

  • Define shipping data for plants / multiple sales areas should be assigned f

    Dear All ,
    Appreciate of you helped me in this:
    I am trying to configure the intercompany STO process, when I reached the step of u201CDefine shipping data for plants u201C I found that the issuing plant is already assigned  to sales Area ( 2000 , 60 , 10 ) which represent local sales , but I need to assign the sales area ( 2001 , 60 , 10 ) which represent foreign sales.
    Both sales areas should be used because we are doing STOs with a local company here in jordan and another one in Algeria , so Is there any way to have both sales areas assigned for the same issuing plant?
    Thanks ,
    Malik

    Hi Malik,
    I am afraid this is impossible in SAP standard. For this purpose you have the BAdI ME_PROCESS_PO_CUST. The method PROCESS_ITEM of this BAdI gets one single parameter, IM_ITEM, which is the pointer to the PO item object. This object has a lot of useful methods, among them:
    - GET_SHIPPING_DATA gives you the Shipping tab of the PO item derived by SAP, among them the ship-to number
    - SET_SHIPPING_DATA allows you to amend the data on the Shipping tab
    Let your ABAPer implement the BAdI and program its method PROCESS_ITEM.
    BR
    Raf

  • Re: Separate shipping charge for multiple ship to party

    Hi guys,
    We are using the total order value to calculate shipping charge that should be applied to the customer.
    0 - 25  -- $6
    26 - 50 --$10
    and so on
    So i am using a condition type ZSHH which groups all the conditions types on value basis and applies the right charge in the sales order.
    However when there are 2 ship to party in the sales order, then also it is adding the value of all the lin-items in the sales order and applying the shipping cost.
    What is desired that the condition type should calculate the total of the items to be shipped to every ship-to-party and apply different shipping charge for every Ship-to-party separately.
    I am not able to figure out how to do this?
    Do I need to write a different Structure Group Key Formula so as to acheive this functionality.
    Currently The condition type is assigned to the structure key - 1 (Overall Document)
    If yes ... kindly guide me .. what all things should I pass to the abaper so as to help him develop the structure key.
    Thanks in advace
    Vinit

    Does my question make sense ... as no one is replying ... I feel that I am asking some ridiculous or may be an obvious question.
    Can anybody guide me ?
    Thanks
    Vinit

  • Unable to enter multiple Schedule lines for BOM material in Sales Order

    Hi All,
    We have a Sales Order where in which we cannot add additional schedule lines for BOM material.
    The schedule lines are greyed out, user was able to add schedule lines earlier.
    I have checked all assignments in VOV6, VOV7 and everything seems to be fine and no changes have been made to item category being used.
    Please provide a solution for this.
    PFB link in which similar situation posted in this community but the final resolution method is not discussed.
    http://scn.sap.com/message/13201504#13201504
    Regards,
    Samiksh

    Hi Samiksh,
    Pls check for that particular customer, only complete delivery allowed(c) is set in the CMR or CMIR. If so, you can't enter multiple schedule lines for that customer.. it would be grayed out in the sales order schedule lines except confirmed line.
    or check the problematic sales order at item level shipping tab if the par del/item is set to 'C'
    With regards
    S.Siva

  • Multiple PO's for a single PR reg

    Hi,
    The system incorrectly allows multiple PO's for a single PR.Then,I configured message no 00 06 076 & 400 as a error message and system is not allowing mutiple PO's for single PR and if PO Qty is greater than PR it's not allowing and it's ok.
    Now the issue is If PR qty is 2 and as per requirement 1 qty for one vendor and one more qty for some other vendor and two PO's are to be created and the system is not allowing and throwing error message.
    Can you pl.throw some light on this issue.

    Hi
    It is not incorrect to have multiple POs for single vendor as we might have different vendors for the same item. Secondly the message setting what you have on 00/06/076/Materials of requisition & item & alr. ordered in full- E is used to stop POs being created from the PR once PR quanitity gets consumed.
    Now i do not think system will ever stop you from allowing to create multiple POs for a PR if you are distributing the Quantities between different vendors.
    By setting the message 00/06/400/Materials/services for requisition & & already ordered with & & to E mode you are blocking the PO creation with altaernate vendors change it to warning mode.
    Regards
    Edited by: samuel mendis on May 8, 2009 8:42 AM

  • Multiple line selection for RRI  in WAD

    Is it possible to select multiple lines from 1 query and do a RRI to the receiver query. Eg : Select multiple POs and then go to PO details query which shows PO details of multiple POs in WAD and both the results shown in the same web report?
    I tried the below solution, but all I get is the display of the entire Master data dump and not the filtered values. Any suggestion?????
    Rao  
    Posts: 135
    Registered: 6/24/04
    Forum Points: 8 
       Re: Multiple line selection for RRI   
    Posted: Feb 4, 2008 2:22 PM    in response to: LAKSHMI HARINDRAN           Reply 
    Yes. You can do this. You create web template with ANALYSIS web item. In the item parameters of ANALYSIS web item, you can set a property, single line or multiple for the runtime selection. Once you do this, you create a button option or context selection menu option to jump target. In the button (RRI button) in the command sequence, the first command should be SET_SELECTION_STATE_BY_BINDING and then, the RRI command to jump to the target. Hope it will help.
    Venny.

    Hi, Do you have any solution on this. please suggest. Thanks

  • Assign Multiple Sales Org for One Plant in STO process

    Hi Experts,
    Aware that I can assign multiple sales org to 1 plant (relationship: many to many).
    I am trying to create STOs to supplying plant and assigning them to different sales organization but encountered problem.
    Example:
    Supplying Plant 1000 - Sales Org 1000A (food) and 1000B (apparel)
    Receiving Plant 1100
    Plant 1100 wants to issue 2 STOs to Plant 1000 - 1 for each Sales Org (for instance STO1 to food division, and STO2 for apparel division).
    However, when I tried creating STO in the system, noticed that in the shipping tab (item details) the sales org, DC has been assigned to 1 particular assignment and data is locked.
    Tried to get into SPRO to configure and define the shipping data for plants but noticed that it's 1 to 1 relationship (SPRO - IMG - MM - PO - Set up Stock Transport Order - Define Shipping Data).
    How can this be done?

    You can set different sales areas (~sales organisation) for one plant in SAP - based on issuing SLoc provided STO between storage locations is activated.
    SPRO > Materials Management > Purchasing > Purchase Order > Set up Stock Transport Order > Set Up Stock Transfer Between Storage Locations > Define Shipping Data for Stock Transfers Between Storage Locations
    Edited by: Csaba Szommer on Jul 2, 2011 6:14 PM

  • Multiple Shipping notifications (Inb.Dlv) created via message type DESADV

    Hello All,
    I'm working on implementing the below SAP Standard process for my client. Version is SAP 4.7. The below process has to be implemented for different legal entities working on Same SAP environment.
    PO -> SO (Created via IDoc) -> Outbound Delivery -> Inbound Delivery (Shipping Notification) -> Invoice -> Invoice reciept.
    Most of the process are working, but facing few challenges while creating a shipping notification via message type DESADV and Basic type DESADV01 genereated out of Output type LAVA from Outbound delivery.
    I'm using 2 IDoc types to create Shipping notification via Outbound delivery and defined as below
    Outbound Process: Message type DESADV and Basic type DESADV01 with Process code SD05 for Customer (KU)
    Inbound Process: Message type DESADV and Process code DESA for Logical system (LS)
    I'm facing the following issues with respect to above process
    01) We need to update Batch Details like batch number, Date of Production, SLED/BBD in Shipping notification (Inb. Dlv) as Batches Instead of vendor batch
    02) When Outbound delivery has multiple line items, it is creating Multiple Shipping notifications (Shipping notifications for each line item). PO has
    As per the the threads posted here, I understand that for 01) We need to modify the Outbound IDoc FM "IDOC_OUTPUT_DESADV01" & Inbound IDoc FM "IDOC_INPUT_DESADV". But any idea, which Enhancements i have to use to fill the data?
    Also on point 02) i think, it should be a SAP standard to create a single Shipping notifications for all line items in the outbound delivery instead of each for line item. But in case if it is not a standard process, can any one tell me which user exits / enhancements to use to achieve the desired functionality.
    Appreicate your early response
    Thanks in advance
    Regards,
    Pradeep

    Hi,
    Why have you pasted Deepak Kumar's program into this forum?
    Regards,
    Nick

  • Multiple ship to party issue.

    Hi Experts,
    I have multiple ship-to, bill-to, payer for one sold to party. I maintain the same in customer master for sold to party. I create a contract for sold to party with default ship to party.
    In creating sales order with reference to contract, the system is letting me assign any ship-to party and other partner functions to the document even though they are not assigned to sold to party in customer master.
    If there any option by which I can restrict the partner functions option only to the partners assigned in customer master of sold to party.
    If some one has the solution please provide me it ASAP.
    Thanks
    Chakrapani

    Hi Chakrapani
    Please check your Partner determination procedure configuration.Also check how the ship to party partner function is assigned
    to the account groups.
    Regards
    Srinath

  • Maintaining multiple ship to party address in SD

    Hi Guys,
    Could you please let me know, how we can maintain multiple ship to party address for a customer?
    Thanks,
    Kam.

    hi,
    this is to inform you that,
    you can create another SH against 0002 - or yours and create a multiple address for SH.
    then assign the SH number to original customer then this will reflect as two SH's one for the original customer and second is created SH in sales order you will get a POP up screen you can select manually there.
    or
    you can use contacts person address tab page for alternate address of SH if you dont want to trigger another SH and this is use ful for only address maintaince.
    if you can come to a confirmation that you are not using contacts person tab page for any other purpose.  then you can use it
    regards,
    balajia

  • Maintaining multiple ship to party address in ECC 6.0

    Hi Guys,
    Could you please let me know, how we can multiple ship to party address for a customer in ECC 6.0?
    Thanks,
    Kam.

    I suggest you ask this question in an SD forum - and/or try to get this information from SAP help or a consultant.
    Markus

Maybe you are looking for

  • Track file usage by recording PC name?

    Is there any way for a pdf form file to record the PC name everytime it is opened on a new pc?

  • My problems with X1

    Moved to x1 section.

  • Mac File Migration Between Windows File Servers (NAS to SAN)

    My company has upgraded our Windows based file server from a NAS to a SAN, and I need to know the best method to migrate our Mac files from the old Windows Server to the new Windows Server; do we have to use a Mac to preserve resource fork data? The

  • Medium in output type

    Dear all, I'm in the midst of figuring how ALE being sent out via message control. While looking at a Sales order's output type setting screen, under Medium column it contains: 1. Print output 2. Fax 3. Telex 4. External send 5. Simpal mail 6. Specia

  • Can't open docx files

    Recieved a docx file from a windows computer can't open with pages on ipad or mac comes up with unknown error