Need to update the actual start date & time of a operation in workorder

Hi Experts,
               I need to update the Actual Start date and Actual start time of a Operation of  a WorkOrder through a Function Module.
I was looking into the BAPI_ALM_ORDER_MAINTAIN FM, but i couldn't find any field relating to the actual start date and start time of a operation.
Kindly Suggest me which Function module i can use to complete my task.
Thanks in Advance
bye

Hi,
It is system's standard behavior and no other MRP type will help you in moving the start date outside the planning time fence. With MRP type P3 new requirements are covered at the end of the fixing period, the end date is set and planed order is scheduled backword. Hence the start date will lie within the planning time fence.
Rgds,

Similar Messages

  • How can we update the last synchronization date and time..on SUP in sccm 2012 R2

    Hi,
        Can you any one please guide me how can i update the last  synchronization date & time in SUP on SCCM2012 r2 , some how its updated as future date and when ever i try to synch the SUP with disconnected WSUS its shows in the wsyncmgr.log 
    "Wakeup for a polling cycle " and  " Wakeupby inbox drop" and "Wakeup by SCF change"  
    Thanks 
    Balaji K

    You'll probably have to call CSS on this one as this not normal by any means. The messages you noted above are completely normal but if that's all you are seeing then there's an issue.
    Have you reviewed wcm.log and wsusctrl.log?
    Jason | http://blog.configmgrftw.com | @jasonsandys

  • Pricing conditions for the articles are getting triggered one day before the actual activation date to 3rd party systems through job WPMU.

    Hi SAP Guru´s,
    Currently we are sending the pricing, promotions & article master data delta load to 3rd party system from SAP ECC via SAP XI through IDOCS using daily scheduled batch jobs WPMU. IDOC segment - WP_PLU.
    Here the issue is the promotion & pricing data are sent to 3rd party system one day before the actual start date.
    Eg: Promotion 123456 which has start date as 15/05/2014 & ending on 30/05/2014 & was created & activated on 13/05/2014.
    This promotion 123456 is getting triggered from SAP ECC through batch job on 14/05/2014 morning & 3rd party system receives the data on 14/05/2014 & the promotion are getting activated at 3rd party system end on 14/05/2014 itself which actually gets active from 15/05/2014.
    Same in the case for Standard Pricing data which needs to be active from 31/05/2014 once the promotion 123456 ends on 30/05/2014.
    The standard pricing data gets triggered from SAP ECC on 30/05/2014 through batch job & reaching 3rd party system on 30/05/2014 & getting activate on 30/05/2014 itself.
    This creates more issues at the store end as well as affecting business.
    We checked at 3rd party system end & they replied that their system considers the updated time stamp & date to activate the prices & it does not considers the actual active from & active to date. They need the data to be sent from SAP ECC on the effective date of the pricing & promotions.
    Can any one help me how to change the pricing conditions beign triggered through batch job in SAP ECC based on the actual promotion & pricing conditons start date or is there any other process to trigger the data through the batch job on the actual promotion & pricing data activation date.
    Thanks in Advance.
    Thanks & Regards,
    P.P.Shankar

    Hello Shankar,
    Change the lead time in the POS Outbound Profile. You can't put less than 2 days there so data for today and tomorrow will be transferred which also means you need to adjust your batch timing accordingly.
    Sales and Distribution -> POS Interface -> Outbound -> Maintain Profile for POS Outbound.
    See if it helps. The best option would still be that the 3rd part system considers the activtion date.
    Kind Regards
    Kaizad

  • Mass updation of Dep start date in Asset

    Hi All,
    Please note that I have created a new depreciation area for client for tax reporting purpose(areas do not post).The client wants to update the depreciation start date in all the assets with this new dep area.This can be done through customizing settings( transfer of dep terms) but then the useful life will also be identical to reference area(01) which client wants to change as per requirement and should not be same as reference area.
    The other options are LSMW & BDC upload where i can do a mass upload for depreciation start date for all the assets.However I have not used this feature.
    I would really appreciate if someone can help me with the steps.
    Regards
    Pranay

    Hi,
    To do the mass changes to the assets create a substitution in Asset Accounting in GGB1.
    Asset Accounting - AM Master data mass change.
         Create a step under the substitution with the required changes(take Deparea and Asset Classes in Prerequisite)
    You would require multiple substitutions. Precisely one substitution for all the asset classes with the same set of Deprecation start date and Useful life.
    In OA02 create new entry for the compny code.
    In AR01select the assets for which the mass change needs to be done.
    select the Create work list icon on appln tool bar. Name the work list. select Change asset w/o dialog (bulk change). Give the substition name that is created.
    In AR31 give the worklist details
    Select the Release Work List icon on the appln tool Bar.
    the changes will be effective for the existing selected assets.
    Try first in IDES before you do the actual changes. This will work.
    Thanks,
    Raja.

  • Actual Start Date vs Actual End Date - Activity

    In an Activity, I would like to seperately enter the Actual Start Date and Actual End Date.
    - If I try this using (partial) confirmation,  I receive a pop-up with an error that the two dates must be entered together or no dates can be entered.
    The activity in my project can take over a year to complete and the requirement is to confirm start (at start) and to confirm end (at end).
    Does anyone know of a solution for this issue?
    Thanks in advance!

    Hi Patrick,
    I think you need to research a bit more on confirmations in PS. Actual dates in partial confirmations are practically interpreted as provisional actual start dates and actual finish dates. The actual start for the activity remains the same however the actual finish date is overwritten once the final confirmation is entered.
    For example, take an activity with start date 05.09.2011 and finish date as 14.09.2011. Now when you provide confirmations on a daily basis, you can use the following strategy:
    Day 1, 05.09.2011: actual start 05.09.2011, actual finish 05.09.2011, % complete 10%
    Day 1, 06.09.2011: actual start 05.09.2011, actual finish 06.09.2011, % complete 20%
    Day 1, 07.09.2011: actual start 05.09.2011, actual finish 07.09.2011, % complete 25%
    Only when you provide the final confirmation the actual finish date is confirmed. The various confirmation line items may be viewed via CN48N.
    Regards,
    Ammar

  • Update of Planning Start Date does not update macros

    I have written a program to update the planning start date in a planning book using function /SAPAPO/MSDP_PB_SAVE_DVIEW_TAB. I have included this in a process chain. The update is immediately followed by a /SAPAPO/TS_BATCH_RUN variant that runs a macro in the updated book. The macro uses planning start date. The issue is that the macro does not appear to have been updated with the new planning start date. I experimented with using transaction Define Planning Book (/SAPAPO/SDP8B) whilst also in Macro Workbench on another session. If I change the planning start date this is also not reflected in the macro unless I come out of the Macro Workbench completely and fo back in. This appears to be a buffereing issue.
    Does anyone know if there is a way to force the macros to be updated? Otherwise I may have to resort to just putting a delay in the chain and hoping the maco will be updated before it is run.
    Thanks
    Edited by: Peter Phillips on Mar 19, 2010 11:32 AM

    Hello Mani,
    We have planning books used to calculate demand for newspapers at weekends. At weekends the papers contain printed colour magazines. These have  to be ordered in advance. The macros that we run use planning start date to claculate the quntity of magazines required for the next weekend. The business also needs to do advanced calculation for the next two weekends. This requires an update to the planning start date to change the basis for the macros. We do not wish to write separate macros for each weekend as there are quite a few of them. We are trying to keep it as simple as possible.
    Regards
    Peter

  • How to Update the Final Process Date in Termiantion Screen Oracle HRMS

    Hi Gurus,
    I have a requirement where i need to update the Final Process Date. is there any standard api to update the final process date. i know there is a update to update the termination details like actual termination date,last standard process but how about final process date.
    Eg : For one assignment the final process date is 31-March-2013 and as of now he is a exemployee in system as he was terminated on 31-DEC-2012. now i want to prepone the final process date to 31-JAN-2012.
    any replies on this is highly appreciable.
    Thanks in advance.

    I would reverse the termination then terminate the employee with the right FPD.
    hr_ex_employee_api.reverse_terminate_employee
    hr_ex_employee_api.actual_termination_emp
    hr_ex_employee_api.final_process_emp
    Maybe also the below might work:
    hr_periods_of_service_api.update_pds_details
    Please note that there should be no payroll result in your case after January payroll.
    On a side note, you can also termiante employee without setting the FPD, and then put it only when approved by the business - in this way wou can avoid the prepone.

  • Making actual start & finish time fields mandatory in COR6

    I need to make the actual start time (AFRUD-ISDZ) & actual finish time(AFRUD-IEDZ) fields mandatory in COR6. Currently the system gives a default value of 00:00:00.

    Hi Manish,
    Have you also checked changing the setting for these fields
    AFVGD-isbz...?
    Also one more option would be use of transaction variant.

  • Dynamic update of Planning Start Date in Planning Book

    Hello.
    Has anyone ever created a program to update the Planning Start Date of a Planning Book dynamically to the next Friday of the month for example?
    The help information available for this field mentions a PDATE userexit, but I can not find it. Has anyone ever used it and has some examples to share?
    Many thanks.
    Aline Passos

    Hi there,
    I have never done this earlier. However i know that planning start date is stored in table /SAPAPO/PBDVWHDR-TBID_START. I tried changing this entry in the table and it correctly updated the dataview plannig start date.
    So you may write a small program to update this field and it shall update the dataview.
    Please let me know if this helps you.

  • I am trying to scan a photo on to my computer but every time i try it says i need to update the lcd

    i am trying to scan a photo on to my computer but every time i try it says i need to update the lcd

    TRY FORCE IPAD INTO RECOVERY MODE
    1. Turn off iPad
    2. Turn on computer and launch iTunes (make sure you have the latest version of iTune)
    3. Plug USB cable into computer's USB port
    4. Hold Home button down and plug the other end of cable into docking port.
    DO NOT RELEASE BUTTON until you see picture of iTunes and plug
    5. Release Home button.
    ON COMPUTER
    6. iTunes has detected iPad in recovery mode. You must restore this iPad before it can be used with iTunes.
    7. Select "Restore iPad"...
    Note:
    1. Data will be lost if you do not have backup
    2. You must follow step 1 to step 4 VERY CLOSELY.
    3. Repeat the process if necessary.

  • How does the GR processing time affect the scheduling of the process order & the latest start date in the operation.

    Hi
    Can anyone explain  how does the GR processing time affect the scheduling of the process order & the latest start date in the operation overview.

    Hi
    GR processing time means number of workdays required after receiving the material in storage.
    Check this link:GR Processing time
    Regards,
    Anupam Sharma

  • HT1338 I have os 10.5.8 software on my mac and I need to update the software on my mac so I can update my iphone 4s, every time I try to update my mac with the 6.0 it says it doesn't need any updates, but my mac still has 10.5.8.... any help??  Please...

    I have os 10.5.8 software on my mac and I need to update the software on my mac so I can update my iphone 4s, every time I try to update my mac with the 6.0 it says it doesn't need any updates, but my mac still has 10.5.8.... any help??  Please...

    You must first buy Snow Leopard from Apple: 800-MY-APPLE (in the US)
    Make sure your system meets Snow Leopard's requirements:
    Mac OS X 10.6 "Snow Leopard" System Requirements
    To install Snow Leopard for the first time, you must have a Mac with:
    An Intel processor
    An internal or external DVD drive, or DVD or CD Sharing
    At least 1 GB of RAM (additional RAM is recommended)
    A built-in display or a display connected to an Apple-supplied video card supported by your computer
    At least 5 GB of disk space available, or 7 GB of disk space if you install the developer tools

  • I need to get the Current System Date and time in the format

    I need to get the Current System Date and time in the format
    *6/24/2009 11:30:29 AM*
    How do i do it ?

    I seem to be saying this a lot lately.
    Google is your friend.
    I googled "java current date format" and SimpleDateFormat featured prominently in the results.

  • Need By Date Should be equal or after the effective start date- error in po_requisitions_interface_all

    Hi All,
    We have created a manual planned order for one buy item in ASCP workbench for some qty and released it.
    But, we are not able to get its requisition created in source.
    When we check the PO_Interface _Errors table, we found that it is errored out with error as --
    Need By Date Should be equal or after the effective start date .
    Can anyone please help me out to find the cause of this issue. Any help/pointer in this regard will be highly appreciated.
    Thanks,
    Avinash

    Hi Abhishek,
    We found the root cause of the issue.
    Its BPA was not having any Effective start date mentioned in its terms. So we put it as BPA creation date and ran the data collection and plan run.
    After that we were able to see its BPA release created without any error.
    Thanks,
    Avinash

  • Need a FM which returns the last modified date& time

    Hi,
    Kindly Suggest me if any Function Module is there which returns the last modified date& time for tables HRP1000 and HRP1001.
    Rgds
    Kishor.C

    just check the following tables..
    CDHDR - Change document header
    CDPOS - Change document items
    you can use this function module..
    BPCT_CHANGEDOCUMENT_DISPLAY
    Edited by: Arunima Rudra on Apr 14, 2009 4:49 PM

Maybe you are looking for

  • How to release function module...

    Hi All,    I have created one function module and activated that. How to release that function module?   But Release option is in deactive state...how can i release the FM....please let me know the resons for that. thank you.

  • Airport disconnects when there's more than one device

    I've got a really weird problem.. I have an Apple Airport Extreme 802.11n 3rd Generation. Software version 7.6 When more than one device connecrts to the base station it will disconnect everyone and then all devices will go into a connect/disconnect

  • Read email from microsoft exchangeserver 2010 and save attachement

    Hello, I want to read email from microsoft exchangeserver 2010 and save attachement into a folder.I created an Java program to import attachments from a exchange server mailbox using "POP3S".It works fine when run as a java application.But when i put

  • What is hpsetup and how do I stop it interfering with my airport?

    For a couple of weeks now our household (Powerbook G4 and iBook) have both been sporadically unable to connect to our own network because something called hpset up seems to be in the way. We don't have any hp printers or any hp appliances in our hous

  • Regarding FYI Notification in SSHR

    Hi Group, The requirement which we have is to have a FYI notification for the the address change and and Extra Information Type Change(EIT) through self-service. The FYI Notification should have the detail for the field change and what has been chang