Need WBS split to AUC and Expanses during settlement (not %wise)

Hi,
We have some capital projects settling to AUC but we are also charging WBS for labor costs and travel expanses and offcouse capital costs.
Managment wants PS team to Settle labor/travel to CCTR and Capital cost to AUC. How can WBS recognize cost elements carry expanses and Capital Costs and split them during settlment?
expanse range: 500000-599999 travel/labor
Capital expance range: 600000-699999 to be capitalized
I will appreciate any clue in this regard.
-Atif
PS.: I am trying capital investment key at this time, so that WBS will settle only capital range in AUC.

Hi,
Maintain different settlement rule for WBSE with different recevier such as AUC & CTR. In settlement configuration define source structure such as CTR & AUC along with cost elements for settling the cost into different receiver.
Hope this will help you.
Regards,
Rakesh Pradhan

Similar Messages

  • HT201401 im trying to reset my iphone 4s and it says it needs the origional apple id and password. i do not have this because i bought the phone from someone who bought it from someone is there a way to get around this issue?

    im trying to reset a iphone 4s that i bought from someone. it is in the middle of the restoring process and it says it needs the origional apple id and password. i dont have this and the person i bought it from got it from someone else so there is no way for me to get that info. is there any way around this issue?

    No. There is no way around this. Without the credentials used to lock it, you can't use it at all. Return it to the person you got it from and get your money back. Failing that, turn it over to the police. There is a high likelyhood that it's stolen.

  • Split GL sale and cost of sale

    Hi all,
    User need to split GL sale and cost of sale according to the model of the car. 1 GL for 1 model. Currently for all sale and cost of sale will flow to 1 GL. I need to create new GL for each model. How do I split and is it can be done in the system?
    Thanks

    Hi vamsi Krishna,
    I am having the requiremnt:
    Pertaining to GL account and Cost center combinations. During transactions, the system has to throws an error " GL account xxxxx and Cost center xxxxx combination not valid ".
    can u check your validation and let me know wht logic they given.
    Go to GGB0 --> Fianncial accounting --> step one or related step
    Pre requisits : from this wht right side wht logic they given ?
    Check : from this wht right side wht logic they given ?
    Rule : from this wht right side wht logic they given ?
    Can fill the logic....
    Rds, Anil

  • Wbs in customer/vendor and gl document lines during initial balance upload

    Hi gurus,
    Can we enter wbs in customer/vendor and gl documents lines during upload of opening balance upload?
    What is the impact of this?? Do we need to run project settlement on 1st day after go live to get data in cost center from ar, ap and gl????
    Thanks

    Hi Mohit,
    Why do you want to udpate WBS element for vendor and customer line items. Basic concept of said cost object (WBS element) is transfer values to Fixed assets or GL accounts or any other cost objects like cost center ,Internal order,sales order like that.
    You can update WBS element for all fixed expenses based on settlement rule and allocation types,which you created in customization and assigned cost elements or cost elment group over there. You can update WBS elements for said line items settle after opening balance update.  Please note ,it may not possible to update WBS element for vendor and customer line items.
    Basic cocnept of WBS element is cost collector ( You may use to collect revenue also as per nusiness processes) ,collects the cost from various resources and settle to said above objects. Vendor and customer balances are balance sheet accounts,which can settle through payments.
    Regards
    ManiKumar

  • How to split Inventory and customs during Goods Issue

    Hi Friends,
    We create an Intercompany PO and do a GR against it. It creates an automatic GI. The Material document posted during GI is Dr. COGS account and Cr. Inventory account. The Inventory account consists of stock value + customs duty paid during GR.  Now we want to split this inventory and customs separately while posting the GI.
    For Example: Stock value = $100, Customs duty $10. Then total inventory value is $110.
    Current postings
    Dr. COGS      $110
    Cr. Invenotry  $110
    To be postings
    Dr. COGS          $100
    Dr. Other Costs $ 10
    Cr. Inventory      $100
    Cr. Customs       $ 10
    Please share any inputs to achieve the required postings.
    Regards
    Surya

    Hi
    In our company we have the following cycle if it can gives you any idea:
    inventory purchase with custom/ freight cost
    Dr. Inventory                         1150
         Cr. GR-IR                         1000
         Cr. Custom for Inventory    100
         Cr. Freight for Inventory       50
    While Goods issue to production :
    Dr. COGS                1150
         Cr. Inventory        1150
    Regards
    Mahmoud El Nady

  • AUC and WBS

    Dear all
    As you all  know that AUC will be automatically created when Wbs created in investment project, system creating  AUC at all WBS level.I want only one AUC at 1st level WBS. i do not want AUC at other level.  How i do that.
    Regards
    KP

    Hello,
    You need to have settlement rule for top level WBS only in that case.
    How are you creating settlement rules for your WBS- manually or automatically?
    Since you just want to settle the top WBS, i guess, you don't need automatic generation. In that case, just create the rule manually only for top WBS.
    Another option could be when you are running settlement, just run it for top WBS without hierarchy indicator checked. This will not settle lower level WBS.
    Hope the above helps you.
    Sourabh

  • Activity Labour HR & Machine HR need to upload to IO and then to AUC

    I have created a Internal Order-AUC, and also created a AUC. I am booking expenses/cost to IO and  able to settle those costs to AUC since all the cost element are assigned to Allocation structure A1.
    Issue: I am booking Labour HR and Machine HR cost (by maintaing activity prices- t,code KPB6) maitained to that IO through code: KB21N .
    Now when I am settling this IO to AUC it gives error. I am not able to maintained secondry settlement cost element for the activities. I have even tried but system is giving error that maintain allocation structure A1 properly.

    Hi,
    If AUC is to be linked to Internal Order,then the Object class of the IO should be INVESTMENT.
    If you create an IO with type Investment,then it will create an AUC automatically.
    And in the settlement profile of the IO, you will assign the model order and also assign the settlement profile 50.
    Then while settling an IO , it will automatically get settled to AUC and there would be no error.
    Hope this is useful.

  • Secondary costs from WBS to an AuC

    Hi,
    1. I have executed Assessment[KSU5] that actually settled costs from secondary cost element[800099] to a WBS element [AAA]
    2. Now I am trying to settle costs [which is secondary] from WBS element [AAA] to an AuC using CJ88 and I am getting below error
    3. Just for info in allocation structure Z1, I have given settlement cost element for WBS, but still I am getting below error
    Any advises/ideas, thanks
    Complete allocation structure Z1
    Message no. KD503
    Diagnosis
    During settlement, the system puts the sender debits into groups (assignments), which are settled using the same settlement cost element. The settlement assignment is made in the allocation structure, which is stored in the settlement rule for the sender (under settlement parameters).
    Cost element 800099 cannot be assigned to a settlement cost assignment in allocation structure Z1, and therefore it cannot be assigned to a settlement cost element.
    Procedure
    Possible solutions are as follows:
    If the posting under cost element 800099 was made to the sender because of an incorrect entry, and you can reverse the posting, and do not need to update the allocation structure. You only need to reverse the incorrectly assigned posting before repeating the settlement. Exception: For an investment measure with a line item settlement, you need to extend the allocation structure, even after the reversal.
    If the posting was made correctly, you can do the following:
    a) You can assign a different allocation structure to the sender: In the master data maintenance for the sender, choose "Settlement rule -> Goto -> Settlement parameters" and then enter a different allocation structure.
    If necessary, also check whether the correct allocation structure is entered in the settlement profile. The allocation structure is defaulted in the settlement profile when you create sender master data or when you maintain the settlement rule.
    You can update allocation structure Z1
    Regards,
    Sri
    Edited by: Sridhar Nagavarapu on Jul 4, 2008 12:45 AM
    Edited by: Sridhar Nagavarapu on Jul 4, 2008 12:47 AM

    Through MM, contract is created (ME31N) whereby the settlement G/L accounts are identified.
    The contract then is released through MM with TCode ME21N which prompts Commitment Costs to be entered, after which the Service Entry Sheet SES through TCode ME81L which then automatically updates into the WBS.
    Through WBS, CJ88 would be the TCode you would have to use for settlement.
    Hope this helps.
    Thanks.

  • Error when I execute CJ88 form WBS element to AUC asset.

    Hi,
    We have one WBS element which was created to settle the values to AUC asset at the period end. Now we are in 2012 fiscal year 8th period. Asset accounting books were closed for company code of the 2011 fiscal year. This company code currency AUD and Controlling area currency is EUR.
    User has booked some expenses to this WBS element in company code currency in 2012 fiscal year 1st period. When he tried to settle in 2012 fiscal year 1st period, he is getting error like "First clear the values in previous year". when we go and see the WBS element for the 12th period of 2011 fiscal year, still there is a difference "0.01".
    When we go and see the CJI3 for this WBS element, fiscal year 2011 and period 12 still there is some 0.01 value. My doubt is why system is showing this difference in CJI3, even I have posted transactions in company code current. Client was able to close the Asset accounting books without any errors. 
    User has posted expenses debit and credit amount to this WBS element during the period in 2012 fiscal year, still system is showing 5.25 difference  for the same WBS element in CJI3 transaction code.
    Could any body help me to know why this difference is showing even we post the amounts in company code currency. Why system has not given any error in 2011 fiscal year when user was closing books for asset accounting?
    Thanks and regards,
    Yelamanda Rao.

    When closing the year, the system checks to see if Periodic Posting has been recently run, and throws error if it still needs running.  System performs other checks too, such as checks for incomplete asset records.
    However, the system doesn't check for missed settlements.  We have to manually check for settlement errors, and for pending settlements, before closing out the AA year.
    There could be an OSS Note on this topic, do not know.  You may need to reopen the fiscal year and AA year and complete your asset support transactions, settlement, periodic posting, AFAR, AFAB.
    Since the year is already audited, stay in touch with accounting and your auditor before taking these steps.
    It is possible to enter offsetting g/l entries to nullify and defer the impact of your settlement, etc., to FY12 if your requirement is to not alter the FY11 g/l balances audited.  But the AA sub-ledger will be slightly changed.
    Regards,
    Greg

  • AUC and settlement rule mismatch.

    Hi,
    We have created many AUCs while uploading initial data at the time of go-live by posting JVs on WBSE and then performing the settlement. Now due to some currency issues we have reversed all settlements, and then Asset accounting person has resetted the asset register.
    now when I am trying to create AUC from CJ20N, system creates AUC and provides the number. but this newly generated AUC number is not matching with the AUC in settlement rule. I can't delete the old settlement rule as the settlement performed on that. as well as I am not able to add new AUC in settlement rule.
    Please let me know if there is any program / tcode which can remove this inconsistency. or is there any other procedure to make it streamline.
    Please help.
    Regards,
    Nilesh.

    Hi,
    There is no error message in this case.
    The scenario is like:
    I have one WBSE and AUC is created for this WBS. for example AUC number is 1. the WBSE is released and some cost has incurred on it. during periodic settlement the cost is settled on the AUC.
    Now the Client FICO team observed that the asset accounting is wrong due to currency conversion problem, so FICO team decided to reset the asset register and upload the entire master with new corrections. this will reset the AUCs as well.
    so i reversed the settlement done on AUC and got the cost back on WBSE.
    FICO team has resetted the asset register and all AUCs got deleted.
    Now the issue is: WBSE is having AUC #1 in settlement rule which can not be deleted as settlement is carried out on this rule.
    But when I create new AUC for WBS it is being created as some different number, (lets say #7) so even if now I run settlement the settlement will be done on AUC #1 insted of #7 even though #1 belongs to some other WBSE now in new scenario.
    I hope I have clearly mentioned the issue.
    Regards,
    Nilesh

  • Settlement of proj cost to AUC and final settmnt to f.asset for closed proj

    Hi PS Experts,
    If the project (Investment Projects) has been closed and AUC has been fully settled to final asset but in some cases they still received invoices for the same project.
    Would it be correct if they undo closed and undo teco the project and charge the cost to related WBS elements and settle to AUC then proceed to fully settled to a new fixed asset ? SInce the previous fixed asset has been depreciated, i guess we should create totally new asset to settle this new cost.
    Please advise.
    Thanks and regards,
    Yuzeila

    yes it is fine to do that from a system perspective
    choose full capitalisation in  transaction CJ88
    also make sure that the settlement rule to the final asset is entered on the WBS
    you need to check with your FI guidelines about asset value dates etc to check about the business perpspective
    As an alternative - It would be OK to create a sub asset with new asset value dates and use this sub asset in the settlement rule

  • Need help with multiple devices and apple id

    Between my husband and myself, we have two Iphones, two Ipads, and one Imac.  I back all of them up on my Imac using ONE iTunes account....we prefer not use Icloud, and I think that helps keep the information on each device relatively separate from each other...no overlaps with contacts and calendars.  We have one APPLE id and password, that we use for Itunes and the App Store.   We just got the Iphone 6 for my husband, and it keeps asking him to enter his Icloud PW.(his recognized user name is his PRIMARY email address)...which presumably he does not have, nor does he need (or maybe he does I need some real guidance on that).  To keep this from making him crazy can I just delete his Icloud account, which again presumably, was created automatically with the new Iphone 6 set up??
    Similarly, I need to use FIND my Phone (etc), and HIS devices are not in MY listed devices....is this because he NEEDS his own APPLE ID, or is there a way to add his devices to my list of devices within the APP....I thought because we share the Itunes account they should all be in MY devices.
    Can someone help me make sense of this?
    THANKS!!

    Hello melissaben6250,
    Thank you for using Apple Support Communities. 
    I understand that you are not seeing your husbands new iPhone 6 in your Find My iPhone app. First, while you may "prefer not use iCloud", you are using it, at least in regards to Find My iPhone for your existing devices.
    Now, for your husband's phone and Find My iPhone. It sounds like during the setup of his phone, he logged in to his Apple ID and even possibly created another iCloud account. In order to see his phone on your existing Find My iPhone, it will have to log in to the iCloud account where the other devices are signed in. Take a look at this article on troubleshooting Find My iPhone, especially the first section on the device not appearing.
    iCloud: Troubleshooting Find My iPhone, iPad, iPod touch, or Mac - Apple Support
    Cheers,
    Jeff D. 

  • HT1414 C apple i need to know few things,first of all i shall tell my scenario. I got an iphone 3gs from my uncle in US. I m at india k. well , in that iphone it showing activation screen and trying to activate. not more than that..plz help!

    C Apple, i need to know few things,first of all i shall tell my scenario. I got an iphone 3gs from my uncle in US..after long waiting. I m from south india, living at God's country called Kerala k. well , in that iphone it showing activation screen and trying to activate. not more than that..plz help!
    means.. in simple words, it is trying to activate and all( searching wifi,, taking few minutes..again searching...if it couldnt find any wifi - telling .. try connect using itunes an all)...well any way. finally I try connect to a wifi network, with full speed...3mbps..from Ravi's internet cafe in downtown.
    All after Im getting the below message from that white candy box!( thats all I can use now, because, in my dreams iPhone is something great,  that mankind ever seen....but this really disappointed me......im simpling blinking!!(same with itunes too)
    ""Your iphone could not be activated because the activation server is temporarily unavailable. try connecting your iphone to itunes to activate it, or try again in a couple of minutes.
    If this problem persists, contact apple support at apple.com/support""
    EVERYDAY .EVERTIME.. I C this message and sleep....no use.....and i use to charge that 'white candy box' to c this message!
    I try searching internet and all for solutn...but no one knw about it..but there are...some one me abt method called jailbreaking ..rednw..white snw ..ultrasnw and all...I dnt knw why it is so complicated to troublesht...apple is suppose to be simple and friendly.
    C why u manufacturing these stuffz like this, if does'nt serve the any of its purpose ....or useable to any of its features atleast....C i wont be that disapppointed, if u put an option to playbck music or video during activation and all...
    If you are responsible for manfacturing such unuseable thing, then its ur responsible to destroy it too.....
    anyway now everyone knws that ..I have an apple iphone with me, but that doest make me proud at all...
    Finally I have only few questions to ask...
    1 will it work with my vodafone sim in kerala?
    2 is any way , i can hear any music out frm it?
    3 will i become a proud iPhone user?
    I am already fedup with asking questions..begging for an solution.....
    I hope so you can help to figure it out, without any complications....thank u!

    It was not legitimately unlocked by the carrier it was originally locked to. ONLY the carrier it is locked to can authorize unlocking it.
    In order to allow it to be used on a different carrier, the phone was hacked or jailbroken. An unauthorized modification was made to the phone. That modification has damaged the phone. You can not get support for it here or from Apple.

  • Help needed in splitting files using BPM

    Hello experts,
    I am working on an interface where i need to split files within BPM.
    I know,i can achieve it in Message Mapping by mapping Recordset to Target structure and then using Interface Mapping within Transformation step.But i dont want to follow this.Is there an alternative way to achieve this within BPM.
    I have an input file with multiple headers and i need to split for each header.My input file looks like this:
    HXXXXXABCDVN01
    MXXXXXXXXXXXXXX
    MXXXXXXXXXXXXXX
    SXXXXXXXXXXXXXX
    HXXXXXABCDVN02
    MXXXXXXXXXXXXXX
    MXXXXXXXXXXXXXX
    SXXXXXXXXXXXXXX
    HXXXXXABCDVN03
    MXXXXXXXXXXXXXX
    SXXXXXXXXXXXXXX
    Is there a way, where i can specify this condition within BPM , that split files for every H.
    Thanks in advance.
    Regards,
    Swathi

    Hi,
    have your target structure with occurence as 0...unbounded in the mapping and map the header filed to the root node (repeating parent node) of the target structure....this will create as many target messages as the header fileds....if you want to send these messages separately then use a block in BPM with ForEach option....
    Splitting and Dynamic configuration can be applied in the same mapping.
    Regards,
    Abhishek.
    Edited by: abhishek salvi on Dec 18, 2008 12:59 PM

  • My MacBook keeps freezing and crashing during startup and use, what's wrong?

    My MacBook functioned perfectly for YEARS, and suddenly it started freezing during startup. One of four things happens: it starts up no problem, it freezes at the apple logo with the load wheel spinning, it freezes at a 'no' symbol (a circle with a line through it) with the load wheel spinning, or it freezes at a logo which is a folder with a question mark in it. It occasionally goes through and gets to the homepage, where I can use the computer for a certain amount of time before it freezes again. I never get to use it for more than 30 or 45 minutes at a time.
    Yes, I have updated all my software, and I haven't dropped it or downloaded anything that could cause this issue. What could be going wrong? :(

    There are corrupted system files involved, so my suggestion is to reinstall OS X.
    If you are using Snow Leopard:
    Reinstall OS X without erasing the drive
    Do the following:
    1. Repair the Hard Drive and Permissions
    Boot from your Snow Leopard Installer disc. After the installer loads select your language and click on the Continue button. When the menu bar appears select Disk Utility from the Utilities menu. After DU loads select your hard drive entry (mfgr.'s ID and drive size) from the the left side list.  In the DU status area you will see an entry for the S.M.A.R.T. status of the hard drive.  If it does not say "Verified" then the hard drive is failing or failed. (SMART status is not reported on external Firewire or USB drives.) If the drive is "Verified" then select your OS X volume from the list on the left (sub-entry below the drive entry,) click on the First Aid tab, then click on the Repair Disk button. If DU reports any errors that have been fixed, then re-run Repair Disk until no errors are reported. If no errors are reported click on the Repair Permissions button. Wait until the operation completes, then quit DU and return to the installer.
    If DU reports errors it cannot fix, then you will need Disk Warrior and/or Tech Tool Pro to repair the drive. If you don't have either of them or if neither of them can fix the drive, then you will need to reformat the drive and reinstall OS X.
    2. Reinstall Snow Leopard
    If the drive is OK then quit DU and return to the installer.  Proceed with reinstalling OS X.  Note that the Snow Leopard installer will not erase your drive or disturb your files.  After installing a fresh copy of OS X the installer will move your Home folder, third-party applications, support items, and network preferences into the newly installed system.
    Download and install the Combo Updater for the version you prefer from support.apple.com/downloads/.
    If you are using Leopard or Tiger:
    How to Perform an Archive and Install
    An Archive and Install will NOT erase your hard drive, but you must have sufficient free space for a second OS X installation which could be from 3-9 GBs depending upon the version of OS X and selected installation options. The free space requirement is over and above normal free space requirements which should be at least 6-10 GBs. Read all the linked references carefully before proceeding.
    1. Be sure to use Disk Utility first to repair the disk before performing the Archive and Install.
    Repairing the Hard Drive and Permissions
    Boot from your OS X Installer disc. After the installer loads select your language and click on the Continue button. When the menu bar appears select Disk Utility from the Installer menu (Utilities menu for Tiger, Leopard or Snow Leopard.) After DU loads select your hard drive entry (mfgr.'s ID and drive size) from the the left side list. In the DU status area you will see an entry for the S.M.A.R.T. status of the hard drive. If it does not say "Verified" then the hard drive is failing or failed. (SMART status is not reported on external Firewire or USB drives.) If the drive is "Verified" then select your OS X volume from the list on the left (sub-entry below the drive entry,) click on the First Aid tab, then click on the Repair Disk button. If DU reports any errors that have been fixed, then re-run Repair Disk until no errors are reported. If no errors are reported click on the Repair Permissions button. Wait until the operation completes, then quit DU and return to the installer. Now restart normally.
    If DU reports errors it cannot fix, then you will need Disk Warrior and/or Tech Tool Pro to repair the drive. If you don't have either of them or if neither of them can fix the drive, then you will need to reformat the drive and reinstall OS X.
    2. Do not proceed with an Archive and Install if DU reports errors it cannot fix. In that case use Disk Warrior and/or TechTool Pro to repair the hard drive. If neither can repair the drive, then you will have to erase the drive and reinstall from scratch.
    3. Boot from your OS X Installer disc. After the installer loads select your language and click on the Continue button. When you reach the screen to select a destination drive click once on the destination drive then click on the Option button. Select the Archive and Install option. You have an option to preserve users and network preferences. Only select this option if you are sure you have no corrupted files in your user accounts. Otherwise leave this option unchecked. Click on the OK button and continue with the OS X Installation.
    4. Upon completion of the Archive and Install you will have a Previous System Folder in the root directory. You should retain the PSF until you are sure you do not need to manually transfer any items from the PSF to your newly installed system.
    5. After moving any items you want to keep from the PSF you should delete it. You can back it up if you prefer, but you must delete it from the hard drive.
    6. You can now download a Combo Updater directly from Apple's download site to update your new system to the desired version as well as install any security or other updates. You can also do this using Software Update.

Maybe you are looking for

  • Calendar & File Upload Components - Threadinar6

    Hi All, This is the sixth in the "Threadinar" series , please see Threadinar5 at http://swforum.sun.com/jive/thread.jspa?threadID=99473 for details In this Threadinar we will focus on the "Calendar" and "File Upload" Components Let us begin our discu

  • DBMS_Metadata package wrapping lines

    How can you set the line size for the DDL that is generated from the DBMS_MetaData pkg? If I try to run the script that is generated by this output, I get errors because things are wrapped. I used this sql to generate my ddl: select dbms_metadata.get

  • Battery charge won't hold

    I need help!  A couple of days ago I was reading a book on my PlayBook for at least 2hours and and the charge still showed 100 per cent. And when I left the PlayBook in stand by mode over night the charge hardly changed at all. This morning the charg

  • Not that it's biggy but whatsup with my new iPad freezing up...

    Not that it's biggy but whatsup with my new iPad freezing up... Should I be worried?

  • Changing source system reference

    Hi,      When I transport from dev to Q, how can I change the source system assignments to Q system? I guess I have to change the assignments as they are referencing dev source system in development and should reference Q when they come to Q. Thanks.