Network confirmation with Personnel number

Hi,
In project systems, While confirming the Network with personnel number, the planned cost is calculating based on Activity rate maintained in KP26. However for actual costs, the calculation is from HR I assume. Am I right?
If it is from HR,  where in HR the time sheet rate is maintained for the personnel number?
Thanks,
Prabha

Hi,
I got the answer.
FYI
If the network confirmation is entered with the personnel number, the system is looking for the "Position" in HR master and based on that it is picking the workcenter assigned with this resource. So the cost is from the activity assigned in the workcenter even though the network is confimed with a different work center.
Thanks for your responses, it helped me in tracing out this issue.
Regards,
Prabha

Similar Messages

  • Confirmation with Serial Number

    Hi all,
    Can anyone explain what's the purpose and how it works with confirmation with serial number? I already do customizing for one single entry confirmation to make serial number appear on CO11n.
    regards,
    Arman

    What ever we entering the serial number  In Confirmation, Its updating In COIB transaction after transfer you can see the list in
    1) Go to IH20 or IH22
    give the material No and serial No U can get the Installation Base No.
    2) Go To IB53
    give the installation No, U can see the assigned serial No . for header material
    BUT there is no standard report for serial no  relate with order operation
    And the table related to serial No "EQUI" is no where link between the  any Confirmation table.

  • PP Confirmation with serial number

    Hi Gurus
    I try to confirm Production orders through serial numbers.
    I customized the confirmation profile in OPK0. i am now able to enter a serial number in CO11N
    If I enter only serial number in CO11N . it is not sufficient for SAP. System requires production order number and Operation. 
    And this message
    Enter confirmation number or order/sequence/operation/suboperation
    Message no. RU001
    I want to confirm only  with serial number is this not possible in SAP?
    Best Regards
    Emre

    Hi,
    Q - I want to confirm only with serial number is this not possible in SAP?
    A - Not Possible
    We need to fallow the standard process.
    1) Need to create serial No profile & same need to maintain in material master.
    2) Create the production order or Purchase order depending on the procurement type material master.
    Procurement Type E - In house produce material - Need to create production order. basically production order is the reference to start the priduction after release the production order.
    Procurement Type F - External Procurement - Need to create purchase order.
    3) We consider the production order, created & released.
    4) Confirmation CO11n- Need to enter production order no & opreation. That operation should final & auto GR relevent.
    5) If operation condition is true, then system will allow to create serial no equal to yield quantity. Confirm the serial no & save.
    6) Check MMBE whether selected serial no get created against material or not.
    Rgd,
    Chetan

  • EIC: Employee search - wild card search with personnel number

    Hi,
    The employee search functionality in EIC employee-search screen allows to search an employee through wild card search. We had set up this and everything was working fine, but suddenly the functionality to search an employee by giving part of personnel number as wild card search is not working, surprisingly other search criteria are listing employee list. For example, if i need to search an employee with personnel no 30000111, then i can give 30* in search criteria and employees starting with 30XXXXXX would be listed. This is the functionality not working at the moment.
    Can anybody please help - what could be the probable cause or where should i look to fix this? Any documentation in this regard would really be helpful.
    Thanks in advance.
    Sujit

    hi,
    Probably u can set a debug point in the bsp application and ask your abaper to debug the same.
    check if any patch application has been done after you saw the functionality working fine.
    Regards
    Sameer

  • Problem with personnel number

    Hi all,
    I deleted all the personnel number using the Report RPUDELPN  but know when I tried to generate the hiring process again I get the personnel number from the position where it was deleted.Let me explain this....
    Suppose I deleted the number from 2-30 now when I start the hiring process again I just get the personnel number starting from 31 but I need to get it generated from the very beginning .
    Thanks all
    Regards
    Navratan

    Hi Navratan
    You will have to reset your Number Range status for this. Basically change the next number to be generated by the number range.
    SPRO --> Personnel Management --> Personnel Administration --> Maintain number range intervals for personnel numbers --> NR Status
    Reset the NR Status number to 4

  • How to link applicant number with personnel Number

    Hii Experts,
    We are trying to extract a report  which will get the employees who have been relieved from the organisation within 90 days..
    Is there any way to findout the applicant number of an employee.Please advice.
    Regards,
    sai,

    Hi Vicky,
    since there is 90 day requirement ,i reckon this need to be customised taking PA0000-MASSN,PA0000-STAT2 and begda and enda into consideration and if there is any date specification (PA41) maintained DAR01 -date type maintained.Hiring action start date and seperation action date.
    No Worries
    KG

  • How to maintain EMP number same as Personnel number

    Hi Expert ,
    I have requirement where i need to create emp number always with personnel number .Any user exit or badi to serve this purpose ?
    This is very urgent requirement so pls help me out

    Hi,
    >>How is the required pl/sql code to do that ?
    In this case, just a SQL code resolve your problem:
    select DOC_NUMBER from doc_number where doc_code = <value> for update;
    update DOC_NUMBER set doc_number = doc_number+1 where doc_code = <value>;
    commit;Cheers

  • 2LIS_04_P_ARBPL; incorrect Delta; missing personnel number in confirmation

    Hi
    I'm facing following problem. I made a new setup of LO-extraction 2LIS_04_P_ARBPL just for one order. The order has one operation "10"  with one quantitiy confirmation from person "123".
    INIT-Load: I get the data correct .
    Delta-Load: I get the quantity confirmation correct but without personnel number.
    I made a new quantity confirmation for user 123 and operation 10. My delta load books the quantity correct but without personnel number. The field PERNR is initial.
    I didnt' found any reason. please help.
    regards
    Pascal

    Mapping errors. Solved on own.

  • Infotype to link Personnel Number with Vendor Master Record

    Hi All,
    pls help me what infotype to link Personnel Number with Vendor Master Record in AP module.
    Customer require when Create Employee then system automatic gernerate Vendor Master.
    pls help us.
    Thanks

    Hi,
    PRAA works absolutely fine. I have external number range for vendors.
    There is an option so that you can create HR accounts in vendor accounts
    Path:Accounting> Financial accounting>Travel
    management>Personal-Related Master Data> Create Vendors (tr.code PRAA)
    Look at this description:
    From the HR master data, this program creates a batch input session for
    maintaining person-specific vendor master records.
    The report can process vendor master records as follows:
    o Initial set up (create/add missing company code segment)
    o Uupdate (change completely according to vendor and HR reference)
    o Change (only according to HR master data, for example, name
    Block
    The following infotypes from HR master data are taken into account for
    the key date specified:
    o Actions (Infotype 0000)
    o Organizational Assignment (Infotype 0001)
    o Personal Data (Infotype 0002)
    o Permanent Residence (Infotype 0006 Subtype 1)
    o Bank Details (Infotype 0009 Subtype 0 or 2)
    All other required data is taken from a reference vendor that you can
    specify as a parameter when you start the program. Note that for the
    reference vendor, reference data must exist for all company codes that
    are applicable according to HR master data. Since program RPRAPA00 cannot
    assign vendor master record numbers externally when creating
    vendor master records, you must be sure that the reference vendor is
    assigned to an account group that requires internal number assignment.
    If no house bank is specified in the reference vendor, this is
    determined via feature TRVHB (Implementation guide for 'Travel Expenses'
    -> Transfer to Data Medium Exchange -> Set up Feature for Determining
    House Bank according to the employee's organizational situation.
    The link between the HR employee's master record and the corresponding
    vendor master record is set up by entering the personnel number in the
    company code segment of the vendor master record.
    General program flow
    Program RPRAPA00 creates a sequential work file in the specified
    directory. Ensure that you use a global directory that can be accessed
    by all application servers; a directory is automatically proposed. The
    work file is later transformed into a batch input session by the
    subsequent program RFBIKR00, which is started automatically.
    In test run mode this program delivers information messages which
    document the creation of a batch input session. Since each information
    message must be confirmed manually, the test run should only be
    performed for a small number of personnel numbers.
    In productive run mode, however, the program RFBIKR00 is automatically
    started as a job; the information mentioned above is stored in the job
    log in this case.
    Initial setup of vendor master records
    Corresponding vendor master records are created from the infotypes
    listed above and the non-HR-specific information from the reference
    vendor. During the process, the personnel number is stored in the
    company code segment of the vendor master record. Persons who already
    have a vendor master record with corresponding personnel number are
    rejected in this run.
    If a vendor master record already exists for a personnel number, but
    without a company code segment for the company code in which the
    employee exists at the key date entered, the program adds the required
    company code segment to the vendor master record. You must however
    activate the checkbox "Create new company code segment for existing
    vendor master records".
    The HR master data used is the info type record valid on the key date
    entered.
    Update of vendor master records
    The corresponding vendor master records are updated from the infotypes
    listed above and the non-HR-specific information from the reference
    vendor. Persons who already have a vendor master record with
    corresponding personnel number are rejected in this run. The system uses
    HR master data from the infotype records valid for the key date.
    Change vendor master records according to HR master data
    All HR-specific data is changed in the vendor master records for
    personnel numbers that have changes since the date recorded under '...
    with last change since'. The system uses HR master data again from the
    infotype records valid for the key date specified.
    Block vendor master records
    All vendor master records which correspond with the selected personnel
    numbers are blocked for posting.
    User exits
    For the following situations, two empty routines are supplied in the
    includes RPRAPAEX and RPRAPAEX&H5F001 which you can adapt to your
    requirements.
    o The employee's last name is entered in the sort field in the vendor
    master record. If you do not want this to happen, you can program
    the situation you want in the user exit routine
    'set&H5Fmc&H5Ffield&H5Fby&H5Fuser'.
    o If the address editing in the vendor master record does not suit
    your requirements, it can also be changed. For this purpose you have
    the user exit routine 'set&H5Faddress&H5Fby&H5Fuser'.
    o If you want to assign numbers to the vendor master records to be
    created via external number assignment (for example, vendor master
    record number &H3D personnel number), you can adjust the user exit
    routing 'SET&H5FVENDOR&H5FNO&H5FBY&H5FUSER' (in include RPRAPAEX&H5F00). Note
    that
    the account group of the reference vendor must also have external
    number assignment.
    Note that in each case a thorough knowledge of the programming
    language
    ABAP/4 is necessary.
    Set up vendor master records in a separate system
    The distribution of personnel master data from a HR system to an FI
    system is a prerequisite for creating, changing, and blocking vendor
    master records.
    In the section Master Data Distribution (link to separate HR unit) of
    the ALE IMG, an explanation is given regarding the way in which the
    FI
    System is supplied with the relevant employee data from the HR System
    In the FI System, report RPRAPA00 described here can be used to
    create,
    change, and block vendor master records.
    Other wise try with VPE1 t.code.
    Regards
    Devi

  • Assigning a personnel number (PERNR) to a network - CN21/22

    Hello guys,
    I would like to know how to assign a personnel number to a network. I have been able to do it on the person assignment tab in an activity but the field PERNR in AFVC table is blank? Is this the correct way to assign a personnel number to a network? How the field PERNR in AFVC table should get fill for a network?
    Thanks and regards,
    Ally

    Hello Yahsaar,
    Agree with Sudhakar & Panagiotis.
    Person assignment needs to be done in Internal Activities created under Network. Ensure that appropriate Work center is maintained in internal Activity.
    Then in Work Center, go to HR assignment and do the assignment of Person's position number in it.
    Hope this helps.
    Regards
    Tushar

  • Assign personnel number with workcenter.

    I want to assign employee ID number with maint. work center. It will be helpful in completion confirmation.
    How can we do this ? I have clicked on HRMS in work center(change screen), but after this where do we enter the personnel number ?
    Regards,
    VM

    Done. We will have to goto capacity header. Then click HRMS, then click on person and enter the employee ID. Similarly we can enter position also.
    Regards,
    VM

  • Multiple personnel number assignment in the confirmation

    Hi Experts
    Can anybody tell me how to assign multiple personnel numbers for each operation confirmation of the production order. System is not allowing me to assign the multiple employee codes in the confirmation.
    I have maintained No. of individual capacities in the work center capacity category of Labor and assigned one personnel number for each individual capacity.
    I have tried to change the confirmation screen settings in the IMG, but still system is not allowing me to assign multiple personnel numbers.
    Please suggest me how to achieve this.
    Regards
    Prabhakar

    Hi ,
    Thank you very much for your quick reply . I will check with my ABAPER and let you know .
    I am unable to Log in with my previous user id , so sorry , I am unable to give you any points .
    Regards
    Prabhakar
    Edited by: preddy27 on Jan 25, 2011 9:04 AM

  • I have just transferred my application file from an Imac to an identical Imac, both running OS 10.9.5. When I attempt to open Photoshop 6, I am prompted for the serial number. I enter the serial number provided by Adobe, which I have confirmed with my "pr

    I have just transferred my entire application file from an Imac to an identical Imac, both running OS 10.9.5. Everything works fine, excepting that when I attempt to open Photoshop 6, I am prompted for the serial number. I enter the serial number provided by Adobe, which I have confirmed with my "previous purchase" records kept by Adobe. It is demanding a "qualifying product", all of which is contained in the complete files I transferred. Why can't Adobe recognise my valid serial number for Photoshop 6?

    I have just transferred my entire application file from an Imac to an identical Imac,
    Say what?
    Please use the proper installer.
    Are you really talking about Photoshop 6 or about Photoshop CS6?

  • MIRO invoice creation with the Personnel Number in account assignment

    I am using BAPI_INCOMINGINVOICE_CREATE for creating an Invoice using MIRO transaction.
    In MIRO transaction-> PO reference-> Multiple account assignment-> we have the personnel number: In BAPI table-parameter ACCOUNTINGDATA and ITEMDATA is used to populate the account assignmet data but this structure doesn't have the Personnel Number field (PERSON_NO).
    How can i create an Invoice with the Personnel Number in Account assignment, Is there any Userexit or BADI is available ?
    Thanks,
    Fract
    Edited by: fract_get on May 23, 2011 6:49 PM

    You can use EXTENSIONIN parameter from tables. There are BADI's related to this but don't know the name of badi. Please search forum for or use transaction code SE84 to search the BADI's/
    you can check the badi: INVOICE_UPDATE and method 'before_save or something similar to map to db table fields.
    See this thread to understand how extension parameters works.
    bapi_salesorder_simulate extension bape_vbap standard field
    Edited by: Sampath Kumar on May 23, 2011 11:28 AM

  • Problems with goods movements cancelling network confirmations

    Hello experts,
    I'm having some problems with goods movement when cancelling network confirmations.
    I assign a component for a operation in the project builder (CJ20N). Then when I execute a confirmation for that operation in CN25 everything works correctly, I can assign the time for the confirmation and SAP automatically carries the component assigned to the operation. Once I have done the confirmation the goods movements and the hours have a correct account assignment.
    The problem is that if I cancel this confirmation, the hours are correctly cancelled but the component is still there. If I try to cancel the goods movement with MIGO it is no possible because the system says that must be cancelled with the corresponding transaction (CN29) but, as I have said, the system does not cancel it.
    On the other hand, If the goods movement goes to COGI transaction and then I post-process the error, If later I cancel the confirmation, everything works correctly.
    Does anybody know why this could happen?
    Thanks and regards
    Laura

    Hi
    I think this question was raised earlier also. The best way is to allot a fixed time slot for your users so as to avoid clash. I suppose i explained that the master data of any material is stored at one place only and if you schedule a background job for this then all your good movement transaction will be in que and performed in orderly manner.
    If automatic posting is not possible then use the time slot method.
    Krishna

Maybe you are looking for

  • Query to populate an alert message to avoid the duplication of Reference no

    Hi Experts, SUB:Query to populate an alert message to avoid the duplication of BP reference no. In A/R invoice, BP reference (numAtcard) is used to enter sales Order no as the reference number. As human error, double A/R invoice is created to that pa

  • HP Officejet Pro 8620 - Scan to TIFF?

    I don't own this MFP so it's not in front of me. I'm trying to assist a client who keeps sending PDFs that are too large for our portal.  If he could send as TIF/TIFF it would likely be much smaller.   I've looked at the manual and don't see instruct

  • Changing Clip Name

    I understand that the best time to name a clip is when capturing. And changing a clip name will pose a problem when reconnecting media. However, if the "clip name" is changed via "item properties" in the browser AND the "QT file" in the "Capture Scra

  • Motion 3 crash during training

    I purchased the Motion 3 training book While going threw lesson 2 it crashed over and over when I tried adding the "Sharpen" filter. Other than that I can't proceed to E.blendmodes.motn stage - it crashes again & again

  • How to transport a custom table data into QA

    Hi, Requirement is to transport data maintianed in customtable from DEV into QA. I have maintianed the delivery class to "C" in attribute and Data class to "APPL2" for this custom table. But still i am getting following error when trying to insert th