Network Header at the Project Planning Board gantt chart
Hi again,
Does anyone knows a configuration to allow the network header to appear in the project planning board gantt chart?
Tks
James
Try transaction OPT7
Double click on the appropriate Profile
On the Table Area Tab, select the flag for the field "Display Network"
Hope this helps
Regards
Steve
Similar Messages
-
Default print settings in the Project Planning Board CJ02N CJ2C
Hello
When you print the Project Planning Board CJ02N/CJ2C - there is an option to change the page setup.
I would like to change the default settings for left,right, top and bottom margins for all users.
Can anyone suggest where this would be done ?
Thankyou
RosHi Varun,
Thanks for the fast repply!
Please see below the CJ2C and CNE5 screen shots:
Thanks and Regards
James -
Ability to display multiple texts within graphic planning board Gantt chart
I have been unable to change the planning board Bar Chart Graphic Profile (OPG0 and OPG9) to be able to display both material text and a user field within the Gantt chart graphic. I have copied the SAPSFCG011 profile and created my own. The profile is displayed below from CMCH.
Overall prof: ZBWSFCG011 SFC: View work center/capacity (3 graf.)
...... Select.profile: ZBWSFCS001 SFC: View work center -> cap.(3 graf.)
...... Control profile: ZBW___C002 Gen: Planning table
...... Time prof: ZBW___Z002 Gen: Medium-term (3 months)
...... Evaluation prof.: ZBW___A001 Gen: Standard evaluation profile
...... Strategy prof.: ZBW___T001 Finite scheduling forw./all functs.activ
...... Capacity planning table: ZBWSFCL010 SFC: only main cap. (3 graf.)
.......... Graphics profile ZBW___X002 BARC 1 Default profile 2 Capa. planning board
.......... Chart sequence ZBWSFCT002 SFC: Main caps. (3 graph.)
.......... Layout ID ZBWSFCLA10 SFC: Work center view (graphical)
.......... LineRepresSelection ZBW___ZR02 SAP standard 2
.......... Scale time axis SAP___M031 Stand. weekly per. split rough
.......... Graph.object.select. ZBW___OA02 Pool group order path
.............. DStat Sq Structur Field na ROp Comparison val NStat Struct
.............. 00000 01 KBED TYPKZ NE 1 00001
.............. 00000 02 AFVG OBJNR ST SAP005 00000 SAP002 Standard operation partially confirmed
.............. 00000 03 AFVG OBJNR ST SAP006 00000 SAP003 Standard operation completely confirmed
.............. 00000 99 DEF 00000 ZJB000 Standard operation
................... Graphical object type ZJB000 Standard operation
........................ Form type 22 Plan. board:Graphic obj. w. ordNo matTxt
........................... Form group ZBW001
............................... Form definition PLTO22 Planning board graphic order and mat.txt
.................................. Layout definition [[$a//$b]]
.................................. Layout definition
.................................. Layout definition
.................................. Layout definition
In addition to the profile change, I have configured the graphical object type ZJB000 (in OPG9) to look as follows:
0 AFKO Order header MATXT Material description
2 KBED Capacity requirements A SSTAD Latest start / date SSTAU Latest start / time
3 KBED Capacity requirements A SSSBD Latest scheduled start: Processing (date) SSSBZ Latest scheduled start: Processing (time)
4 KBED Capacity requirements A SSSAD Latest scheduled start: Teardown (date) SSSAZ Latest scheduled start: Teardown (time)
5 KBED Capacity requirements A SENDD Latest finish / date SENDU Latest finish / time
6 AFVG Order operation USR08 User field for date
I have found that the 2nd text field (USR08) must be added as the last step (#6). When I had it as #1, the planning board did not display the USR08 value.
Now both are displayed in the Gantt chart graphic. However, it is difficult to see this long string of data as the bars in the Gantt chart may not be long enough to display the data.
Therefore we would like to use the "hover over" text which is displayed in the status line at the bottom of the screen. We have tried using both the Info Text and the Quick Info options within the Bar Chart: Options Profile (OPG0). Only the first text (the material descirption) is dislayed within either the Quick Info or the Info Text.
Is it possible to have multiple object values appear in Quick Info or Info Text? Or is it possible to control which text is displayed in the Quick Info or Info Text?
Any help in this area would be greatly appreciated, as this is a make-or-break issue for the business to use the planning board. Thank you!I'm also looking for a standard customizing alternative to do the same thing.
Still, if you're interested, I've already done it successfully with user exit PLAT0001.
Hope this helps.
Best regards. -
Scheduling comparision in Gantt Chart- Project planning board
Hi All,
I Need to use the "Scheduling comparision" in Project planning board gantt chart. This is to compare the original status of activities before and after scheduling.
But the "Scheduling comparision" button in the PPB does'nt seem to work.
( I am selecting the activity and then pressing the button for"display original status" )
How do I use this functionality?
Thanks in advance.Hi Potluri Srinivas ,
After some tests, I still donot get, how does this functionalties work either.
I assume, it is linked with the setting in 'option' -> 'planning board' -> 'diagramm area' -> 'orginal schedule'. But I donot know, how the two things linked directly.
If you find it out, please post it.
Thanks and regards,
Zhenbo -
Project planning board report to microsoft project report
hi all
good morning
i want to convert the project planning board report to Microsoft project and primavera report ...
please guide me through the steps......
Thanks in advance
SuryaHi,
OpenPS for Microsoft project (OpenPS4MSP) is an Add-on to SAP R/3 Project System which enables users to transfer project related data between Microsoft Project and R/3 Project System.
Refer SAP Note: 579761 for OpenPS.
Then to integrate SAP and Primavera , you can use various integration tools available. One of them is Primavera Inspire.
Refer :
http://www.oracle.com/applications/primavera/primavera-inspire-for-sap.html
Regards,
Amit -
Viewing CO versions in project planning board
Hello,
I have saved two CO versions of my project. When i go to the project planning board the approved plan column is full of data and looks great but the other version as no information. I have SAPALL so this isn't an authorization issue. Can someone please help me work out was is wrong?
Thanks a lot
JasonHi,
Basically there are possibilities of creating Plan version.
1) one you can create in CJ40 by manually feeding the Version ex:0,1,2 etc....
2) create one version in CJ40 and copy the same to another version in CJ9BS.
once the versions are created make the changes of values in the respective versionand save the changes.
Please check the version comparission in S_ALR_87013539 - Project Version Comparison: Plan.
Comming to plan board which fields did you picked up for comparission?
Rgds
Sudhir Reddy -
Project Planning Board - Customising
Hello All,
Do we have an option to customize project planning board.
If yes where exactly in SPRO can we do this, and does anyone have any documentation on what all can be configured in project planning board.
Points assured.
Thanks in advance.
Warm Regards,
Jatinder BansalProject planning board customization is available at IMG. path IMG>PS>Structures>Project Planning Board.
Planning Board is based on Gannt chart. the customization includes, Define Time Profiles, Define profiles for time scales , Define scale for the time axis, Define Profiles for the Project Planning Board, Maintain Report Assignment from the Planning Board & Capacity Leveling/Capacity Evaluations.
Regards
Murali -
Activity bar not displaying on Project planning board
Dear All,
I am getting one problem related to project planning board. I am working on a system in which when i am trying to run project planning board, its coming but in that gant chart i am not able to see bar for activity. Bar for project definition and wbs coming properly. In tabular form also i can see the activities. But the only problem i am not able to see bar for activity with relationships. I have check almost all configuration related to project planning board profile and also scheduling proflies.
Kindly suggest what can be the reason for the same.
Regards
Abhishek SinhaHi Abdul,
Thanks for reply. I have check all these options but all things are in place. OPT7 setting also right there. Kindly suggest what other setting can affect. In the planning board i can see the activity at left hand side corner with details but in gantt chart where we see bar chart for schdulines there activties are not coming.
Kindly suggest.
Regards
Abhishek Sinha -
Small Font for Date in Project Planning Board
Hello Friends?
Iam Using ECC 6.0 C Version in our Company. iam facing a problem in <b>CJ2B</b> that Date is displaying in very small font. i could n't solve that problem till date. Can any body help me where can we make settings for making fonts size bigger for <b>dates</b> other than zooming in Planning Board.
Appreciable for ur kind information.
Thanks.Hi Hari,
Once you are into CJ2B, Please follow the following steps:
1. Click on the icon " Planning board Assistant"
2. Select the gantt Chart----Misc. in diagram Area
3. In the Selection of the "Text" of "Date Descript."--- Select "Dates one-line " ( This is applicable if your date is on the left or right side of the date bar)
4. Now you can change the Font colour, Font and Font Size, Bold or Italic.....
5. To Confirm the setting Click on "Update graphics" button on the screen.
6. Now, If you notice, the dates fonts will be as per your requirement.
If this does'nt work.. Try to explore in this area only..Probably try selecting other "Text" in the "date Descript."
Hope this helps.
Warm regards,
Srinivas Potluri -
Issue while saving the project plans into XML
Hi,
Could anyone of you please help me here.
We are having one custom field(Type: Text) in the project level(Custom field name: ProjectComments) and end users are entering the data against this custom field more than 200 characters.
The problem here is when we are saving the project plans into XML and opening the same file again thorugh MPP, the data for this custom field(ProjectComments) is showing till 129 Characters only. Seems to be the data is truncating till 129 charachers.
Could anyone suggest me how to resolve this issue without trucnating the characters in the custom fields.
Thanks in advance!
Regards,
VenkatHi,
I cannot reproduce this issue with Project Pro 2010 SP2. Which SP do you have? How is configured your custom field?
Hope this helps,
Guillaume Rouyre, MBA, MVP, MCP | -
Hiding the Optimizer button from the DS planning board
Hi
How to hide the optimizer button from the DS planning board ..
ThanksHi Chak
I think the problem may be with a livecache inconsistency. The Planning Board should be reading it's information from the livecache, whereby the Product View may be getting it's situation from the database. Try running the livecache consistency checks if it occurs again.
Regards -
Unicode in Project Planning Board Screen (CJ20N)
Hi,
I'm facing a problem of unicode as follows:
I inputed some unicode (Vietnamese) at Project Structure screen, It is ok. but when I switch to Project Planning Board screen, It don't work. I also cannot input Vietnamese with unicode at this view.
Text example: "Các công tác chuẫn bị"
Please help!
Thanks
LongHi,
Found something on Service.sap.com
Thought would be useful..
To access this page you need a login id for service.sap.com
https://websmp108.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000557148&
thanks.. -
Reason for delay on the DS planning board grafic
Dear SAP Fans
Have you done any development on the DS planning board to show reason of the delay of a planned order?
We are implementing PP/DS and this is a hard requirement for the acceptance. The users have another schedule system with this functionality, when an order is delayed you can see the reason in the chart by clicking on the delayed order. When they see the reason they can see all the constraints that prevent the optimizer to schedule the planned order in an early date, for example:
- Order 0001 is delayed to 15.04.2011 because;
- Reason 1: Machine A is unavailable up to 30.03.2011
- Reason 2 : Componente 0001-01 have purchase order scheduled to 15.04.2011
- Reason 3 : PRT is under maintenance up to 10.04.2011
With this information on hand the user can take some actions to antecipate the order in case this order is causing delay on a priority A customer order. For example the actions could be:
- For reason 1, rearrange orders in the machine to schedule the order in an early date.
- For reason 2, negotiate with supplier an early delivery date.
- For reason 3, negotiate with plant maintenance to accelerate it.
Maybe something related to look for the delay log of a specific order.
Appreciate any insight.
Thanks and BRhello,
first check the operations of the order.
right click on the produce operation and navigate to Order Processing.
In the order tree open all nodes for operations.
Is the set up activity visible there?
If yes doble click on the activity.
does the set up activity have a duration?
If yes check the status of the set up activity.
go back to the planning board.
in the menue select extras-> Legend
a pop-up with the graphical objects is displayed.
Check the graphic objects for the activity status you read before.
did you change the customizing settings for the graphic object?
If yes check them again or reset them to the default SAP settings.
I had a similar problem with a set up activity when I wanted to change the color of the activity according to the set up group. I changed the settings in the customizing Maintain Planning Board Profiles.
It is very difficult to maintain the decision table for graphical objects.
If you did this recheck the decision table.
Go back to the SAP default settings and check the planning board again.
Are the set up acitvities displayed now?
Then the porblem is with the decision table.
rethink every step again. -
Validation in the network header for the responsible cost center field
Hi Experts,
I want to do the validation for the network header that, the cost center in responsible cost center field of WBS & network should be same... If the user enters other than WBS in the network it should give an error message....
when i am trying to do validation in the network header i am unable to see the filed of the responsible cost center for the WBS element.
kindly suggest how can i achieve these....
with regards
Raman T SHi Abdul,
Thank you for your reply. There was no entries in the GB01. I went to SM30 & in view V_GB01C i maintained the entries
as
Boolean Class - 71 - WBS element
Class type - B
Table - PRPS
Field - FKSTL.
Next i went to maintain the validation in the T-Code OPSI, i am unable to find the field of the WBS element cost-center in the Network header.
Can u tell me if i had done anything wrong in the above steps.
what the user exit for the network can u tell me...
With Regards
Raman T S -
Actual Time bar for the activity duration in Gantt Chart
Hi all,
The Actual time bar for the elapsed activity duration in Gantt chart is not appearing. The same is true for all the activities i.e. activities which are not yet confirmed and activities which are partially confirmed.
Is there any customizing for the same? ( I am getting the bar in IDES, but not in DEV/QAS/PRD )
Any Help in this regards will be highly appreciated
Warm regards,
Srinivas PotluriHai Srinivas
Got the solution.
1)For this first check in the project profile of the Hierarchry graphic -
Time scheduling profile - check the colour patterns which been assigned.
2)open the project - Cj20N - go to planning board - bar chart - under settings - Planning board assistant - Gantt chart - check the dates display for Project definition , WBS , Acitivity - try to change the colour and check.
while changing can see - basic date of the acitivity. based on the confirmation can see the bar confirmed activity with respect to basic date. the bar confirmation will show withrespect to duration.
3) If the bar chart need in daily /hourly - can check in CNE5 . click on the graphics -bar chart - which u will get the bar chart - in this choose the Time Axis - where can select the monthly /weekly/daily /hourly format .
Award points if clear and got the solution.
Regards
PP
Maybe you are looking for
-
How to check whether a user session is null or not
Hi I am using Jdeveloper 11.1.2.2 I have a use case of running some Junit test case, this is the problem I have : There are some Junit tests which are written for some VO's. While testing insert and update operation in Junit there is two mandatory co
-
How PLM Document save on content server
Hi All, Please tell me the concept about given below scenario: Normally PLM documents are either saved in the Content Server or in the database. What if we have neither configured a database nor a content server. Where are they being stored then. wha
-
How can we see the errors displayed in IDOC?
-
Error while installing AD exchange connector
Hi All, When I m trying to install exchange connector 9.1.1.7.0 in OIM 11.1.1.3.0 I m getting the following error the error occurred while importing connector xml files please help me in this regards DOBJ.XML_IMPORT_ERROR oracle.iam.reconciliation.ex
-
Enter an equation into a textbox and it will automatically calculate an answer
Hi All, I have created two textboxes. What I would like to do is after entering an equation, e.g. "(9-5)*30 + 1", into the textbox 1, textbox 2 will automatically gives me the answer "121". I have no idea which function can give me an int 121 from a