Network Header at  the Project Planning Board gantt chart

Hi again,
Does anyone knows a configuration to allow the network header to appear in the project planning board gantt chart?
Tks
James

Try transaction OPT7
Double click on the appropriate Profile
On the Table Area Tab, select the flag for the field "Display Network"
Hope this helps
Regards
Steve

Similar Messages

  • Default print settings in the Project Planning Board CJ02N CJ2C

    Hello
    When you print the Project Planning Board CJ02N/CJ2C - there is an option to change the page setup.
    I would like to change the default settings for left,right, top and bottom margins for all users.
    Can anyone suggest where this would be done ?
    Thankyou
    Ros

    Hi Varun,
    Thanks for the fast repply!
    Please see below the CJ2C and CNE5 screen shots:
    Thanks and Regards
    James

  • Ability to display multiple texts within graphic planning board Gantt chart

    I have been unable to change the planning board Bar Chart Graphic Profile (OPG0 and OPG9) to be able to display both material text and a user field within the Gantt chart graphic.  I have copied the SAPSFCG011 profile and created my own.  The profile is displayed below from CMCH.
    Overall prof: ZBWSFCG011           SFC: View work center/capacity (3 graf.)
    ...... Select.profile:                     ZBWSFCS001      SFC: View work center -> cap.(3 graf.)
    ...... Control profile:                    ZBW___C002      Gen: Planning table
    ...... Time prof:                           ZBW___Z002      Gen: Medium-term (3 months)
    ...... Evaluation prof.:                 ZBW___A001      Gen: Standard evaluation profile
    ...... Strategy prof.:                    ZBW___T001      Finite scheduling forw./all functs.activ
    ...... Capacity planning table:      ZBWSFCL010      SFC: only main cap. (3 graf.)
    .......... Graphics profile                      ZBW___X002      BARC    1  Default profile 2 Capa. planning board
    .......... Chart sequence                      ZBWSFCT002      SFC: Main caps. (3 graph.)
    .......... Layout ID                                 ZBWSFCLA10      SFC: Work center view     (graphical)
    .......... LineRepresSelection                 ZBW___ZR02      SAP standard 2
    .......... Scale time axis                         SAP___M031      Stand. weekly per. split rough
    .......... Graph.object.select.                ZBW___OA02      Pool group order path
    .............. DStat Sq Structur Field na ROp Comparison val NStat Struct
    .............. 00000 01 KBED     TYPKZ    NE  1                      00001
    .............. 00000 02 AFVG     OBJNR    ST  SAP005         00000 SAP002 Standard operation partially confirmed
    .............. 00000 03 AFVG     OBJNR    ST  SAP006         00000 SAP003 Standard operation completely confirmed
    .............. 00000 99                   DEF                                  00000 ZJB000 Standard operation
    ................... Graphical object type               ZJB000          Standard operation
    ........................ Form type                           22              Plan. board:Graphic obj. w. ordNo matTxt
    ........................... Form group                          ZBW001
    ............................... Form definition                     PLTO22          Planning board graphic order and mat.txt
    .................................. Layout definition                   [[$a//$b]]
    .................................. Layout definition
    .................................. Layout definition
    .................................. Layout definition
    In addition to the profile change, I have configured the graphical object type ZJB000 (in OPG9) to look as follows:
    0     AFKO     Order header                          MATXT     Material description                                                                     
    2     KBED     Capacity requirements     A     SSTAD     Latest start / date     SSTAU     Latest start / time
    3     KBED     Capacity requirements     A     SSSBD     Latest scheduled start: Processing (date)     SSSBZ     Latest scheduled start: Processing (time)
    4     KBED     Capacity requirements     A     SSSAD     Latest scheduled start: Teardown (date)     SSSAZ     Latest scheduled start: Teardown (time)
    5     KBED     Capacity requirements     A     SENDD     Latest finish / date     SENDU     Latest finish / time
    6       AFVG    Order operation                       USR08    User field for date                                                                               
    I have found that the 2nd text field (USR08) must be added as the last step (#6).  When I had it as #1, the planning board did not display the USR08 value.
    Now both are displayed in the Gantt chart graphic.  However, it is difficult to see this long string of data as the bars in the Gantt chart may not be long enough to display the data. 
    Therefore we would like to use the "hover over" text which is displayed in the status line at the bottom of the screen.  We have tried using both the Info Text and the Quick Info options within the Bar Chart: Options Profile (OPG0).  Only the first text (the material descirption) is dislayed within either the Quick Info or the Info Text.
    Is it possible to have multiple object values appear in Quick Info or Info Text?  Or is it possible to control which text is displayed in the Quick Info or Info Text?
    Any help in this area would be greatly appreciated, as this is a make-or-break issue for the business to use the planning board.  Thank you!

    I'm also looking for a standard customizing alternative to do the same thing.
    Still, if you're interested, I've already done it successfully with user exit PLAT0001.
    Hope this helps.
    Best regards.

  • Scheduling comparision in Gantt Chart- Project planning board

    Hi All,
    I Need to use the "Scheduling comparision" in Project planning board gantt chart. This is to compare the original status of activities before and after scheduling.
    But the "Scheduling comparision" button in the PPB does'nt seem to work.
    ( I am selecting the activity and then pressing the button for"display original status" )
    How do I use this functionality?
    Thanks in advance.

    Hi Potluri Srinivas ,
    After some tests, I still donot get, how does this functionalties work either.
    I assume, it is linked with the setting in 'option' -> 'planning board' -> 'diagramm area' -> 'orginal schedule'.  But I donot know, how the two things linked directly.
    If you find it out, please post it.
    Thanks and  regards,
    Zhenbo

  • Project planning board report to microsoft project report

    hi all
    good morning
    i want to convert the project planning board report to Microsoft project and primavera report ...
    please guide me through the steps......
    Thanks in advance
    Surya

    Hi,
    OpenPS for Microsoft project (OpenPS4MSP) is an Add-on to SAP R/3 Project System which enables users to transfer project related data between Microsoft Project and R/3 Project System.
    Refer SAP Note: 579761 for OpenPS.
    Then to integrate SAP and Primavera , you can use various integration tools available. One of them is Primavera Inspire.
    Refer :
    http://www.oracle.com/applications/primavera/primavera-inspire-for-sap.html
    Regards,
    Amit

  • Viewing CO versions in project planning board

    Hello,
    I have saved two CO versions of my project. When i go to the project planning board the approved plan column is full of data and looks great but the other version as no information. I have SAPALL so this isn't an authorization issue. Can someone please help me work out was is wrong?
    Thanks a lot
    Jason

    Hi,
       Basically there are possibilities of creating Plan version.
    1) one you can create in CJ40 by manually feeding the Version ex:0,1,2 etc....
    2) create one version in CJ40 and copy the same to another version in CJ9BS.
    once the versions are created make the changes of values in the respective versionand save the changes.
    Please check the version comparission in S_ALR_87013539 - Project Version Comparison: Plan.
    Comming to plan board which fields did you picked up for comparission?
    Rgds
    Sudhir Reddy

  • Project Planning Board - Customising

    Hello All,
    Do we have an option to customize project planning board.
    If yes where exactly in SPRO can we do this, and does anyone have any documentation on what all can be configured in project planning board.
    Points assured.
    Thanks in advance.
    Warm Regards,
    Jatinder Bansal

    Project planning board customization is available at IMG. path IMG>PS>Structures>Project Planning Board.
    Planning Board is based on Gannt chart. the customization includes, Define Time Profiles, Define profiles for time scales ,  Define scale for the time axis, Define Profiles for the Project Planning Board, Maintain Report Assignment from the Planning Board & Capacity Leveling/Capacity Evaluations.
    Regards
    Murali

  • Activity bar not displaying on Project planning board

    Dear All,
    I am getting one problem related to project planning board. I am working on a system in which when i am trying to run  project planning board, its coming but in that gant chart i am not able to see bar for activity. Bar for project definition and wbs coming properly. In tabular form also i can see the activities. But the only problem i am not able to see bar for activity with relationships. I have check almost all configuration related to project planning board profile and also scheduling proflies.
    Kindly suggest what can be the reason for the same.
    Regards
    Abhishek Sinha

    Hi Abdul,
    Thanks for reply. I have check all these options but all things are in place. OPT7 setting also right there. Kindly suggest what other setting can affect. In the planning board i can see the activity at left hand side corner with details but in gantt chart where we see bar chart for schdulines there activties are not coming.
    Kindly suggest.
    Regards
    Abhishek Sinha

  • Small Font for Date in Project Planning Board

    Hello Friends?
    Iam Using ECC 6.0 C Version in our Company. iam facing a problem in <b>CJ2B</b> that Date is displaying in very small font. i could n't solve that problem till date. Can any body help me where can we make settings for making fonts size bigger for <b>dates</b> other than zooming in Planning Board.
    Appreciable for ur kind information.
    Thanks.

    Hi Hari,
    Once you are into CJ2B, Please follow the following steps:
    1. Click on the icon " Planning board Assistant"
    2. Select the gantt Chart----Misc. in diagram Area
    3. In the Selection of the "Text" of "Date Descript."--- Select "Dates one-line " ( This is applicable if your date is on the left or right side of the date bar)
    4. Now you can change the Font colour, Font and Font Size, Bold or Italic.....
    5. To Confirm the setting Click on "Update graphics" button on the screen.
    6. Now, If you notice, the dates fonts will be as per your requirement.
    If this does'nt work.. Try to explore in this area only..Probably try selecting other "Text" in the "date Descript."
    Hope this helps.
    Warm regards,
    Srinivas Potluri

  • Issue while saving the project plans into XML

    Hi,
    Could anyone of you please help me here.
    We are having one custom field(Type: Text) in the project level(Custom field name: ProjectComments) and end users are entering the data against this custom field more than 200 characters.
    The problem here is when we are saving the project plans into XML and opening the same file again thorugh MPP, the data for this custom field(ProjectComments)  is showing till 129 Characters only. Seems to be the data is truncating till 129 charachers.
    Could anyone suggest me how to resolve this issue without trucnating the characters in the custom fields.
    Thanks in advance!
    Regards,
    Venkat

    Hi,
    I cannot reproduce this issue with Project Pro 2010 SP2. Which SP do you have? How is configured your custom field?
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, MCP |

  • Hiding the Optimizer button from the DS planning board

    Hi
    How to hide the optimizer button from the DS planning board ..
    Thanks

    Hi Chak
    I think the problem may be with a livecache inconsistency. The Planning Board should be reading it's information from the livecache, whereby the Product View may be getting it's situation from the database. Try running the livecache consistency checks if it occurs again.
    Regards

  • Unicode in Project Planning Board Screen (CJ20N)

    Hi,
    I'm facing a problem of unicode as follows:
    I inputed some unicode (Vietnamese) at Project Structure screen, It is ok. but when I switch to Project Planning Board screen, It don't work. I also cannot input Vietnamese with unicode at this view.
    Text example: "Các công tác chu&#7851;n b&#7883;"
    Please help!
    Thanks
    Long

    Hi,
    Found something on Service.sap.com
    Thought would be useful..
    To access this page you need a login id for service.sap.com
    https://websmp108.sap-ag.de/~form/sapnet?_SHORTKEY=01100035870000557148&
    thanks..

  • Reason for delay on the DS planning board grafic

    Dear SAP Fans
    Have you done any development on the DS planning board to show reason of the delay of a planned order?
    We are implementing PP/DS and this is a hard requirement for the acceptance. The users have another schedule system with this functionality, when an order is delayed you can see the reason in the chart by clicking on the delayed order. When they see the reason they can see all the constraints that prevent the optimizer to schedule the planned order in an early date, for example:
    - Order 0001 is delayed to 15.04.2011 because;
             - Reason 1:  Machine A is unavailable up to 30.03.2011
             - Reason 2 : Componente 0001-01 have purchase order scheduled to 15.04.2011
             - Reason 3 : PRT is under maintenance up to 10.04.2011
    With this information on hand the user can take some actions to antecipate the order in case this order is causing delay on a priority A customer order. For example the actions could be:
              - For reason 1, rearrange orders in the machine to schedule the order in an early date.
              - For reason 2, negotiate with supplier an early delivery date.
              - For reason 3, negotiate with plant maintenance to accelerate it.
    Maybe something related to look for the delay log of a specific order.
    Appreciate any insight.
    Thanks and BR

    hello,
    first check the operations of the order.
    right click on the produce operation and navigate to Order Processing.
    In the order tree open all nodes for operations.
    Is the set up activity visible there?
    If yes doble click on the activity.
    does the set up activity have a duration?
    If yes check the status of the set up activity.
    go back to the planning board.
    in the menue select extras-> Legend
    a pop-up with the graphical objects is displayed.
    Check the graphic objects for the activity status you read before.
    did you change the customizing settings for the graphic object?
    If yes check them again or reset them to the default SAP settings.
    I had a similar problem with a set up activity when I wanted to change the color of the activity according to the set up group. I  changed the settings in the customizing Maintain Planning Board Profiles.
    It is very difficult to maintain the decision table for graphical objects.
    If you did this recheck the decision table.
    Go back to the SAP default settings and check the planning board again.
    Are the set up acitvities displayed now?
    Then the porblem is with the decision table.
    rethink every step again.

  • Validation in the network header for the responsible cost center field

    Hi Experts,
           I want to do the validation for the network header that, the cost center in responsible cost center field of WBS & network should be same... If the user enters other than WBS in the network it should give an error message....
    when i am trying to do validation in the network header i am  unable to see the filed of the responsible cost center for the WBS element.
    kindly suggest how can i achieve these....
    with regards
    Raman T S

    Hi Abdul,
       Thank you for your reply. There was no entries in the GB01. I went to SM30 & in view V_GB01C i maintained the entries
    as
    Boolean Class - 71 - WBS element
    Class type - B
    Table - PRPS
    Field - FKSTL.
    Next i went to maintain the validation in the T-Code OPSI, i am unable to find the field of the WBS element cost-center in the Network header.
    Can u tell me if i had done anything wrong in the above steps.
    what the user exit for the network can u tell me...
    With Regards
    Raman T S

  • Actual Time bar for the activity duration in Gantt Chart

    Hi all,
    The Actual time bar for the elapsed activity duration in Gantt chart is not appearing. The same is true for all the activities i.e. activities which are not yet confirmed and activities which are partially confirmed.
    Is there any customizing for the same? ( I am getting the bar in IDES, but not in DEV/QAS/PRD )
    Any Help in this regards will be highly appreciated
    Warm regards,
    Srinivas Potluri

    Hai Srinivas
    Got the solution.
    1)For this first check in the project profile of the Hierarchry graphic -
    Time scheduling profile - check the colour patterns which been assigned.
    2)open the project - Cj20N - go to planning board - bar chart - under settings - Planning board assistant - Gantt chart - check the dates display for Project definition , WBS , Acitivity - try to change the colour and check.
    while changing can see - basic date of the acitivity. based on the confirmation can see the bar confirmed activity with respect to basic date. the bar confirmation will show withrespect to duration.
    3) If the bar chart need in daily /hourly - can check in CNE5 . click on the graphics -bar chart - which u will get the bar chart - in this choose the Time Axis - where can select the monthly /weekly/daily /hourly format .
    Award points if clear and got the solution.
    Regards
    PP

Maybe you are looking for

  • How to check whether a user session is null or not

    Hi I am using Jdeveloper 11.1.2.2 I have a use case of running some Junit test case, this is the problem I have : There are some Junit tests which are written for some VO's. While testing insert and update operation in Junit there is two mandatory co

  • How PLM Document save on content server

    Hi All, Please tell me the concept about given below scenario: Normally PLM documents are either saved in the Content Server or in the database. What if we have neither configured a database nor a content server. Where are they being stored then. wha

  • Errors in IDOC

    How can we see the errors displayed in IDOC?

  • Error while installing AD exchange connector

    Hi All, When I m trying to install exchange connector 9.1.1.7.0 in OIM 11.1.1.3.0 I m getting the following error the error occurred while importing connector xml files please help me in this regards DOBJ.XML_IMPORT_ERROR oracle.iam.reconciliation.ex

  • Enter an equation into a textbox and it will automatically calculate an answer

    Hi All, I have created two textboxes. What I would like to do is after entering an equation, e.g. "(9-5)*30 + 1", into the textbox 1, textbox 2 will automatically gives me the answer "121". I have no idea which function can give me an int 121 from a