New Development project  in the middle of  ECC EHP7 upgrade project

Hi All,
We are performing ECC EHP7 upgrade project in our project system landscape and i have already started Dev system upgrade.Suddenly our development team wants to perform new project  which required to install add-on product from third party application. Installing new add-on will require us to regenerate stack.xml file right? if that is the case  do we need to perform re upgrade to Dev right?. As per my knowledge this is not recommended to perform parallel project with upgrade project.
Is there any  best practice or recommended method to perform multiple projects with upgrade project at the same time.
Thanks,
Raghu

Hi Raghu,
First here i would like to suggest you & your development team i.e during an upgrade project dual maintenance is required as per SUM guide,as per SUM guide you need to maintain parallel systems to perform regular activities, for same you could refer SUM guides and follow the standard procedures.
Installing new add-on will require us to regenerate stack.xml file right?
Yes you need to regenerate the stack.xml file .
if that is the case  do we need to perform re upgrade to Dev right?
If you are under upgrade phase no need to perform re upgrade,required add on can be installed after completion of an upgrade as per availability for EHP7.
Try to avoid perform multiple projects with upgrade project .
Regards,
Gaurav

Similar Messages

  • Suddenly in the middle of editing a large project the cropping and other tools stopped working. Did i hit some key or something accidently?

    suddenly in the middle of editing a large project in Aperture the cropping and others tools stopped working. Did I accidently hit something to do that?

    Maybe you hit the "p" key?
    Then "Quick Preview" will be turned on and prevent editing. Hit "p" again or use the "View" ->"Quick Preview" menu entry.

  • Video Playback Problem with Developer Walkthrough of the Continuous Measurement and Logging Sample Project

    Hi!
    I have serious problems playing the video Developer Walkthrough of the Continuous Measurement and Logging Sample Project.
    As the video pauses every few seconds for buffering. I am not able to watch it. Just wanted to check if you can playback the video:
    http://zone.ni.com/wv/app/doc/p/id/wv-3401
    This happens on any browser (chrome, ie, firefox). I am using Win XP and the latest Adobe Flash Player. About 2 weeks ago NI Germany confirmed the problem and promised to contact NI USA as they are responsible for these videos. So far nothing happened. In the meantime I received an e-mail that the problem could not be confirmed although they had confirmed it before...
    Thank you for any feedback.
    Regards,
    Anguel

    Hello ctVolFan,
    As indicated in the "support" section of the SPOT, you should get in touch with self-paced-training(at)ni(dot)com.  I don't believe that team monitors these forums directly.
    Regards,
    Tom L.

  • HT1174 I'm trying to update my iphone 4 with the new iOS6 and in the middle of updating it gave me an error35, how am I able to update my phone in order to get certain apps?

    I'm trying to update my iphone4 with the new iOS6 and in the middle of udating it gave my an error 35, and I would like to figure this out so I can download the apps i need?

    What version do you currently have?
    If you have iOS 5.0 or later, do not update through iTunes if possible; update over Wi-Fi if you have it. Just go to Settings > General > Software Update.

  • I opened a new project with the same name as an existing project and it deleted my existing

    Bad day on my part. I spent all day recording a song with Garageband. As I finished it, I exported it to iTunes (Thank God), closed garage band and listened to the song. Hearing that it had several seconds at the beginning that were silence and not edited out I opened a new Garageband project under the same project name as the previous one and it erased everything the previous project had. Leaving me with no file. No project. No memory of the initial project. Any clues or am I SOL?

    SchilbAaron wrote:
    I opened a new Garageband project under the same project name as the previous one
    the OS should have asked if you wanted to replace the old file with this one. if it did not, perhaps you saved this file in a different folder and the old one still exists? You could try a spotlight search on your entire hard drive to see if both files exist.
    if you did replace the old with the new, the only real hope is that you have a backup (perhaps you use Time Machine?)
    SchilbAaron wrote:
    Hearing that it had several seconds at the beginning that were silence and not edited out[...]  am I SOL?
    if that's the _only_ issue, not completely out of luck. you could drop the audio file back into a new GB project and export an exact length:
    http://www.bulletsandbones.com/GB/GBFAQ.html#exportexactlength
    (Let the page FULLY load. The link to your answer is at the top of your screen)
    Note: if you compressed the export (mp3/acc) you'll be double compressing the file and losing a lot of musical information, but it may be better than losing a One-Time piece of work.
    an alternate method would be to use an Audio Editor to cut out the silence. i'm not sure that this would save any quality, i think you'll still be double compressing the file, but it's something else to try, and listen to, to make a decision on which is better:
    http://www.bulletsandbones.com/GB/GBFAQ.html#audioeditors
    (Let the page FULLY load. The link to your answer is at the top of your screen)

  • How can I create a new skin (other than the default skins) for my Captivate Project?

    Hi everyone,
    I am working on a project where my client wants me to create a player skin which is completely different from the default themes that captivate has already. The design which client has shared with me contains in this way:
    1. TOC - should be truncated and can be expanded by pressing "+" button against the Navigation Text. Its like opening and closing the menu bar using + and - buttons
    2. Playback controls required by him are also not in the default skins.
    I dont know, if there is any way to customize the skins to this level inside captivate.
    Please help me out.
    Thanks & Regards
    Vikas Sharma

    Unlikely, I'm afraid.
    The LMS has no control over the playbar that pauses or plays the Captivate content.
    In a Multi SCORM package, the LMS also may be showing a TOC in the SCORM player with links to launch the lesson modules.  This TOC is in addition to the TOC inside the Captivate project file which gives access to sections of the module by jumping to slides that begin those sections.  But the LMS doesn't usually give you any control over the look and feel or functionality of that TOC either. 
    If your client is adamant that they want complete control over these areas, then your best option may be NOT to build this course with Captivate but build it from the ground up with another tool.  E.g. Flash, or Dreamweaver.  Either way, that will add a lot more time and expense to the project.  But if the client has the budget and is unwilling to budge on their requirement, then that's what I would be telling them to do.

  • Create a New Report Server in the Middle Tier

    Hi
    Everybody,Please help me for creation of a new report server.The Application server version i have is 10.2.0.1.0 .How can i configure a report server in windows and linux?
    Please help me..........
    Regards
    Debashis Pattanayak

    Doc ID: 459177.1

  • New tabs opening in the middle of the tab bar instead of at the end.

    Opening a new tab from a link would open the tab right after / behind the tab you are currently viewing - not at the end. This makes for a very confusing / annoying / clustered browsing as it's impossible to keep track of what you opened (if you are opening more than one link from a certain page).
    == Operating system ==
    WinXP

    To revert this to the previous behaviour of all tabs opening at the end:
    Enter '''about:config''' into the address bar, click through any warning, then into the '''Filter''' box paste:
    '''browser.tabs.insertRelatedAfterCurrent'''
    Double-click the line listing that preference to change the value to '''false'''

  • [ANN] New developer poll on the JDev homepage

    What are your JSP plans?
    Let us know by answering the survey on the JDeveloper home page:
    http://otn.oracle.com/products/jdev
    Previous Survey results:
    JDeveloper DB modeler 16.2%
    Oracle Designer 26.7%
    ERWin 26.3%
    Embarcadero 6.1%
    Other 24.7%

    The comments on the blog center on why Hibernate was not included, which I would have liked to see also.
    What I wonder about is what these numbers actually represent. I think you would get very different results from a poll on TheServerSide or anywhere other than technet. I mean, I would never have heard of BC4J if we hadn't tried JDeveloper as an IDE, which we probably wouldn't have bothered with if we didn't already license a lot of technology from Oracle, making JDeveloper a no-additional-cost solution for us. Similarly for TopLink, if we didn't already have a Smalltalk application that uses TopLink, I think it would have been unlikely that we would have understood how much it can do for us. And even then, we weren't going to use the Java version until Oracle bought it and it suddenly became another no-additional-cost solution. What I'm saying is, if we weren't already an Oracle shop, we'd probably be working with Eclipse and Hibernate. I actually think that JDeveloper and TopLink will provide us with a more robust solution, but I'd feel better about the long run if I thought that this approach was gaining more acceptance in the industry as a whole.
    TopLink may have brought a fair number of not-necessarily-Oracle people with it, but I'd like to see JDeveloper and UIX used by people who don't already think of themselves as an 'Oracle shop'. If we were using BC4J, I'd feel the same way about that. Unfortunately for JDeveloper, unless Oracle can find a way to market it better, I think the wider acceptance of technologies like UIX and BC4J may not come until you can use them as easily with other IDEs as you can with JDeveloper.

  • Hello, Help needed! I want to add an extra 4 bars of a new track in the middle of my project but I need all the remaining tracks to move over 4 bars if you know what I mean. Whats the best way to do this?

    Hello, I need to add 4 extra bars in the middle of one of my projects. Therefore all the tracks need to be split at that point and moved 4 bars further along. Is there an easy way to do this? I cant see a way without painstakingly splitting each track at that point, trying to move each of the tracks individually along by 4 bars and trying to line them all up exactly again. Ive tried this a few times but their not in exact sinc. Any help at all greatly appreciated! Thanks Declan

    Use the arrangement track. If you define arrangement regions, you can move sections of your song around, across all tracks.
    See this help text on how to add arrangement markers and to move arrangement regions:
    http://help.apple.com/garageband/mac/10.0/#gbnd8431c634

  • Project 2013 - How do you sort the list of Enterprise Templates in Project Pro?

    In Project Pro 2013, click File > New > Enterprise I see the list of templates from our project server. We have a global installation with 40-50 templates. These are displayed in a random order and reading through the whole list to find the one I
    want is quite tedious. Is there a way to sort this list alphabetically? Can the list be displayed as a "details" view rather than icons?

    Greg --
    Guillaume is totally correct.  The display order of enterprise templates is by the date they were created.  I have tested this on a Project Server 2013 system that has the latest Cumulative Updates applied.  The problem is that in the
    Microsoft Project 2013 desktop application, Microsoft has ditched the Templates dialog we used to see and replaced it with a page in the Backstage.  I am afraid that in doing so, they have eliminated the sorting capabilities that we found in earlier versions.
    Out of curiosity, I have sent an e-mail to my MPV contacts within the Microsoft Project Server development team at Microsoft, asking if there is any intention of changing this functionality to allow for sorting by template name.  If I get an answer,
    I will post it in this user forum.
    Your question is a good one, and the sorting problem (or lack of sorting) can be a real problem in any organization that has a sizable number of enterprise templates.  Hope this additional bit helps.
    Dale A. Howard [MVP]

  • ABAP developer part in an upgrade project

    Dear experts,
    can anyone explain me the role of an abaper in an upgrade project...
    thanks in advance.

    Upgrade Project:
    The Upgrade Project is to upgrade the SAP implementation version to the latest version of the SAP R/3 released by the SAP.
    Generally the Upgrade Projects are initiated because SAP has suggested to the clients that few of the components delivered by it are no longer supported in the old version. Hence for the Support and Performance reasons it will suggest the clients to upgrade its SAP R/3 version to the latest release.
    In upgrade projects we will have to revive all the BDC programs and implement the BAPI's that are given. Because the BDC is a Screen Dependent Object and the SAP might have made changes in Screen Fields, or may have removed the screen totally. So to achieve the functionality with BDC we have to deliver new BDC program or implement BAPI'S instead of BDC.
    Check below thread
    upgradation to ecc 6
    Role
    abaper
    what kind of documentation an abaper has to do give it with an exaple
    Upgrade
    http://www.thespot4sap.com/upgrade_guide_v2.pdf#search=%22upGRADE%20STEPS%20-%20SAP%22
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/5ac31178-0701-0010-469a-b4d7fa2721ca
    http://service.sap.com/instguides%20service.sap.com/upgrade
    http://service.sap.com/releasenotes
    Check transactions SPAU and SPDD. For more information please have a look at the link.
    http://help.sap.com/saphelp_nw2004s/helpdata/en/60/d6ba7bceda11d1953a0000e82de14a/content.htm
    Reward Points if useful.

  • My new printer just stopped in middle of job and died

    My new printer died in the middle of a job. No lights or message.

    Please read this post then provide some details.  What printer model? What operating system? How is the printer connected - USB, wired LAN, Wireless LAN, bluetooth?
    Bob Headrick,  HP Expert
    I am not an employee of HP, I am a volunteer posting here on my own time.
    If your problem is solved please click the "Accept as Solution" button ------------V
    If my answer was helpful please click the "Thumbs Up" to say "Thank You"--V

  • SAP Query in ECC 6 Upgradation

    Hi All ,
    I am working in an ECC 6 Upgradation project , upgrading from 4.6 C to ECC 6.
    Somebody told me , Query cann't be coppied from 4.6 C to ECC 6.
    Is it true ? If so what is the alternative ?
    Thanks in advance.
    Regards
    Srikanta

    Hi Srikanta,
    U didnt need to re-copy all the queries. When you upgrade from 4.6, the new version of sap does not default to the correct query area. You merely need to point it to the correct one. Just set a parameter against you own user data called AQW and leave the parameter value blank.
    Take a look at OOS note 672784.
    You can transport queries between systems in SQ02 (by using the lorry button) or run report RSAQR3TR.
    You download the infosets, queries etc into a file and load them into whichever system you wish.
    Hope it will be useful.
    Regards,
    Lakshman.

  • SAP Upgrade project

    Hi Experts,
    I need some inputs to do SAP upgrade from 4.& to ECC 6.0.
    Generally the steps involved in the Upgrade project?
    What is the role of ABAPer in Upgrade project?
    What us the role og Functional consultant in project?
    How the configuration kind of stuff take care?
    Can anyone send me the best document to understand the process..?
    Regards,
    Sekhar.J

    Hi,
    Upgrade Overview
    The objective on SAP Technical version upgrade would be to bring in enhanced SAP functionality while retaining the custom development in the original system. The enhanced functionality is not necessarily implemented during the upgrade. The upgraded system is tested for all the functional scenarios existing in the original system and the custom objects are tested for its functioning as in the original system.
    Upgrade project consists of 5 phases:
    1.     Project Preparation
    2.     Blueprinting
    3.     Realization
    4.     Production Preparation
    5.     Go Live & Support
    ABAPer Role
    a) Syntax Correction
    b) Upgrade Correction (Replacement of obsolete statement)
    c) BDC Program correction
    d) BDC to BAPI conversion
    e) Unicode testing using UCCHECK transaction
    Functional consultant role
    Unit Testing
    Test Scripts preparations for Changes
    Regards
    Praneeth

Maybe you are looking for

  • Bridge Rebuilding Cache on External Drive Unnecessarily – How Can I Stop It ?

    I have Bridge CS4 on a MacBook Pro with Snow Leopard 10.6.8. Connected to the laptop is a Firewire hard-drive on which I am storing my images. For some unknown reason, and only from time-to-time, Bridge wants to rebuild the entire cache in any given

  • Problems with JDK and NetBeans

    Hi, I've just started to learn java and I'm having some problems to compile projects. I installed JDK 1.5.0 (with NetBeans 4.0 beta 2), but when I try to compile any program (including the sample ones) I get the following error message: C:\Documents

  • I downloaded FireFox 5 and now were are my favorites List at ?

    I have windows 7 xp pro

  • How does the AWGN block work

    Hello, im trying to add AWGN to a Sine wave, but I dont know how exactly this block works. Im referinf to the Gaussian White Noise Waveform vi. Can somebody explain me,, where or whitch link represents the Eo/No ... for example if i want to add noise

  • How to set the break for repeater

    Hi ,      Here i am trying to stop the repeater based on codition. But the repeater is not breaking. can any one help for break the repeater settings