New label in Purchase requisition (iteml)
Hi experts,
I would like to add to the PR A NEW LABEL IN the item posItion l "DELIVERY SCHEDULE" like PO,,,,
Is it possible?
TKS in advance,
Grettings
Nachos
Hi,
PR do not have Delivery schedule like PO.
You need 2 details or mode in PR.
Regards,
Gaito
Similar Messages
-
Activate new tab in Purchase requisition
Hello Folks,
I am trying add a new tab in purchase requisition on Screen exit MEREQ001. Can anybody tell me where I should go in SPRO and activate my tab?
Thanks in advance and reward point will be given.
ZCHi,
You cannot activate new tab through SPRO.
You have to goto CMOD > give some project name say <CREATE>, Give some description and press SAVE > select Enhancement assignment > give Enhancement "MEREQ001" and press SAVE .
Select Components, double click on Screen exit, it will prompt you to create screen 111. Then add required fields in screen.
Further you will need ABAPer. -
New items to purchase requisitions
Hi all,
I want to add new items to purchase requisitions, which bapi or function can I use?
I tried BAPI_PR_CHANGE and BAPI_REQUISITION_CHANGE, but these functions didn't work for new items..
Thanks..Hi,
You can use FM ME_UPDATE_REQUISITION for updating the purchase requisitions.
You have to pass XPREXT-KZ = 'U' as import paramter along PR number as import paramter.
Rest data can be passed to corresponding tables.
Hope this solves your query.
Regards,
Brajvir -
Associate new type of purchase requisition to WRP1
I have created a type of purchase requisition (ZNBB) and I can't associate it to the Replenishment Planning.
I have tried to associate it in the SRS parameters and also using the MRP Groups, but WRP1 keeps calling the standard type of requisition (NB). This is a problem for us since we have a different logic for our retail operations than for the rest of our operations. Is there anyway of making WRP1 call the new purchase requisition type?
Best Regards,
Patrício SilvaHi
Does anyone has the solution to this issue? I am also having the same issue..
Best Regards
Junwen -
Update Purchase Requisition from Sales Order
Hi,
My requirement is to Update Purchase Requisition from Sales Order based on the Vendor number in
Purchase Requisition .
I have used Userexit :- MV45AFZB
Customerexit :- EXIT_SAPFV45E_002
BADI :- ME_REQ_OI_EXT, ME_REQ_POSTED
for my requirement, but in vain.
Of these Userexit MV45AFZB, Customerexit EXIT_SAPFV45E_002, BADI ME_REQ_OI_EXT are getting triggered in Sales order creation but, Purchase requisition is not yet triggered and we dont have the VENDOR value with which i need to do perform some checks and update the Purchase requisition.
After I SAVE sales order, BADI ME_REQ_POSTED is getting triggered.Here, the purchase requisition is created ( not yet inserted into the database ) .I also have required VENDOR value, but in the given
BADI ME_REQ_POSTED I can make checks according to my requirement but not able to update the new values into purchase requisition.
Literally speaking, Iam struck up..Dont know what to do.....
Please let me know any Userexit/BADI/BTE where I can Update Purchase Requisition from Sales Order based on the Vendor number in
Purchase Requisition .
Thanks,
Shivaa..Hi Max,
It just struck to me...
As suggested by you, I thought of calling BAPI BAPI_REQUISITION_CHANGE from user exit USEREXIT_SAVE_DOCUMENT in MV45AFZZ .
I f I give PReq no. , BAPI BAPI_REQUISITION_CHANGE will take the particular PReq no., from database and then change it according to our requirements...
But, in our scenario I am calling the BAPI BAPI_REQUISITION_CHANGE and passing a PReq no..which doesnt exist in the d/b itself.....
Anyways, let me try......
Meanwhile ,please suggest any other options for resolving the issue in question...... -
Error in new purchase requisitions, for already deliverd materials
Dear all,
I have a problem with newly created purchase requisitions, although material was partially delivered and no delivery is expected anymore.
For example I have ordered 1767kg of oil and a total sum of 1766.2kg was deliverd. This means only a minor amount of material was not deliverd and only 80gramm are missing. The purchase value key allows a 5% over and under delivery.
Usually I would expect, that because of the purchasing value key of 5 % over and under deliverance allowence this situation should not occur anymore. Additionally at the time of goods receipt the key of final delivery was set and the purchase order is updated correctly.
But when I run the MRP again I will have another purchase requisition. The dependend requiement of the material above still existis as production is not finished yet or this is still a planned order.
What keys do I need to set in total for allowing a "partial delivery"?
- Purchaseing value key in the material master
- Delivery completed at the time of goods receipt
Maybe this question is to basic as I cannot find any questions / answers related to this issue here in the forum.
In some points, I found that I need to set up the vendor accordingly to set up partial deliveries. But I cannot find the right setting to allow the vendor to do so. I use MK02 for the change of the vendor settings.
Thank you very much for your support!
With best greetings,
BjoernHello Jürgen,
yes after thinking about this issue again, I think this might not be an appropriate solution. Now I am thinking about other possibilities.
1) Automatically change the value in the production order at the time of saving MIGO - will not create any more missing material messages and no new purchase requisitions .
2) Errror message, that for this positions no more postings are possible as the purchase order still remains "open"
3) I need to find the customizing of the indicator "delivery completed". At the moment I just dont see, the influence of this indicator.
Sorry for my "stupid" questions, but I am quiete new to these MM topics. Up to now I was always doing only PP and QM but our collegue for MM has left the team and there are some open issues which now belong to me. Lucky me.
I have created a new posting at:
With best greetings,
Bjoern -
How to add a new line item to a Purchase Requisition number
Hello All,
Can anyone please provide me with some FM or BAPI to add a new line item to an existing Purchase Requisition number.
Can it be done using BAPI_REQUISITION_CHANGE; if yes, then how do I pass the parameters into the BAPI tables..?
Useful pointers would be appreciated...!!
Thanks & Regards,
Tarun Gambhir@Gautham,
Thanks for the quick reply.
I want to update the table EBAN, so should I use the parameter table XEBAN to put in the new line item and then execute..
Also to fill up this table I need to pass certain value, so can I use BAPI_REQUISITON_GETDETAIL and pass the same details as found from the same BAPI and create a new line item...
Regards,
Tarun Gambhir -
Enable Purchase Requisition and Purchase Order for a New company Code
How to enable Purchase Order and Purchase Requisition for a new company code.
create purchasing organisation,
assign it to a company code or plant.
do you already receive errors? -
ME57 - Convert Purchase Requisitions - New fields to Tree ALV in Overview?
Hello,
From ME57, one can get a list of purchase requisitions, click "Assignments," and then "Process Assignment."
What next appears is a list of requisitions in a Tree ALV grid. The title of the grid is: "Convert Purchase Requisitions."
I would like to add a new field from EBAN to this ALV grid. The field is not currently available in change layout. The structure that I think is displayed is MMPUR_S_DBL_ASSIGNEDREQS.
Is there a BADI or some other way to get additional fields on this Tree report (which, of course, is used to drag requisitions to the right side of the screen in ME21N)????????
Thank you,
-KenHello,
From ME57, one can get a list of purchase requisitions, click "Assignments," and then "Process Assignment."
What next appears is a list of requisitions in a Tree ALV grid. The title of the grid is: "Convert Purchase Requisitions."
I would like to add a new field from EBAN to this ALV grid. The field is not currently available in change layout. The structure that I think is displayed is MMPUR_S_DBL_ASSIGNEDREQS.
Is there a BADI or some other way to get additional fields on this Tree report (which, of course, is used to drag requisitions to the right side of the screen in ME21N)????????
Thank you,
-Ken -
Add new line item to Purchase Requisition
Hello All,
I want to add a new line item to the exixsting Purchase Requisition. The documentation for BAPI 'BAPI_REQUISITION_CHANGE' says that new items cannot be added using this BAPI. Is there any other BAPI or FM that does this? Thanks,
ChandniHi,
Try using ME_UPDATE_REQUISITION.
Thanks,
Naren -
How to create new requisitioner in sap mm for raising purchase requisition?
How to create new requisitioner in sap mm for raising purchase requisition?
Hi Dear,
There is some link will help you to create Purchase Requisition and other MM Documents.
http://www.docstoc.com/docs/11307932/SAP-MM-Manual-Create-Purchase-Requistion
http://www.r3.duke.edu/training/stepbystep/#purch
http://sapdocs.info/sap/materials-management-2/download-sap-purchasing-user-training-ppt-material/
Regards
Aamir -
New processing status in purchase requisition
Hello,
I would like to add new processing status in purchase requisition such as E - Edited when simple changes are done in document.
Is it possible to add it?
If it is yes, please give your inputs.
Regards,
SivakumarHi,
It is not possible via standard customization. You have to implement user exits with help of ABAPer;
MEREQ001 - Customers' Own Data in Purchase Requisition / Check in SMOD -
New Purchase Requisition required once Purchase Order Released
Dear Expert,
Here i am creating Purchase Requisition from the project by assigning
material component in Network Activity. All the Material assigned to a
single network have a single Purchase Requisition with different
different Line Item which is acceptable but once the Purchase Order
created and released and a new material component is assigned to the same
network. Now it will added into the same purchase requisition with
separate line item, which is not acceptable since that purchase
requisition was already closed and Purchase Order was released then
system should generate a new Purchase Requisition against the same
Network,
Pls suggest how it could be configure, is there is any setting in config
to full fill this requirement.Hi,
As such there is no config requirement.
Its purely your process needs to be re think.
You are assigning the material to activity and getting PR,PR,GR and all . Once the material is consumed, thinking that activity is also over. In this case, again you are assigning other material to the same activity and you want to have the different purchase requistion not same PR with line item.
option 1, you can have the different PR nos always whenever you are assigning the materials to same activity. If 1 activity requires, 10 materials, you will have 10 PR's which is practically not correct. chnages you can do it in parameter for network type.
Option 2, New materials which is required can have a new network.
Regards
N.Raju -
MD01 deletes purchase requisition, MD02 creates a new one
Can someone please explain why when doing MD01 (plant level), there are Preq that were deleted.
While in MD02, it creates new Preqs.
Thanks,
JCThanks for your big help.
Anyway, as for my issue, there is only one material (material X) that was not planned in MD01.
These are the results:
Planned orders deleted 3
Purchase requisitions deleted 4
Just want to know what can I do or how can I create a Preq for Material X in MD01?
Kind Regards,
JC -
Release strategy for purchase requisition does not kick in
Hi Gurus!
I've been struggling with this issue for some weeks now.
I have set up the release strategy configuration for purchase requisitions with classifications.
However, if I create a purchase requisition the release functionality is not taken into account by the system.
See below some more information regarding my configuration:
1. I've created a new characteristic "REL_PR_GROUP". Status: released, Multiple values, Number of Chars 3, 7 values (TR1, TR2, TR3....TR7), Table name: CEBAN, Field name: EKGRP, Procedure for value assignment set to not ready for input.
2. I've created a new class: "REL_PR_ANPC". Class type 032, Status: released, Same classification: do not check, Char: "REL_PR_GROUP"
3. I have one release group "T1", Rel. object 1, OverReqRel is marked, Class: "REL_PR_ANPC"
4. I have 5 release codes. Grp: T1, Code: 01....05
5. I have 2 release indicators:
"R = Released", Rel. for ordering is marked, Changeabil: 4, Value chgs. 100,0
"X = Blocked", Changeabil: 4, Value chgs. 100,0
6. I have 1 release strategy:
"T1 with Grp T1"
- one release group, 01 Manager
- release prerequisites not applicable because of only one release group
- release status, nothing marked = blocked, 01 marked = released
- classification, purchasing group is TR1 or TR2 or TR3 or TR4 or TR5 or TR6 or TR7
I intentionally kept the configuration as simple as possible so I can try to get it working first.
Now if I create a purchase requisition for an item with release group T1, I would expect the release strategy to be activated. However, this is not the case. I don't see the "release status" tab in the PR, and if I try to relase via ME54 the system says the PR is not relevant for release.
Could you please assist in getting this working?Hi,
Have you checked in CL30/CL30N if your release strategy is derived successfully?
See section 3 of Note 365604. A small section of it:
You can use transaction CL30 search for an object using the data
of the purchase requisition/purchase order. Here, it is important
that the object search determines exactly one strategy. If this
is not the case, this indicates that there are overlapping
strategies in the system or that the release strategies in
Customizing do not correspond with those from transaction CL24.
See the previous point. If the object search returns more than
one result, the system subsequently determines an incorrect
release strategy or no release strategy at all.
If it is derived successfully, next, check the user exit EXIT_SAPLEBND_001 as per Note 371667:
The following assignment statement has to exist within activated SAP
enhancements M06B0002 (include zxm06u13) and M06B0005 (include zxm06u31)
for purchase requisitions:
E_CEBAN = I_CEBAN.
Regards,
Purnima.
Maybe you are looking for
-
Issue with instance config.ini
Hello All, I have added one line code in my instance config.ini file <WebConfig> <ServerInstance> <ForceRefresh>TRUE</ForceRefresh> </ServerInstance> </WebConfig> as per my knowledge it will by presentation server query and cache not OBI server cache
-
I can't copy files to External Hard Drive : Please help..
Evening, I've just bought a Macbook and am just getting to grips with it. This is my first question on this forum...the first of many no doubt. Problem I've got is that I can copy file's from an external hard drive on to the MAC but I can't go back t
-
I bought last week (Adobe Acrobat Professional XI) through the website and I received an e-mail to confirm the purchase, but so far I have not got any mail to be able to download the software My order number: MENA 9723990859
-
Asset history sheet version is not complete
Hi Guru, I have implemented a new Asset history sheet version. When I run the Completion check I have the message "Asset history sheet version is not complete". This message I see it when I run the transaction code S_ALR_87011990 - Asset History Shee
-
My editor is making separate incopy files for each chapter. When I placed them into my indesign layout, they have the same name in the assignment window, even though there have different distinct names, chapter 1.icml, chapter2.icml..... Why do they