I have a problem in Process Order Confirmation.
I have a order with Co-products. When I do confirmation, 101 Mvt type is not happeneing for all the co-products along with the main product.
The configs looks fine
1. Control key has "Automatic GR"
2. Confirmation parameters have "GR Co-products"
What else could be the problem?
Hi Jack,
I'm not sure how it works with process orders but in case of production orders is it not possible to do auto GR for co-products - according to my best knowledge.
Please check:
http://help.sap.com/saphelp_erp2004/helpdata/en/b1/c04d01439a11d189410000e829fbbd/content.htm
You can use MB31 + PrdOrd reference to book the co-products by mvt 101.
(You can also search in this forum to find threads in connection with this.)
BR
Csaba
Similar Messages
-
Product Costing - Process Order Confirmation
Dear Experts,
We are facing a situation with our Product Costing Scenario :
Under SFG Process Order Confirmation, there are Ten Phases to finally confirm the order. First Phase is for Raw Material Issuance. From Second Phase to Ninth Phase are relevant to Activity Types. Tenth Phase which is final phase, in this point Goods Receipt posting is generated.
At first phase, system posts Raw Materials Goods Issue (Movt Type 261) to Process Order:
Entry : RM (Cr), Consumption (Dr).
Client needs the system to post one more entry at the same time by : WIP (Dr), Inv Change (Cr).
Reason:
According to client, they have made consumption entry in finance but what if all raw materials are not consumed as yet and factory comes under fire, then how can they claim insurance on those Raw Materials which are not consumed and are still in the IN PROCESSING Stage?
My Answer was:
- They can find all material costs in Process Order as Debit Item.
- They can also calculate WIP but cannot post WIP in Finance unless the order is settled.
Ultimately, as per my knowledge client cannot check the unprocessed Raw Materials report in FI but they can check in CO. And this is the point of reservation from client.
They need an entry in Finance for WIP to claim insurance in case of fire and therefore they need a posting of WIP entry immediately after Goods Issue of Raw Materials to Order.
Can anyone please guide me further regarding this scenario and if any one can suggest any work around then it would be highly appreciated!
Regards,
Zain BashirHi Zain
This is a very unusual question
Buddy, there is something in accounting called as "Going Concern Concept" which we all were taught in our accounting days.. That means when you do business, do it with a mindset that you are goinig to do it for long / for ever.. Accidents dont happen every day and you cant build a system around such things
Assume there is a fire (God forbid).. After the accident, you wont even know how much was lying there unconsumed which got gutted in the fire..
And insurances not just covers the stock lying consumed, but also stock manufactured and stock in the process of manufacturing (WIP)
And most importantly, dont expect SAP to throw up a figure at the click of a button.. Does your client really think that they will simply submit the report generated from SAP as-is to Insurance people?? SAP is just a technology enablement, which requires human intervention at various places
My opinion - Dont build system for such requirements
Br. Ajay M -
BAPI For Process Order Confirmation
Hi,
For Process Order Confirmation we are using the following tcode. COR6N. in the t-code we are include a new field (Shift Field) with help of CONFPP07. and we made the field as mandatory also. in cor6n it is working fine.
now we are using the bapi for same Process Order Confirmation. here the new field is not available. we want to include the new ( Shift ) Field also. we are using the following
BAPI Fm: BAPI_PROCORDCONF_CREATE_TT .
Regards
SathisBAPI_PRODORDCONF_CREATE_TT to confirm a production Order
Erwan -
Need a BAPI/FM for process Order Confirmation
Hi guys,
I need a bapi or Fm for process Order confirmation.
thnx in advanceChecck
BAPI_PRODORDCONF_CREATE_ACT
BAPI_PRODORDCONF_CREATE_HDR
BAPI_PRODORDCONF_CREATE_TE
BAPI_PRODORDCONF_CREATE_TT
Better read the documentation of each BAPi using the tcode BAPI and proceed.
I feel BAPI_PRODORDCONF_CREATE_HDR would do your purpose.
Documentaion:
<b>
You can use this method to enter order confirmations for production orders.
You can also transfer good movements, that are posted together with a confirmation. If no goods movements have been entered for a confirmation, they are determined using the standard logic for backflushing and automatic goods receipt for confirmations. </b> -
Batch determination for raw materials in process order
I have defined a sort rule, batch search strategy and assiigned this strategy to process order type.classification for batch is also defined with charecterstic mentioned in sort rule.But when i am doing BD for raw materials in Process order , it is barnching into some other screen saying, no selection criteria and no strategy info defined. what are the necessary settings to make BD possible for all the materials having batch management.
Hi
Config Setting In Batch Management
This will help you for config setting:
Logistics general - Batch Management
1.1. Specify Batch Level
Menu Path Enterprise Structure> Logistics General> Batch Management --> Specify batch level and activate batch status management Transaction OMCT
1.2. Batch Number - Activate Internal Number Assignment
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Number Assignment --> Activate internal batch number assignment Transaction OMCZ
1.3. Batch Creation - for Goods Movements
Menu Path Enterprise Structure> Logistics General> Batch Management --> Creation of new batches --> Define batch creation for goods movements Transaction
1.4. Characteristic Value Assignment -- Update Standard Characteristics
Menu Path Enterprise Structure> Logistics General> Batch Management --> Characteristic Value Assignment --> Update Standard Characteristics Transaction
1.5. Activate Batch Classification for Goods Movements in Inventory Management
Menu Path Enterprise Structure> Logistics General> Batch Management --> Characteristic Value Assignment --> Valuation for goods movements --> Activate Batch Classification for goods movements in Inventory Management Transaction OMCV
1.6. Batch Determination u2013 Condition Table(Cross Client)
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Condition Tables --> Define production order condition tables Transaction OPLB
1.7. Batch Determination u2013 Condition Table(Cross Client)
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Condition Tables --> Define SD condition Tables Transaction V/C7
1.8. Batch Determination u2013 Access Sequence(Cross Client)
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Access Sequences --> Define Production Order Access Sequences Transaction OPLF
1.9. Batch Determination u2013 Access Sequence(Cross Client)
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Access Sequences --> Define SD Access Sequences Transaction V/C2
1.10. Batch Determination u2013 Strategy Types
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define Production Order Strategy Types Transaction OPLE
1.11. Batch Determination u2013 Strategy Types
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define SD Strategy Types Transaction V/C1
1.12. Batch Determination u2013 Batch Search Procedure
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define IM Search Procedure Transaction OMCY
1.13. Batch Determination u2013 Batch Search Procedure
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define Production order Search Procedure Transaction OPLG
1.14. Batch Determination u2013 Batch Search Procedure
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define SD Search Procedure Transaction V/C3
1.15. Batch Determination u2013 Batch Search Procedure Allocation
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Allocate IM search procedure/activate check Transaction OMCG
1.16. Batch Determination u2013 Batch Search Procedure Allocation
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Assign Search procedure to production order Transaction OPL8
1.17. Batch Determination u2013 Batch Search Procedure Allocation(SD)
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Allocate SD Search procedure Transaction V/C5
1.18. Batch Determination u2013 Activate Automatic Batch Determination(SD)
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Activate Automatic Batch Determination in SD -->For delivery item categories Transaction V/CL
1.19. Batch Determination u2013 Batch Selection Class
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define Selection Classes Transaction CL01
1.20. Batch Determination u2013 Sort Rule
Menu Path Enterprise Structure> Logistics General> Batch Management --> Batch Determination & Batch Check --> Define Sort Rules Transaction CU70
1.21. Batch Determination u2013 Make Settings for Batch Where-used list
Menu Path Enterprise Structure> Logistics General> Batch Management --> Make Settings for Batch Where-used list Transaction OMBB
regards
Faisal -
Cost Analysis Report - For a range of process orders
Dear all,
Is there a standard report available to get the cost analysis for a range of process order? COR3 --> Go to --> Cost --> Analysis. Here I can see the cost analysis for one report. But I wanted to get the cost analysis report for a range of process orders. Please help.
Thanks
NagarajanDear
You can use cost analysis report like
1.S_ALR_87099932 - Variances Between Costing Runs
2.S_ALR_87099931 - Price vs Cost Estimate
3.S_ALR_87099932 - Variances Between Costing Runs
5.KOC4
Regards
JH -
In process order confirmation screen there should be 2 rows for down time.
hi,
We are using cor6n for process order confirmation, where we can put down time with confirmation text at once,
if there is two different down time, then user has to again run cor6n with 0 yield for put another down time, which gets more time.
for this reason i have customised single screen entry profile by mentioning two down time & confirmation rows in screen.
when i going for confirmation i put two different down time after goods movemnt order get confirmed & settled.
but when i see report in COOISPI there is only one down time against order.
system only considers last down time.
hows the system consider down time?
thanks in advance.
regards
sanjay.Hi,
The report COOISPI considers only one line of the down time, it is not considering the 2nd row of the down time. You need to change the COOISPI program to read the 2 lines of the down time. You need to change the standard program to read the 2 down time lines.
Thanks & Regards,
V. Suresh -
Problem during Process Order Confirmation - COR6N
Dear All,
We are into process industries
Till now we are creating different BOM for each section and different process orders for each BOM.
For example Pulverize, Acid MIXING, Continuous Rotery, Blending and Packng.
Now we have created new BOM for FG - showing all input/output of RM, SFGs. In Recipe, define operation for each section. and assign operation to material. I have attached screenshot of Recipe Operation.
During process order confirmation, system shows movement type of all material perfectly during each phase. But during confirmation of last phase system does not show 101 movemet of FGs.
I have checked in Recipe, control key is ok i.e. Automatic GR, in OPK4 setup is also correct.
We have created new BOM and Recipe. There is no change in other configuration parameter.
Thanks and Regards,
NiravHi Nirav
The automatic goods receipt is defined by the operation/phase control key.
Control key PI03 has the automatic goods receipt setting by defaul.
Analyzing the screenshot I could observe that this control key is assigned to all the opration/phases, however, it should only be assigned to the last operation/phase, where the goods receipt will actually take place.
For all the previous operations/phases you should use a different control key, without automatic goods receipt, such as PI01.
BR
Caetano -
Update Process Order Confirmations Back to SAP ECC
Hi,
Is there a document or step by step guide which explains how i can update SAP EARP with process order confirmations from my shopfloor? Below is the scenario i am looking for help in
1. There is a SQL server table where the SHOP floor update the quantity manufactured against a Process order.
2. I need to pick up that data from the SQL server table and update the ERP against that Process order.
Can any one explain how this can be achieved.
I checked the sample's and the templates in SDN but none of them actually show how to update any ERP?
Please advice!!.
Regards
SurajCheck this one
https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/60ac6bb8-a684-2b10-208d-b90883004a5e
https://www.sdn.sap.com/irj/scn/downloads?rid=/library/uuid/204a13d0-399d-2b10-ec84-9c254cd7efd4
You use this component to enable the shop floor operators to record their production order and process order confirmations using a touch screen user interface. In SAP ERP Central Component (SAP ECC) operators must complete many steps to confirm orders. Instead, you can use this interface, on a touch screen to enter the production performance easily and effectively. You can also use this component to obtain operators' work lists and information on their current activities.
Regards
Ram Upadhyay -
Setting of tolerance limit while Process Order confirmation
Dear Experts,
I want to set tolerance limit onto the components of Process Order while doing the Process Order confirmation, Please teach me what all the steps do i need to follow for doing that.
Thanks!
Regards
Sumit KalyanTolarance limit what you are speaking about is for the components. In wS view what you are setting up is the for the product, not for component.
As I am aware we cannot set any tolarance limit for the component as such.
I am not sure what actually you want.
example - component A, as per the planned qty in production order is lets ussay 10, now when doing confirmation user can enter 10+ or - 1, if he neters moer than 11 or less than 9 system should not allow? is that you are trying to implinment?
If so that mayn not be possible unless otherwise you impliment some user exit.
In OPK4 what settings are there is for product and not for raw material/component -
Process order confirmation without 101mvt type
our client is a process industry.client need during process order confirmation Background 101 not happen.
Step : 1 Process order create
Step : 2 Goods issue The material -261
Step: 3 Process order confirmation (No 101)
Step: 4 Goods Receive (MIGO) 101 happen
Following Steps Process only,
cork-only activity confirmation only,after Activity confirm GR will Happen , how to configure in the system,any user exit or sap note there in the sense tell me?
Thanks For AdvanceHi Thiyaharaajan,
For Goods issue i believe you are using MB1A/MIGO. You also use backflush to automatically issue the material during confirmation.. For this maintain Backflush - 1 in material master MRP 2 view.
Also during confirmation for doing Auto GR (101 movement type) you need to assign the control key ticked with Auto Goods Receipt for Last operation/phase of Master Recipe.
Thanks & Regards,
Ramagiri -
Problem with creating Process order confirmation using BAPI
Hello,
While creating Process Order confirmation using BAPI_PROCORDCONF_CREATE_TT, material document is getting created. But a line item is inserted in the table AFRU without material document number. When it is created manually using the transaction COR6, the table is getting updated with material doc in the line item. Can anyone let me know what other attributes to be passed in order the update the same?
Thanks in Advance.
Regards, Senthil G.Hello , I am working with the same Bapi, can you please send me the code to fill the parameters, if I find the same error like you, I will send you the solution if I correct that.
Thanks for your help.
[email protected]
Guatemala, Cempro ADATSA -
Process order confirmation error in COR6
Hi Gurus,
I am working as sap manual tester and facing below issue in Process order confirmation in t-code COR6.
Batch 456 for component 350515 does not satisfy BOM requirements
Message no. Z_MFG017
Need ur help.
Regards,
Imran
Edited by: imran.shek38 on Jan 25, 2011 7:16 AMHi,
Please check whether the Batch-Management checkbox is maintained for the component in the Material Master (MM02).
Also, check the Transaction MSC2N for this component and activate the checkbox for batch-managed item in the BOM.
Hope it helps.
Regards,
Kaushik -
Process order confirmation reversal
HI friends,
I am cancelling a process order confirmation using T-code CORS. The confirmation cancellation is happening, but the goods movements are not reversed. Help in resolving will be much appreciated.
Thanks in advance.
Warm regards
VivekHi All,
Sorry for the delay in response and thanks for your suggestions.
The backflushing is activated. I checked in COGI transaction for the concerned order. I got several entries with different error text. The error text is as follows
"You have no authorization for this transaction with movement type 102"
"You have no authorization for this transaction in plant XXXX"
"Deficit of SL Unrestricted-use 6,957 TO : 1030604 XXXX PL01"
Please let me know how to resolve these errors.
Warm Regards
Vivek -
Process Order Confirmation and Pallet
Hi,
Would appreciate if you can pitch in to get information on below requirement.
Say for eg., for the 1000 CA of header quantity in a BOM, one (1) Pallet (PAL) is required and assume the pallet's are back flushed.
- if you confirm 1000 CA, then SAP post 1 Pallet
- if you confirm partial pallet, like 800 CA - then SAP posts 1 Pallet
- but, if you confirm partial pallet, like 400 CA - then SAP posts 0 Pallet,
I believe that's the nature of SAP design in rounding up / down. However in this unique circumstance of a Pallet, everyone would always like to Round up rather than round down.. so, in the example above confirm 400 CA should also post 1 Pallet.
I couldn't find a solution in SAP with it, and I guess a user-exit might help to round up, but not sure which user-exit at process order confirmation will help.
Any pointers would be a great helpu2026
Thanks in advance,
NitinIs HU enabled for your location? if that case, you could post by pallet.
Maybe you are looking for
-
I cant install Icloud on Wiondows 7 64 bit
There is a problem with this windows installer package. A program run as part of the setup did not finish as expected. Contact your support or package vendor.
-
Changing File-Open Default Column Widths
In Word and other applications I find I want the column widths to be wider (and stay wider) than the default. Someone on Mactopia said he was able to do the following: 1) Open Word 2) Use File>Open 3) Adjust the window to your taste 4) Select and Ope
-
Recovering from Old Shadow Copy Cache System Files
Hello, We have a client who had data corruption on a large scale (virus) and did not have an active backup. Shadow Copy was enabled, but failed when attempting to restore using built-in Shadow Copy recovery. Folder and File level recovery failed. We
-
How to use RDBMS Realm in Weblogic Commerce Server?
Hi All, Same as the subject. Thx Ray
-
Commenting functionality not available when I open a pdf in air application
commenting functionality not available when I open a pdf in air application. Adobe documentation says that is expected with adobe air 1.0 but I still have the same problem even if I use the latest air runtime