No actual cost in production order

Hello,
We just create a new plant in our SAP system, and create a new production in this plant, but there are no actual cost occured after confirmation although there are plan cost in cost analysi, I check the following areas:
1, cost center, we maintained the price for activity types in KP26
2, costing variant and valuation variant
3, confirmation, there are posted quantity of activity types
4, routing in the production order
But I can't find the reason.
When I use COFC, found the error that said no actitivy type price maintained, but we don't use this activity type for this production order's work center(cost tab).
When I go to cost - itemization, the activity types are what we don't maintained in workcenter(cost tab)
Any body can help me?
Thanks,
Richard

Hi richard,
Pls check that in kp26 transaction, which version do you select in the entry screen. Also the period for which the prices are maintained.
Moreover, if your work centers use that activity type, only then it will show up in your cost itemization.
Pls confirm the above and revert back.
Awaiting for your confirmation,
Regards,
Ankita

Similar Messages

  • Function module for calculating planned and actual cost of production order

    Hi ,
    Do we have any standard function module for calculating planned and actual cost for production order?
    i need to implement this in a Z-report.
    Thanks
    Srini

    Hi,
    try below function module
    CRMCO_GET_PLAN_ACTUAL_COSTS
    CO_IH_GET_PLANNED_COSTS_TOTAL
    Regards,
    Sankaran

  • Actual cost of Production Order settled to Fixed Assets

    Dear all,
    My client is doing in-house production of moulds (internal order suggestion is not accepted by the client) for which
    they have the following
    1. BOM
    2. Machine hour
    3. labour
    4. overhead etc
    5.plan value
    6. actual value
    Can i settle the actual cost of production order to Fixed Asset ?
    If yes
    what are process kindly give me if any process other then the below
    1.production order created
    2. settlement profile - FA is settlement optional
    3. allocation structure
    4. Asset created
    5 define asset in settlement rule
    Kindly give me your valuable input
    regards
    elango

    Hi,
    Although i am not CO expert , please check with your FICO consultant who are expert before make the final call.
    During settlement to a G/L account or a fixed asset, the system ignores additional account assignments that were manually specified in the distribution rule.
    Based on what i know .
    you can stipulate that settlement may be made to cost centers and orders, but not to fixed assets.
    The Settlement profile is something that you need to create a settlement rule to settle the actual costs of a sender object.
    About the Settlement rule is something that  contains the distribution rules for the sender. It will define how the way to settle the cost.
    Allocation Structure
    In the settlement structure you combine the primary and secondary cost elements into groups, in which debits are then posted to the sender objects. For each group, you specify whether (for settlement to a given receiver type) settlement is performed
    by cost element or using a settlement cost element.
    For example, you might use settlement cost elements:
      To document the purpose of an order (such as, repairs or maintenance)
      To reduce data volumes (you can combine a number of debit cost elements
    under one settlement cost element).
    TQ

  • Actual cost of production order in inventory valuation

    Hi,
    Kindly tell me in our client requirement to "capture actual cost of drum manufactured. This cost will go to finished mixer. So actual goods receipt of drum should be with actual production order cost . Also actual mixer cost should be taken from actual production order cost. How to map this s cenarionin in SAP" ?
    Best Regards,
    Anindita

    Hi Shyam,
    In SAP product costing we use generally standard cost estimation. Raw material ara taken as moving averagae price as v and finished products are taken as standard price i.e, S. Before cost estimation we update plan price in material master costing view 2 for accurate cost estimation. In case of standard cost estimation price variance is occured which is post to separate gl account. Our client wants actual cost rather than standard cost. Without implementing material ledger is it possible to do actual costing in SAP. Please let me know the process of actual costing...
    Regards,
    Anindita

  • Actual Costs for Production Order

    Hi All
      I have a scenerio where they dont want any product costing methods say WIP,Variance calculation & Settlement.
      When the Goods receipt is done for production order the actual costs and the Activity costs to be valuated.
    Regards
    Jayshankar.A

    Hi,
    In our case the Standard price is updated in the material master. For this, you need to create a costing estimate using T-Code CK11N and update & release in CK24.
    When CK11N is executed the standard price is calculated for the material by taking Moving Avg Price of RM (Price indicator V) and the activity costs are calculated as per data given in KP26. These cost components are added and a final cost estimate is prepared, which is updated using T Code CK24.
    the pre-requisites are:
    1. BOM should be maintained.
    2. Routing should be made.
    For executing the same procedure for all the materials, you can use T Code CK40N.
    Hope this is what you were looking for.
    Revert for further details.
    Regards,
    Rohit.

  • Actual Costing in Production Order

    Dear All,
    We are in Production Client.I have created cost estimate and moved to material master.
    PP has created a production Order and confirmed the activities.
    When I view the costs from CO03,i can see the target costs perfectly,but actual costs are not apprearing in the order.
    We have 6 activity types and out of 6 ,we have costs for 5 activities and for the remaining 1 activity ,plan qty is maintained ,but there is no plan cost.Is because of this ,actaul costs are not coming in to order? Or any thing is missed out ?  
    Please share any idea on this issue as we are in production.
    Regards
    Su

    Dear Mr Ajay,
    Sorry for the information given in the previous one as I have given wrong Order No.while checking.
    I have checked once again with the correct order.When I checked COFC ,System has given the error messages for the Setup activity type for which price is not available in the system as no costs are planned for the activity type as we don't  have setup hours for this month,but qty is planned and PP has confirmed the set up qty.
    Is because of this issue ,actual costs did not appear in the order?
    To my knowledge ,as I said we have 6 activity types,out of which there is no cost for setup,hence system is throwing a error for no price for that activity.
    But the system can capture the actaul costs for the remaing 5 activities for which prices are available.
    Regards
    Su

  • Actual cost in production order

    Dear Guru's,
    Please note the following scenario: For a production order of 100 pcs if I wastes/scraps 15 pcs in opeartion then how to capture only the cost of 85 pcs in production order? Please suggest the settings.
    Regards,
    SAP CONS

    Y U want cost for Only 85. It should be for 100
    For Ex
    f0r opern 10 
    Lets take Cost incurred for operation 10 for 100 qtys is 1000 rs
    In Operation 20
    If the cost incurred for 100 is 500, Consider 15 qty as waste
    In operation 30 cost incurred for 30 for qty 85 is 400
    Then the  actual cost incurred for the prdn  is operation 10 + Operation 20 + operation 30
    It should not be for qty 85.
    Edited by: Sundaresan . E. V on Jun 17, 2010 5:57 PM

  • How to see cost componentwise production order actual cost-not planned cost

    Hi,
    Can anybody tell me how to see cost componentwise production order actual cost ?
    Thanks,
    Bijay

    Hi,
    CO03->Goto-> costs-> Anlysis
    or use the std. report KKBC_ORD
    std. reoprt MCRI
    KVBI - Actual Costs
    Regards,
    R.Brahmankar

  • Sales order costing - tracking of actual costs at sales order item level

    Hi
    We are going with sales order costing for services
    Service material is non-valuated hence the scenario is non-valuated sales order stock
    PP module is not implemented.
    I am having following questions
    1. How to track the actual costs at sales order item level? Is Internal order/CO production order is required to be created for the same?
    2. Can I do activity confirmations directly from cost center to sales order item.
    3. Can Raw material is issued directly against sales order item.
    4. Is Sales order is a real or statistical account assignment object?

    dear friend,
    please look here:
    http://help.sap.com/saphelp_47x200/helpdata/EN/42/d7248ab27111d19e9a080009b0db33/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/EN/90/ba6cfb446711d189420000e829fbbd/frameset.htm
    reagrds,

  • Splitting the cost of Production Order

    Hello Sapians,
    We have a situation where a purchase order has all of its costs going to one production order but the services provided
    on the purchase order were actual for three production orders. What is the process for adjusting this amount for the
    production order costing?
    For example, PO number is 10001 and this is currently all being charged to production order 60003. I would like
    15000 USD be moved to both production orders 60001 and 60002.
    Do we have any process of splitting the amount to two different Production Orders in SAP?
    Thank you,
    -Harter.

    Hi Ajay,
    I checked the Order and there are some actions after the Production Order is settled.
    For example: The Order got settled twice in 12/10/2010 and 01/31/2011. And the Variance was there when settling the Order second time and it was also settled on 01/31/2011.
    There are some operations that are on the Production Order before and after the second settlement dates. Even after 01/31/2011 month's settlement I can see some charges on the Production Order from the operations (Subcontracting, Overhead PRD, Personnel Hr)
    My questions and doubts are
    1. Do I need to reverse both the months settlements?
    2. What are the impacts of the reversing the settlements on the other operations that were executed before and after the Order is settled? (Operations are Subcontracting, Overhead PRD, Personnel Hr).
    Thank you,
    -Harter.

  • Actual cost of maintenance order

    Hi SAP Experts
    In Plan/Actual Comparison of maintenance order; i'm not getting actual cost of the order while i'm getting planned cost.
    If anybody knows, plz help on this ?
    Regards
    Pooja

    Hi Pooja,
    I think, the first thing in such case is to verify, if there are actual costs of the PM order ro not.
    To do this, you can run the transaction rkacshow, input the the order number, and check the COSPA & and COSSA,  if there are records with value type 4 (field WRTTP).
    kind regards,
    Zhenbo

  • Actual cost of product in COPA

    Dear all,
    I am relatively new to COPA functionality.
    The requirement is that actual cost of product should be reflected in COPA and not the planned.
    Kindly give me the background also, as in the integration of COPC and COPA.
    Thanks in advance

    Hi,
    Sudhakar is completely right in his comments. But, I would not just accept that actual costing is not active, so you have to find a solution without it. Your requirement is a good reason to activate actal costing, and calls for it.
    The way SAP foresees to bring actual costs into CO-PA would be:
    Activate material ledger / actual costing
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/a5/320e28d56c11d295c200a0c930328a/frameset.htm]
    Calculate periodical actual prodcut costs at period end
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/ec/f835d7f08311d185810000e8a4bacc/frameset.htm]
    Revalue CO-PA at actual costs with KE27
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/f5/0f0739edfcb03ae10000000a11402f/frameset.htm]
    [http://help.sap.com/saphelp_erp60_sp/helpdata/en/7a/4c39be4a0111d1894c0000e829fbbd/frameset.htm]
    That brings you a completely integrated and accurate solution for actual product costs in CO-PA
    best regards,
                  Udo

  • Table of Actual cost of production

    Hi Experts,
    I m developing one Z report for our client which shud contain Standard cost & Actual cost of production of the sold material for that particular month.
    I am following KKBC_PKO tcode for the same.
    Standard cost & Actual cost has a part of secondary cost element.
    Can I know which table will have Actual cost details to present in above mentioned report??
    Thanks in Advance.
    Madhu.

    Dear Madhu,
    Table COEP will help you to check the actual cost.
    Check and revert back.
    Regards
    Mangalraj.S

  • To see the cost of production order  after settlement to header material

    hello guys,
       In make to stock,we settle the total cost of prodution order on header material,right(if we keep as the default rule( distribution rule in order type)?
         If i want to see that cost of production order which we settled against the header material,where should i check it?should i check in material account or somewhere else?
             Thanking you guys in advance.

    Dear,
    There is a little missunderstanding in your thought.
    If the material of price control S, When you do the GR, the STD cost of material is deducted from production order cost, then when you settle the production order, the variance is settled to variance account/PD account. hence the production order cost balance is zero.
    Example- Production order cost is 60000
    After GR the production order cost balance is 60000-50000 = 10000.
    After settlement production order cost balance is zero.
    Now your question is where can i see the production order cost?
    You can see the production order cost in the production order itself.
    In the production order...cost disply option just filter the origin with test settlement and GR.
    Then total up the cost, then you can see the cost as 60000.
    please come back if you need more help.

  • BAPI call to actual cost of work order

    Is there a BAPI call to actual cost of work order operations in PM?
    I am looking for to read these actual cost in a PM order and populate the data to the none-SAP application.
    Any helps appreciate it.
    Tim

    I think I have just found it:
    IBAPI_ALM_ORDERCOSTS_READ
    But, thanks anyway for your quick reply and helpful tips.
    points rewarded.

Maybe you are looking for

  • Help Creating Booklet PDF in InDesign CS4 on Mac OS X

    I need to print a 64-page document as a "booklet," and would like to create a pdf document so I can print it off of another computer in my office.  I have printed the booklet successfully from my computer, so I know that my settings for the booklet a

  • How do I get a PDF to attach to an email without expanding?

    When I attach a PDF to an email on my Mac, it expands within the body of the email while I want to attach the PDF as a file.  How do I fix?

  • Smartforms / Font and Lanscape printing issue

    Hello,         I have developed a smartforms which is in landscape format. When I look at the output which is a pdf the smartform appears to ignore all of the smartstyles that are associated with it so all of the details are printed exactly the same

  • Regular reboot following Kernel Panic

    We have a Dual 1Ghz G4 xServe running 10.4.10 (It also has some external Firewire devices) that reboots every day or so following a Kernel Panic. Can anyone decipher the log file below? Mon Oct 8 17:18:53 2007 panic(cpu 0 caller 0x0003FFE8): zalloc:

  • Everytime I close Itunes it loads back up

    I never had this issue until 6 months ago, I have been looking on the internet for a solution and I cannot seem to find one. ITunes works perfectly but when I close it just reopens and I have to go to task manager and end process it. These are the fe