No Bom Explosion for Fert material

I try to create a BOM where a A1 material(FERT) is link to 3 raw material, A, B and C. Enter the qty in MD61 independent requirement, after that i tried to run MRP and found out that there is no requirement/PR created for the 3 raw materials, only the A1 has the indep requirement. seems there is not BOM explosion.
After that i try to create B1 material(SEMI) is link to 3 raw materials as well. But the 3 raws material able to show the requirement/PR after the MPR run.
Am i miss out any step in the config for the material type? or may be other steps?

Dear ,
MRP will explode BOM  for FERT or HALB which has valid BOM , based on the following set up :
1.In MRP4 view of FERT/HALB , keep BOM Selection method -Blank or 1 .If you have Production Version with valid Lot size , Valididt dates (To/From ) , then keep the BOM selection method as 2/3.
In case of Blank , MRP will  selt the BOM as per the Qty or BOM lot size ( Valid Lot Size-TO/From -CS02-BOM Header )
In case of 2/3 -System will  Check the Production Version Validdity or Lot size , select the PV and explode .
2.In OPPQ-MRP Plant parametrs -Keep BOM Explosion indicator as Blank -BOM explosion method /order start date .
3.Keep MRP Dep.Req filed in MRP4 vewi of FERT /HALB as Blank ( meand you want to plan the dependent ofr FERT/HALB-BOM Compoenet -a,b,c  etc )
4.All the material (FERT/RAW/HALB) should have porper MRP1-MRP4 view parameters  like MRP Type -PD , Procurement Type E-In house /F-External procured item .
5.All the material should be Block for Procurement in Basic Data1 -X plant status as 01
6.All of them should have Planning File Entry in MDRE/MD20/MDAB
7.Run MRP in MD02-2,1,3,3,2,NETCH
Hope this is clear .Check Point 1 to Point 4 frist and try
Regards
JH

Similar Messages

  • BOM explosion for variant material

    Hi Gurus!
    I created a material variant, when type match is done, the configurable material is changed for the variant properly, in this case, BOM explosion is done in the sales order and components are shown properly (I did this thought customizing).
    When I try to sale the variant material directly (without configurable material and type match), the system do not show the BOM explosion.
    I need the BOM explosion in the sales order for invoicing proposes.
    Can anyone help me?.
    Thanks!!.
    J. Carlos.

    Hi,
    To do a requirements explosion for a configured material, you must maintain the data in the
    material master record and link a BOM to the configured material.
    If the material of the material variant is the same as the configurable material, the link
    is already there.
    You can either create a BOM especially for the configured material (perhaps using the copy from
    function) or allocate the configured material to the BOM for the configurable product. The second
    option is the more common solution.
    If you allocate the configured material to the BOM for the configurable product, the BOM for the
    configurable product is interpreted and exploded according to the characteristic values assigned.
    The interpretation includes the processing of selection conditions and the setting of field values in
    BOM items according to the relevant actions.
    Allocating a Configured Material to a BOM: From the bills of material menu, choose Bills of material   Material BOM   Alloc. config.
    mat.   Create.
    Chidambaram

  • BOM Explosion for Multiple Process Orders

    Hi,
    I hope someone can assist me with the following: Is there a report I can run or transaction I can do to have BOM explosion for multiple Process Orders? I would like to input process orders for a week and see the BOM details per PO.
    Thanks

    Dear Sukendar,
    1.For this requirement you have to go for a Z report and you can give the Functional Spec's to prepare
    this report to your ABAP consultant.Prepare the input format,logic of the program and the output format.
    In the logic part you can make use of this Functional Modules's CSAP_MAT_BOM_READ or 
    CSEP_MAT_BOM_READ  or CS_BOM_EXPLOSION   or CS_BOM_EXPL_MAT_V2 .
    2.Using CEWB helps you to identify all the material that's having the BOM,but here the report does not
    shows you the level by level by BOM for a FERT.
    Check and revert back.
    Regards
    Mangalraj.S

  • BOM Explosion for MRP Area

    Dear Expert,
    I have doubt regarding BOM explosion for MRP Area. This doubt is triggered when performing MD01, as result I do not find the dependent requirement in MD04 for my FG. I have maintained the BOM through CS61 and MRP area for all component, I understand that only component level system is taking into account MRP area (storage location). FYI before maintaining all components to MRP area, the BOM explosion was successful exploded. Your advice is appreciated.
    Best regards,
    Mahnansa

    Dear,
    Please check the Explosion control in Customizing, Transaction OMIW.
    Try to explode the BOM in CS11 , CS12 or CS13 if it is working there in curret date then chack the planning file entry in MD21.
    You need to convert the planning file entery at MRP area in OM0F.
    Also note the dependent requirement is not generated in the corresponding MRP area to which the production storage location in the material master has been not assigned for the data of the MRP area.
    Regards,
    R.Brahmankar

  • BOM explosion for Multiple  materials

    Dear All
    In Cs11 where we can get bom explosion  report for single material,but i need multiple material more than one material as desired.
    Any Std T code is there.

    Dear Sukendar,
    1.For this requirement you have to go for a Z report and you can give the Functional Spec's to prepare
    this report to your ABAP consultant.Prepare the input format,logic of the program and the output format.
    In the logic part you can make use of this Functional Modules's CSAP_MAT_BOM_READ or 
    CSEP_MAT_BOM_READ  or CS_BOM_EXPLOSION   or CS_BOM_EXPL_MAT_V2 .
    2.Using CEWB helps you to identify all the material that's having the BOM,but here the report does not
    shows you the level by level by BOM for a FERT.
    Check and revert back.
    Regards
    Mangalraj.S

  • BOM explosion  with Two Material Number

    Hi
    How can  i Explosion in  BOM with  two material number, if any Fm is there in sap or any othre options
    Please tell me
    Regards
    Mani

    Your question is not complete.
    There are two types of bom explosion. from child to parent and parent to child.
    You have to pass one material at a time. Please search in sdn for the fm's. This question ihas been widely discussed here.

  • No BOM explosion for sub-contract purchased materials

    Hello,
    I have searched google and this forum and have not found any info on this.  Hopefully someone has run across this same situation and can help.
    We do not want to have a bom explosion happen for externally procured materials (using CU51).  We are using user exit CCUX0800 (EXIT_SAPLCUKO_008) to set no_expl_ext_procurement = 'X'.   This works good, except if the material is set up for external procurement (marc-beskz = "F") and also has a special procurement (marc-sobsl) of "30".  Include LCUKOFFB says to still explode the BOM if the special procurement is "30". 
    Does anyone know why it does this?  We don't want the bom to explode for externally procured parts even if they are set up as subcontracting ("30").  Any way we can do this with a different user exit?
    Thank you.

    Melissa,
    Since you are using Special proc 30 ( subcontracting) system assumes BOM components will be supplied by purchaser.
    When a Subcontract purchase order for subcontracted material is cut on vendor, the components of the subcontrated product is typically supplied by buyer to the vendor. Hence MRP(system ) typically explodes BOM to plan for those compoments in buyer's plant.
    If however you do not want BOM to be exploded &/or components planned in buyer's plant you can set that in BOM of subcontract material at the component level. In the BOM component item detail screen (under tab status/long text) there is a field called Material provision indicator. Set that to L(material provided by vendor).
    This should prevent planning of components (or explosion of BOM) for the subcontract material ( with settings F, 30).
    Hope this clarifies & solves your issue. else please come back with further questions.
    Thanks,
    Ram

  • How to get bom application for a material

    hi abapers
              how can we get the bom application for a particular material.
              suggest me a suitable tables.
              thanks in advance.
    Regards
    Rajaram

    Hi,
    for BOM related tables are MAST+STPO.
    and for 1 st case
    Use the report CS15 - Where Used List: Material in BOM
    Give the material number for which you want to find where it is used.
    In the Type of Where Used List Check the Direct checkbox,
    and in Used in Check the Material BOM,
    Then Click on the Next Screen button available on the Top left cornerof the screen.
    Then in the next screen give the plant number and execute.
    This gives you the report of where ever this material is used.
    Regards
    Message was edited by:
            skk

  • BOM explosion for component in ECC which are relevant for planning in APO

    Hi ,
    as we assign materials the MRP type X0 with the MRP procedure X (without MRP, with BOM explosion) which are relevant to APO, so if i have BOM under this item then how this below level Items will be plan in ECC....?
    as we are excluding the component from planning so how the below level will be plan .....?
    Regards

    Dear SCM APO 22 ,
    Answer lies in your question only.
    as the assembly is relevant to be planned in APO but it will be exploded in MRP and the lower level component will be planned in R/3 only if required.
    Only teh assembly which have MRP type X0 will be planned in APO.
    Revert back if you need further clarification.
    Hope it helps you.
    Regards
    Ritesh

  • BOM Explosions for Materials and Plant

    I am looking for the same functionality as in CS15 where I can check if a component within a BOM is part of another BOM.
    How can I achieve this?
    I have tried the FM: CS_BOM_EXPLOSION or CS_BOM_EXPL_MAT_V2, but I can not get these to work as I wish.
    I have material number and plant as a selection criteria as well as BOM usage.
    Does anyone have a good solution to this?
    Please help out as soon as possible, since I am stuck.
    Rgds,
    /Fredrik.

    Hi Fredrik,
    in the past i used FM CSEP_MAT_BOM_SELECT_WHERE_USED  (and afterwards CSAP_MAT_BOM_READ to get details).
    Also you could have a look at FM CS_WHERE_USED_MAT - it should be like CS15.
    Hope it helps,
    BR,
    Sebastian

  • Problem in BOM explosion for a operation Sub Contract.

    Hi All,
    Please advise how to explode a BOM or Assign component in a Purchase order with Item category (L) for a Operation SubContract External Processing  oriented material for which no material code is created from a Series Operation production order .
    Actually in my scenario, no raw material component will send to the Sub -Contract Vendor. Only Assembled operation material lets say operation 20 from a routing ( which is not having material code ) from an In - house production from a shopfloor has to be sent to the vendor to create a operation 30 material , which is also not having a material code." How to explode a BOM or component allocation for the Non- codified Item in a PO".
    regards,
    YK

    Hi
    Change the control key of the operation to PP02. System will prompt u to PR data screen where u have to tick on Subcontracting checkbox. Enter other mandatory field like material grp, cost element, purchasing grp etc. On saving system will create PR with line items. System will trigger the components reqmt based on the assignment to operation. Example if for operation 20, materials M1 & M2 are assigned, then in the PR u will find M1, M2 in the component screen which u have to send to the vendor.
    Hope it is clear to u.

  • Function module to get the BOM details for a material-plant combination

    hi
    Is there any function module to get the BOM details such as
            BOM Usage       -STLAN
            Alternative BOM -STLAL
            Items                -POSNR
            Required Quantity-EMENG
            Resulting Quantity-MENGE
            Unit of measure    -BMEIN
            Base unit of measure-MEINS
    for a given material-plant combination
    if so please suggest me some FMs.................
    Awaiting for ur reply..............

    try the below fm it may be useful for you
    DATA : BEGIN OF I_BOM OCCURS 0.
            INCLUDE STRUCTURE STPOX.
    DATA : END OF I_BOM.
    CALL FUNCTION 'CS_BOM_EXPL_MAT_V2'
        EXPORTING
          CAPID                 = 'PP01'
          DATUV                 = SY-DATUM
          MEHRS                 = 'X'
          MTNRV                 = P_MATNR
          WERKS                 = P_WERKS
        TABLES
          STB                   = I_BOM
        EXCEPTIONS
          ALT_NOT_FOUND         = 1
          CALL_INVALID          = 2
          MATERIAL_NOT_FOUND    = 3
          MISSING_AUTHORIZATION = 4
          NO_BOM_FOUND          = 5
          NO_PLANT_DATA         = 6
          NO_SUITABLE_BOM_FOUND = 7
          CONVERSION_ERROR      = 8
          OTHERS                = 9.
      IF SY-SUBRC <> 0.
        MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
                WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
    just befor use it check your application area.for my case it is PP01. you can find it in CS12 when you are exploding the bom the value you are giving in BOM application that is the value for CAPID.
    Just go to se37 and checkout the fm it has lot of options here I am using the minimum things.
    regards
    shiba dutta

  • BOM explosion for credit memo req,free of charge,returns order types

    Hi Gurus,
    My client has the following requirement.Sales BOM with header pricing has to be configured for standard order, free of charge, credit memo req, debit memo req, returs order types. I have configured the BOM for standard order(ZOR) successfully, but for credit memo request and other orders its not picking correctly.The component items for the BOM structure is repeating twice.Pleae let me know how to maintain item category determination for credit memo request and other order types.
    For credit memo req  I have created new item category by copying the G2N and updated the structure scope as A and application SD01.so the new item category is ZG2B and I have maintained the below mentioned determination.
    ZCR ERLA  ZG2B
    ZCR ERLA ZG2B G2N
    ZCR NORM ZG2B G2N
    Regards,
    Hari Challa.

    Hi,
    That is incorrect.
    For sales order, you shoudl have used item category groups as ERLA, LUMF respectively. The resultant item categories will be TAP/TAQ etc. The same kind of configuration should be enabled for Credit memos and others also.
    There the item category group will be ERLA, or LUMF
    The document type will be CR / RE etc based on the process
    Now the resultant item category should be TAP/TAQ or you can even have RENN etc but the property of this IC should be same as TAP/TAQ based on what you are expecting, apart from the standard configurations of a return process. If you do this, then your pricing and items will come up properly.
    In specific, you have to look at the BOM configuration of the Item category in the BOM area.
    If you need any detail, pls let us know.

  • Bom explosion collectively

    Dear all
    In cs11 we can see bom explosion for one material. Is it possible to see the explosion collectively in std sap ? if not  so  kindly share your other idea?
    Rgds

    We dont have std transaction to explode more than one BOM, but you can use function module 'CS_BOM_EXPL_MAT_V2' in SE37 and pass on all header materials to explode them all. Thank you.

  • Bill of Material (BOM) for any Material

    Dear all,
    I want to fetch the BOM Components for any material.
    can any body tell me the Flow of tables with link between them for finding the bom.
    Thans in advance
    Regards,
    Anshuman

    Use the FM
    CS_BOM_EXPL_MAT_V2 (BOM explosion for material) or
    CS_BOM_EXPLOSION (General BOM explosion)
    Hope this helps!!
    Regards,
    Prashant

Maybe you are looking for

  • How to setup a new apple ID when one is already connected to ipod

    how to setup a new apple ID when one is already connected to ipod

  • Problem with rfkord10_pdf print program

    Hi,      When i try to execute the standard RFKORD10_PDF program it shows the fallowing error. In comp.code XXX for program RFKORD10_PDF the default form set  is missing Can any one tell me suitable solution to solve this issue. with regards , M.Sree

  • Financial software for personal use?

    I just bought my blackberry bold yesterday and I'm not sure which financial software to use. Has anyone used Ascendo or any of the other money management programs? Which ones do you prefer? I'm looking for something that's more for personal use than

  • Highlight color for Combobox

    I have a JComboBox, when i navigate between the various items inside the Combobox, it gets highlighted by some color. I want to know how to get that color object, i want to use the same color for something else. What would be the RGB combination for

  • Free table space

    Hi, is there a way to free blocks of deleted record? I mean: I have a table of 50Gb and I delete 5Gb; those 5Gb are still part of the table size looking at the dba_segment view. And is there a way to completely free those blocks without export and im