                        Whenever I am making a process order, my by-product is going to the unrestricted storage location through 531 movement but no final inspection lot is generated though I am maintaining inspection plan of origin 05 and inspection type 04 in material master. Please tell how I can get a final inspection lot to record inspection result??
Regards,
Sunit

>
Sunit Kumar Mitra wrote:
> Dear experts,
>
>                         Whenever I am making a process order, my by-product is going to the unrestricted storage location through 531 movement but no final inspection lot is generated though I am maintaining inspection plan of origin 05 and inspection type 04 in material master. Please tell how I can get a final inspection lot to record inspection result??
>
> Regards,
>
> Sunit
Sunit,
1. Inspection Type "05" should be active.
2. Check Movement type 531 in transaction OMJJ, here QM- Not active check box should not be active.
Regards,
Prasobh

Similar Messages

  • QM: NO INSPECTION LOT GENERATED

    Dear Friends,
    My client is using SAP 4.7 version. We are facing the following problem in QM.
    1. For the Material QM view is active in material master, but no inspection type assigned, i.e. inspection set up is not maintained.
    2. After doing goods receipt for the production order, (movement type 101); material stock is in QM (as per MMBE) but NO INSPECTION LOT GENERATED.
    3. I have checked in the display document for the material document posted in goods receipt. It does not show any inspection lot generated.
    4. I tried to assign inspection type 0800 from transaction QA08; but this is again not generating any inspection lot. However the material master is getting updated with the inspection type.
    5. All the Quality masters like inspection plan, sampling procedures, etc. are in place with creation date before the material document posting date.
    Please help in this problem, as it is live system I cannot try many options.
    Thanks in advance,
    Regards
    Vrish

    Hi,
    You need to activate inspection type 04 in QM view of material master. So whenever you do GR for your production order,stock will posted to QM & inspection lot will be created.
    Now in your case,you have done GR,so first you need to cancle material document (101),Then Read PP master data and again do GR for production order.
    Now you will get inspection lot.
    Regards,
    Raja.

  • F110 Error Specify a lot number for the production run Message no.FS546

    Hello Experts,
    I am doing F110 Automatic payment Program.
    All stpes i had done , but Click to start the payment run.
    System give me error,
    Specify a lot number for the production run
    Message no.FS546
    For that I had maintained T code FHCI
    Maintain Check lot , But system can not pick check lot.
    And Maintained Variant in that tab where we can give you House Bank , I'd , Check lot number (But it can not save)
    Please tell me what should i do ?
    Waiting for reply.
    Regards,
    Jemes

    Sir
    No sir check lot is not there.
    Can you tell me in Varaint Field which field i have to fill.
    Program run date:25.09.2009
    Identification feature:P5
    Paying company code:1000
    Sending company code:1000
    Payment method: C
    Pmt meth. supplement:
    Business Area:
    House Bank: STD01
    Account ID: STD01
    Check lot number: 0
    (Check Lot No. is not save inthis field)
    Restart from Check Number:
    Currency: INR
    Payment document no.:
    Print Control
    Print Check:Tick
    Print pay advice note:
    no form summerysection :Tick
    Do not Void any check:Tick
    Please suggest what chnages i do ?
    wating for reply.
    regards,
    Jemes
    Edited by: Jemes on Sep 25, 2009 10:41 AM
    Edited by: Jemes on Sep 25, 2009 10:47 AM

  • Inspection lot creation for inspection type 05

    Hi Gurus,
    We have finished material FERT & semifinished material HALB.We have assigned insp. type 02 & 05 in material master of matl. HALB.When we create production order for FERT & confirm the order , inspection lot is generated for matl.HALB of inspection type 02.
    Now we are reversing the goods issue by movement type mb1a, movement 262.In customizing for movement 262 inspection lot origin 05 is assigned.
    My problem is that when i reverse the goods issue with mvmt.262, inspection lot is not created for insp. type 05. What should be the reason behind this? or are any changes to be done to above setting?
    Regards
    Ram

    Hi Ram,
    Just check the SPRO setting SPRO---> Quality Management ->Quality Inspection->inspection lot creation--->inspection for goods movement --->deactivate quality inspection for a movt type.
    Here against movt type 262 uncheck the QM not active tick.
    It will solve your problem.
    Cheers,
    Tushar

  • Inspection lot is not shown Production order Even after GR.

    Hi Gurus
    My scenario is involved with of Inspection after taking  GR From Production order.i have maintained following settings :
    1.Inspection Type 04 Assigned for relevant Order type.
    2.In Material Mastr Inspection Type 04 Maintained.
    3.Quality plan created with relevant material code with usage -GR(05)
    while i am taking GR Inspection lot is generated.every thing working fine.But inspection lot no.is not displayed in production order (ASSIGNMENT TAB) after taking the GR.
    Am I missing Any settings?
    Regards
    Bala

    Hi
    while i am taking GR Inspection lot is generated.every thing working fine.But inspection lot no.is not displayed in production order (ASSIGNMENT TAB) after taking the GR.
    What is the status of the the lot generated'
    is it REL & CRTD??
    Since You have maintained usage 5 in task list & generally usage should be 1 (for production order ) it will as per my knowledge remin in CRTD state.
    Thenyou have to use QA02 to attach the task list
    This might be a reason that lot is visible.
    I hope this will add some value.
    Regards
    Sujit

  • Want to create inspection lots during In-House production (shop floor)

    Hello,
    As per our requirement we need to inspect a material multiple times (3-4 times) during shop floor production. It means we want to check a material say after operation 30, 50, 70 and 110 (of routing). We don't want to start operation 50 unless inspection of material after operation 30 is over. We don't want to start operation 70 unless inspection of material after operation 50 is over and so on.
    How can we attain this? We have assigned inspection type 03 in material master - quality management. We have assigned various MICs in concerned operations. Inspection lot is getting generated as soon as the release of production order takes place and it contains all MICs (and operations). We are able to make the result recording and defect recording for all operations at the beginning only.
    Is it possible to create multiple inspection lots for these operations and is it [possible to restrict the confirmation of later operation unless inspection of previous operation is over i.e. a usage decision is already carried out for previous operation.
    Puneet

    hi puneet,
    can u please let me know  what miracle u didi to resolve this issue?
    Thanks
    raghav

  • Creation of inspection lot 04 depending on production version

    Hi Experts,
    could you tell me if it is possible to create a Good Receipt inspection (lot origin 04) depending on the production version used ?
    My material has 2 production versions:
    0001 - production with process order
    0002 - production with repetitve manufacturing
    When I do a GR on process order, I do not want to create an inspection lot 04.
    When I do a GR on product cost collector, I want to create an inspection lot 04.
    As I have entered inspection types in material master data, I do not know how to do the distinction ?
    Thanks in advance for your help
    Best regards
    Amaury

    Hi
    Check user exit
    QBCK0003 |Extended QM check for goods receipt
    Regards
    Sujit

  • Automatic Inspection Lot Creation for HUs (storage Loc.) in WHS

    Hi All,
    can someone guide me through customizing/with end result expected from client. How can I setup this configuration.
    The requirement is all Chem.Raw Materilas are subject to Quality inspection with HU managed storage Loc. with WMS.
    Good Receipt is posted Via Vl31n into Quality Stock. Subsequently a Transfer Order will be created & confirmed to transfer of materials from 902 interim storage type to destination storage type and bin. (due to lack of space in the Whse).
    Now expected is that when Usage decision made (Quality Managment) the stock type should change from Q to Unresticted within the same bin and same storage type and material should be made available to issue for orders.
    Also when GR is done 101 mvt. an inspection lot should generate automatically in Whse under the quant.
    Most appreciate your help.
    Regards
    Chandra

    Hi Chandra,
    Generally WM movement type '309' is assigned for posting change (Sap standard setting). This movement type is generally assigned against 321 IM movement type.
    Modify the settings for WM movement type '309' as below:
    Path: LE -> WM -> Activities -> Transfers -> Define Movement types
    - Automatic TO X (activate)
    - Activate 'To item can be confirmed immediately'
    - Activate 'propose confirmation'
    - Activate 'post to same bin'
    This should solve your problem.
    On your other question
    Generally the inspection lot is assosiated with the WM
    stock and Quant if the stock Quality stock is posted to bins directly.
    Please display the Quant using LS23 and let me know your findings.
    Regards
    Madhu

  • Inspection lot PGI for STO-Quality management

    Sirs,
    I have a query. I have an FG where i am using an STO to transfer the material from 1 plant to another. Here i have inspection type 08 assigned in the master. I have assigned the origin 08 to the delivery type NL hence when i save the OBD (not post PGI) the inspection lot is generated. But even though the inspection lot is generated the system is allowing me to post the Goods Issue for the material. How do i bring the lock in invoicing so that if the lot is generated the PGI of the OBD is not allowed and system should give the message 'status of the inspection lot does not allow goods movement'..
    Waiting for your replies,
    Ariel.

    Dear,
    i have the same question..
    is there any way to generate inspection lot from PS Network activity?
    is there any BADI or Workflow...?
    i hope there would be any solution of this scenerio.

  • Inspection lot settings for customer order returns

    Hi
    The course material for CS states the following :-
    +++++++++++++++++++++++++++++++++++++++
    The serviceable item undergoes a technical check when the goods receipt is
    Posted(repair orders) . You can use inspection lots in Quality Management in the technical check. The system automatically generates an inspection lot for the technical check for a returns goods receipt. <The system does this if you have made the corresponding settings in the material master of the serviceable item.>
    +++++++++++++++++++++++++++++++++++++++
    what settings are required & where in the material master ?
    Thanks
    Edited by: Isabelle Britten on May 7, 2008 12:08 PM

    You must have the 05 inspection type activated in the material master.  You'll find this in the QM view of the material.  Click on the button labelled "insp. setup".
    In the next screen add inspection type 05.  Make sure the "Active" box is clicked on at the end of the record line.
    Craig

  • No inspection lot created for new inspection type created

    Hi all,
    We create a new inspection type which is based on a copy-version of an existing inspection type. These inspection type has a inspection type origin of standard SAP 04 (i.e. Goods Receipt from Production).
    Question 1 - we bumped into problem when come to testing in which when perform goods receipt, there is no inspection lot created, may I know why?
    The following fields of this new inspection type are all checked; those not specified, are not flagged.
    1 - Insp with task list (flagged); Automatic Assginment (flagged); Check Chars (flagged); Skip Allow(flagged); Automatic UD(flagged); Serial Number Poss (flagged).
    Question 2 - for this kind of inspection type with origin 04, do i need to perform a goods receipt against a production order or purchasing order? How do I perform a GR against a production order?
    Thanks.

    Hi Tuffy,
    Possibly you might not have ticked on preferred inspection type in material master. This could be one of the reasons. Try to do GR after ticking this.
    The setting you have mentioned (flagged parameters)are seems to be correct. But lot generation is governed by preferred inspection type.
    If you have assigned this newly customized inspection type to lot origin 04, then it would be used against production order and not the purchase order.
    There are several ways to carry out GR against production order. It depends on the scenarios which you follow
    1.     MB31 101 movement
    2.     You may use backflush so while confirming order through CO11N auto GR is posted
    3.     In case of repetitive manufacturing scenario generally GR is done by MFBF transaction
    Regards,
    Anand Rao

  • No Inspection Lot required for Skipped Lot

    Hi Experts,
    I have used DMR to skip 10 lots from a particular vendor and inspect the 11th lot. But the client's requirement is even inspection lot should not be generated for the skipped lots.
    Also, if the material is procured from some other vendor, then the inspection lot should be generated everytime.
    How can I map this?
    Please advise.
    Regards,
    Rahul

    The only alternative I can think of would be to use a development.  Set up the inspections to happen .  No DMR.   You then would use a user exit, (I believe QAAT002, maybe QAAT001 would work). One of those allow you to set a flag in the user exit that supreses the creation of the inspectoin lot.
    You would have to have the user exit look up the GR's for the vendor/material/plant combination since the last inspection lot for this combination.  Then if the count is equal or greater than ten, you create the lot.  If less then 10, you suppress the creation of the lot.
    I would be careful how you code the user exit.  You'll probably only want this to apply to certain materials so you have to come up with a way that allows flexibability in what materials this is used for.  I might suggest using the QMin procuremnet control key.  If you have no procurement functions, you usually define a control key 0000 for this .  Copy that to 1001 for instance.  It will have no functions.  But your user exit would only run if the control key was 1001.  It would immediately exit for any other control key in use.  You might need additional control keys if you do use other features of the conrtol key such as COA receipt.  In that case you might have two control keys that trigger your user exit.  1001 and 1002.  1002 would require a cert.
    I hope this is clear.
    FF
    Edited by: FireFighter on Sep 22, 2011 2:50 PM

  • Inspection lot generation for 343 movement type.

    Hi,expert,
    My client's requirement is to generate inspection lot when a specific type of material is transferred from block stock of a storage location to unrestricted stock of another storage location i.e. movement type- 343, can anybody please explain how to generate the inspection lot and what are the settings, master data to be maintained? thanks in advance.
    rgds
    rajib

    Hi Rajib,
    In first place you need to have Quality infor record for material and vendor create through QI01 t code.
    QM must be activated for mvt type 343 in SPRO --> QM --> Qual Insp --> Insp Lot Creation --> Inspection for goods movements.
    Check the box "QM Proc. Active" in Mat master in Quality tab.
    Activate inspection type 08 in mat master.
    Then do the transfer posting you will get mat doc number.
    Go to display mode of mat doc,
    You will find Ins lot number created in Quantity tab at item level of material document.
    Thank You,
    Anand K

  • Inspection Lot generation for Movement type 101-O

    Hi
    I would like to know, which config / Master data need to generate Inspection Lot for Movement type 101-O.
    I enter subcontract vendor number and set 'SC Vendor' indicator in purchase order delivery address tab and I created QM data in Material Master.(Insp.Type 01)
    While doing GR with reference to purchase Order, stock is Posted to Material provided to vendor - Quality inspection stock. But Inspection Lot
    is not generated.
    Pl suggest me, What should i do to generate Inspection Lot.
    Thanks in Advance.
    RRS

    hi
    Soln 1) Just check whether Inspection is active for 101 - O in SPRO settings if not, activate the same.
    Path: Inspection Lot creation/Inspection for Goods Movement
    Soln 2) As you flag "SC Vendor" in PO and make GR all stocks will be shown against the Vendor.
    From your question I assume that you would like to do inspection for materials coming from Subcontactor end to your Plant:
    If this is the case you dont flag "SC Vendor" in PO, make a normal Goods Receipt for the Subcontracting PO, based on Insp setup in Material Master for 01 Insp type Insp lot will be created.
    Regards
    DC

  • Inspection Lot creation for the 103 movement type

    <<Don't ask for or offer points>>
    Dear Experts,
    we have the requirement of Creating the Inspection lot for the 103 movement type. we have done all the necessary settings for 103 movement type (in OMJJ and under the node   Quality Management --> Quality Inspection -->Inspection Lot Creation -->Inspection for Goods Movements) but still I am unable to achieve the results. Same is happening for 105 movements.
    Kindly let us know what settings need to be done in order to achieve the same.
    Full points will be awarded for the reply
    Regards.
    Edited by: Matt on Sep 18, 2011 4:44 PM

    Hi,
    If you have activated two inspection types (eg 01, 0101) of same inspection lot origin (01), in material master you should  have a preferred indicator set for the inspection type for which you want to be selected when you perform goods receipt.
    This check box is available in the inspection type set up in the Material master.
    Also check whether the post to inspection stock indicator is set for the material (in the inspection type), then only material will be posted to inspection stock.
    Please confirm, what happens to the stock after making MIGO. check in MMBE and confirm
    Go through the link and maintain the necessary settings. I think default settings for 01 type should work.
    http://help.sap.com/saphelp_470/helpdata/en/2d/350e4d448c11d189420000e829fbbd/content.htm