No Purchase Requisition Generated after MRP Run MD02

Hi All,
After runing MRP Run MD02 for finish product with MRP Control parameters for create purchase requisition as 1 (Create Purchase Requisitions) . System is not generating any purchase requisitions for raw materials required for assembly.
If we select 3 create planned order system is able to generate planned orders for raw materials required for assembly.
Plz guide why am not able to generate purchase requisition directly.
Regards,
Sipra

Sipra,
Couple of checks,
1. Check whether the Material is defined for "F" - External Procurement in MRP2 view of the material master.
2. Check whether the material type used for the material is enabled for "External Purchase orders". Transaction OMS2.
Regards,
Prasobh

Similar Messages

  • Purchase req type after MRP Run

    Ca we control the type of Purchase req after MRP Run.
    Now for every material it is creating "NB" type purchase req.
    Can we control it material type or by mat number.
    We have 2-3 purchase req types in system for Material.
    Amit Shah

    Dear ,
    Goto -OPPR-Enter Plant Code and Maintain MRP Group -0000( as SAP Standrad for External Procurement ) -Select Scheduling /Doc Type tab -Here you can assing the PR type as per your requirement so the while MRP run , it will selct the PR documents types based on OPPR .At the same time , assing this MRP group in MRP1 view of the material .
    Try and come back
    Regards
    JH

  • Schedule lines not generated after MRP run

    Dear All,
    I am trying to create Schedule lines through MRP run , but instead system creates MRP element PRqRel  and its PurRqs when i check in MD04 ,  the following are the prerequisite i done before MRP run , but still Schedule lines are not generating.
    1.activated checkbox source list in material master.,Procurement type is F, MRP type PD , lot size MB , marked JIT  Scheduling indicator as 1 in Pur view of material master , no MRP group is used in our process.
    2.Maintained Inforecord.
    3.Maintained source list for the material and marked MRP relevant as 2. Validity also checked.
    4. Quota arrangement for this vendor only.
    5. Created New scheduling agreement.
    6. Material is not sent for subcontracting.
    7. Ran  MD02 with following parameters ,
    Processing key NETCH Net Change in Total Horizon
    Create purchase req. 1 Purchase requisitions in opening period
    Delivery schedules 3 Schedule lines
    Create MRP list 1 MRP list
    Planning mode 3 Adapt planning data (normal mode)
    Please let me know if i am missing something
    Thanks in Advance
    Benny

    Hi,
    Please check the below links...
    Schedule Lines not getting created in MRP
    Schedule Lines not generated for MRP Type PD
    Kuber

  • Schedule Lines are not getting generated after MRP run.

    Hi,
    I have an issue where a SA exists for the parent material with item category L (subcontracting). The parent material has a valid BOM and some sub components as well. I see in CS03 that BOM is fine with validity dates for the parent material. A valid source list also exists for the parent material where SA is present as the source of supply with MRP indicator as 2. Now when i run MRP for the parent material using MD02 (NETCH), with indicators as below:
    Create pur.req.  2
    Schedule lines   3
    Create MRP list  1
    Planning mode   1
    i don't see any schedule lines in MD04. Instead it creates a PR that too without any source of supply.
    In master data for the parent material MRP type is PD with Procurement type F and special procurement key 30. I have checked and every thing seems to be fine still MRP run doesn't create schedule lines.
    Any help is appreciated. I can give more info if required.
    Thanks.

    Dear Rakesh,
    Scheduling agreement:An outline agreement against which materials are procured at a series of
    predefined points in time over a certain period.
    1.For this you have to first use ME31L for creating scheduling agreement and then ME38 for maintaining scheduling agreemnet
    schedule.
    2.Ensure in the source list after maintaining the material,vendor combination the setting for MRP relevancy is set to 2 - Record
    relevant to MRP,Schedule line generated automatically.
    Moreover you have to use value 3 for delivery schedule line which is one of the MRP control parameter while taking MRP run.
    So for the materials for which scheduling agreement exists,schedule lines will be generated.
    Check and revert back.
    Regards
    Mangalraj.S

  • Automatic Purchase Requisition Creation in MRP run

    Hi,
    1. I create a Sales Order for quantity 20 of main material MAT which has two sub-components - COMP1 and COMP2. The plant in which this sales order is being created does not have any stock quantitiy of the material or its sub-components. For quantity 20 of the main material, quantities required of the sub-components are 40 and 60 respectively.
    2. I run MRP using transaction MD03 for the sub-components. This created purchase requisitions for the sub-components automatically. But, I see that the system creates only one purchase requisition of quantity 40 for COMP1 but two purchase requisitions for COMP2 each having quantity 60.
    Can you please tell me why is the system creating two purchase requisitions for COMP2?
    Thank you,
    Helpful answers will be immediately rewarded!

    Hi Janakiraman,
    I compared the parameters - Safety stock, Lotsize, Maximum Lot Size, Reorder point - between the two components but found all the values to be same.
    The only difference I found in the parameter values was...
    For COMP2 (the one for which 2 PRs were generated) 'Special Procurement' field was blank
    For COMP1 this field had the value 4A which means "STO from X101 plant"
    Do you have any idea what could be the reason?
    Thank you.

  • Automatical Purchase Requisition Creation in MRP run

    Hi,
    1. I create a Sales Order for quantity 20 of main material MAT which has two sub-components - COMP1 and COMP2. The plant in which this sales order is being created does not have any stock quantitiy of the material or its sub-components. For quantity 20 of the main material, quantities required of the sub-components are 40 and 60 respectively.
    2. I run MRP using transaction MD03 for the sub-components. This created purchase requisitions for the sub-components automatically. But, I see that the system creates only one purchase requisition of quantity 40 for COMP1 but two purchase requisitions for COMP2 each having quantity 60.
    Can you please tell me why is the system creating two purchase requisitions for COMP2?
    Thank you,
    Helpful answers will be immediately rewarded!

    Hi Janakiraman,
    I compared the parameters - Safety stock, Lotsize, Maximum Lot Size, Reorder point - between the two components but found all the values to be same.
    The only difference I found in the parameter values was...
    For COMP2 (the one for which 2 PRs were generated) 'Special Procurement' field was blank
    For COMP1 this field had the value 4A which means "STO from X101 plant"
    Do you have any idea what could be the reason?
    Thank you.

  • PR,s not getting generated after MRP run

    Dear All,
    I'm running MRP through MD51 for WBS element where RM's are attached to WBS.
    It is MTO scenario where no stocks of RM's are maintained. I have checked all relevant settings of Masters.
    After running MRP through MD51, system is not proposing PR's for RM's but when i run the MRP for independent FG (MD02 & MD03) system is proposing PR's.
    Please suggest & help.
    Thanks in Advance.
    Shaiz

    Little confused on your statement
    System is not proposing PR's for RM's but when i run the MRP for independent FG (MD02 & MD03) system is proposing PR's.
    I would like to Know, whether the FG is attached with WBS or RM?

  • After firming planned order, new planned order is generating in MRP run

    Hi Experts,
    I am using SAP AFS. Planning strategy is 21- MTO with Project settlement. MRP type is PD. Lte size is EX. Procurement type is X.
    We are using the production versions. Individual / collective reqmts is 1. Planning time fence is not maintained.
    In sap AFS T.Code for MRP run is /n/afs/md02. After receiving the Sales order, MD04 screen gets updated accordingly and I am running the MRP.Planned orders are generated accordingly. I am firming the planned order manually through MD04. The satr mark is also appearing.
    My problem starts now. If I am running  the MRP again for the same requirements another planned order of the same qty. is getting generated. That means after the second MRP run, I am having two planned orders (one firmed plnd order) and second is the new planned order. My requirement is that MRP should not generate any new Plnd. order / PR's if there is no new Sales order.
    The parameters for MRP run are "1" for "Create PR's", '1" for "Plng Mode" and '"1" for "scheduling ".
    I have tried in all the possible ways, but of no use. Still new plnd order is generated after firming the 1st plnd. order in MRP run.

    Thanks all for your feedback..
    @ Vishal
    1. Yes, Both Old firmed planned order and newly generated planned order have the same grid value
    2. For both the planned orders :
    Special Stock is E u2013 Orders on hand,
    Consumption is V,
    Sales order is the same (As we are using MTO , Strategy 21) and same WBS element.
    3. First planned order is not in the assigned tab of MD04. This means that has been allocated to some object. u2013 I didu2019nt got this point. Can u please elaborate?
    @ Nikhil
    1. Quantity of sales order is not reducing after firming the sales order
    2. Account assignment category for both the planned orders is u201CZu201D - Indiv.cust./project
    I have made some more observations and found the following differences between the two planned orders
    From  MD04 , keep the cursor on corresponding planned order
    & click on upward arrow ( available on bottom side of the report).
    It will show what will be the originating requirements i e. for which requirements this planned order generated.
    For Firmed planned order it is taking me to screen u201CPegged Requirements
    u201D*And the following data is present:
    Planned dates: 04.07.2010
    MRP element No. 3100001185 (Sales Order No.)
    MRP element item 100
    Scheduling No. is 1
    MRP element indicator - VC u2013 Order
    MRP element data- 3100001185/000100/0001
    Plng segment u2013 3100001185000100000
    P.O / Order Type u2013 ZX
    Rec/reqd Quantity 10
    MRP element u2013 Order
    For new planned order generated, I am going to Screen *u201CProcurement without Requirementsu201D
    *The following data is present
    Planned date 03.07.2010
    MRP element No. 0000123522 (Planned order No. of the newly generated after MRP Run)
    MRP element Ind. u2013 PA
    MRP element data 0000123522/SO
    MRP element item 1
    Scheduling No. 1
    MRP segment 20
    Plng segment u2013 3100001185000100000
    Rec/reqd Quantity 10
    P.O/Order type- KD
    MRP element u2013 Plnd Order

  • 'Releasestepcreated' not getting triggered for PR generated through MRP run

    Hi,
    I have PR Release strategy workflow configured, working well when i try to create PR manually, triggers workflow.
    PR's created thorugh MRP run, triggers release strategy but not workflow.
    I checked the event trace 'releasestepcreated' event not triggered through MRP run.
    Please respond ASAP.
    Your inputs will be highly appreciated.

    Short Text 
    Workflow with multiple workitems 
    Long Text 
    Refering SAP notes that i came to know that workflow is not supported
    through MRP run (md03/md04).we are not using Planned orders.
    To trigger workflow for Purchase requisitions created by MRP run, we
    have developed a custom report to trigger workflow explicitly.
    1.MRP batch job runs every night. After MRP job,planned to schedule
    another job to trigger workflow for PR's created MRP run.
    2. Used FM 'SAP_WAPI_CREATE_EVENT' to trigger workflow.
    3. PR requires 5 levels of approvals based on release strategy
    configuration.
    4. The issue is PR 'XXX' created and waiting for approval in agent's
    inbox.When 2nd day MPR runs same PR 'XXX' effected, another
    workitem for the same PR in agent's inbox.
    We have multiple workitems for the same PR in agent's Inbox.
    If i execute one of the workitem,releases PR, multiple workitems are
    getting generated for 2nd level approval for the same PR.
    Please give your inputs to resolve this issue.

  • Purchase requisition not generate for dependent requirement after MRP run

    Hello PP expert,
      In our MTO scenario after MRP run planned order generate for header material but no PR generate for BOM components, (BOM not explode) when we run MRP component level in MD02 PR generate, system showing message "40- No coverage not provided by master plan" in MD04 order tree. this problem coming after when we DIMP applied. I checked some OSS note also.
    Can any one provide right solution.
    thanks in advance.....its urgent as client requirement.
    regards,
    Amit Awasthi.

    Hi Amit
    You must select the green star for the correct answer, in order to close the thread.
    You may also select the yellow start for the helpful answers, in order to award points for those who helped you. See the blog below for more details:
    How to close a discussion and why
    I can see that most of your old threads are still open, therefore, I'd like to ask you to review and close them, by selecting the correct answer.
    BR
    Caetano

  • Purchase Order is generated after MRP for Material with MRP Type ND

    Hi Everyone,
    Material type := HAWA
    My material procurement type = F i.e. External Procurement.
    MRP Type = ND in Production server , and VB in Quality
    Lot Size = EX
    Material Status :- 15 Pre-release both for Quality and production server
    The Material is bulk material and bulk material indicator is set.
    Purchasing View is also maintained for the same.
    Planning Strat = Z5 Company specific
    Special procurement key:- Z7 Company specific
    I am running MD02 with following parameters.
    Create Pur Req =1, PR
    Create MRP List = 1, MRP List
    Delivery Schedule = 3, Schedule Lines
    Planning Mode = 2 Re- Explode BOM & Routing
    Scheduling = 1
    Issue:
    After MRP run, system is  generating PR, Though with MRP type ND purchase requisition should not be generated.
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.
    After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    We havent been able to locate the root cause so far
    Please guide us
    Thanks in Advance,
    Ayaz
    Edited by: Ayaz Alam Khan on Feb 16, 2011 2:41 PM

    IF the material is ND, system won't Run MRP for the material
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    There is no link
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    system will read the X plant  material status or plant specific material status first and then only system will read MRP type

  • MRP no purchase requisition generated

    Dear Experts,
    I have a problem that I can't generate purchase requisition after MRP run.
    Example : I have a finished goods material FG and under which has 1 component Mat 1.
    The setting in material master of Mat FG is internal procure(E), MRP type = "PD".
    Mat 1 is external procure(F) and MRP type = "ND"
    I entered the forecast requirement in MD64 for Mat FG  and I set the Create PR indicator to 1 in MD02
    and start running MRP.
    Planned order created for Mat FG, but no PR created for Mat 1 which only shows dependent requirement for Mat FG in MD04.
    I can't see there is Mat 1 in the planning file(MD21) under Mat FG.
    Any settings I missed and can anyone help?
    Thanks a lot.
    Claude

    Hi,
    IF you  do not maintain mrp type PD then system wont consider the material during MRP run, so convert it to PD.
    Also go through the below link which will clear your doubts of master data maintenance for MRP.
    [http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/30f4d6c1-0808-2d10-2ea5-f9b2863cfed8?QuickLink=index&overridelayout=true&47034186922243]
    Please check and revert.
    Thanks
    Hrishi

  • Creation of Purchase Order automatically via PR after mrp run.

    Hi Experts,
    I want  to know that , after MRP run  i got the no of PR'S. As i know , through MD04  i can create purchase order from particular pr but is their any option from which purchase order  get generated automatically from pr's which are generated afrer MRP run.
    Thanks n Regards
    Anupam

    Hi,
    You can maintain source list Tcode ME-01 and make it MRP relevant by selecting Sorce list MRP relevant. In sorce list you can maintain vendor and material data valid for particular period and make it MRP relevant.
    With this you can automatically generate purchase order from Purchase requisitions after MRP Run.
    Regards,
    Tushar Patankar

  • Planned order created after mrp run instead of purchase req

    Hi All,
    I am facing a strange problem about planned order being created after mrp run jobs runs in background instead of purchase req. This is happening randomly. In the material master MRP view 2 procurement type is F and in the varient for the MRP job the in Purchase requisition control parmater 1 is marked that is purchase requisition. Also planning file is having the entry once there is shortage and hence MRP run is there always if there is shortage of material.
    With Regards
    Tarun

    Hi Tarun,
    Please maintain the control parameters as
    Processing Key                                       NETCH
    Create Purchase Requisition                          1
    Sched. Agreement Schedule Line                   3
    Create MRP List                                            1
    Planning Mode                                               1
    Scheduling                                                     1
    Please let me know the results.
    Regards,
    satyajit

  • How system will generate schedule line for PO after  MRP run.

    Dear Experts,
                                 i have updated  MPS in MD61, the period indicator was  M (monthly),  after  MRP run, system  generating schedule  lines  on daily basis for Scheduling Agreement(ME38), i want  schedule lines   on mpnthly basis, how to achive this,
    thanks in advance.
    regards
    rajakarthik

    Hi
    1. Are you maintaining any Planning time fence period for MPS- No 
    2. What is the PIR qty you maintained in MD61:
                                                                                    i.) FG01 is having BOM  child part RM01.
                              To  produce 1 nos of  FG01 , I need 1 nos of  RM01                                                                               
    ii.) i maintained  FG01 in MD61  with PIR  Qty 5000. in MD61,Planning period is M  and planning hirizon1- jan10To 31-Jan10
           ii.)  i maintained lot size:Monthly lot size for RM01.
           iii.)  there is  no stock  available for  both RM01 and FG01.                                                                               
    3. After MRP how much qty is get planned on what date-     
         i)   planned order created for FG01 in co41 with qty-5000 nos.
         ii)  in ME38, schedule  line created for RM01,  on 01-01-2010, with 5000 nos,  currently Category of Delivery Date
    field is D and delivery date is   01-01-2010, but i want Category of Delivery Date should  be M and delivery date should be 01.2010.
    thanks
    raja