While creating control cycle for kanban i am getting this error,
No suitable replenishment strategy.
strategy has been assign to plant .

What is the replenishment strategy that you are using? Some of the external procurement strategies (without MRP) require storage location to be excluded from MRP.
This can be done by maintaining 1 in the SLoc MRP Indicator field (MRP4 view of Material master for the storage level you are using)
KANBAN Without MRP - PP KANBAN - SAP Library
Anoop

Similar Messages

  • Kanban Replenishment Strategy with Reporting Points

    I am trying to implement a SAP kanban system with repetitive manufacturing using reporting points.  My problem is that when I change the status from empty to full I get error RM086 - GR with backflush not for reporting point logic with automatic GR option.  I get this error regardless of control key (auto GR or not auto GR) setting on the routing.  I reading SAP help on the subject; I see there is a page discussing replenishment strategy with reporting points which would infer that there should be a strategy with a similar name in configuration for replinishment strategies for in-house prodution.  We are on ECC 6.0 and this option is not available in our system.    What am I missing???

    Hi,
    As you are using In House production Replenishment Strategy , You must define Replenishment strategy for reporting points in Configuration as below:
    SPRO->Production>KANBAN>Replenishment Strategies>Define In-house Production Strategies>Working With Reporting Points Replenishment strategy you need to define.
    Then assigned this defined strategy in KANBAN Control Cycle in PKMC-->Replenishment Strategy->
    Choose In-house Production Radio Button and in front of that select the above defined replenishment strategy to work with reporting points.
    Hope this helps.
    Regards,
    Tejas

  • PK01 Replenishment Strategy without MRP

    Dear guru ,
    i want to create a control cycle with a Replenishment Strategy without MRP.
    The material master have MRP Type ND.
    When I create a control cycle the system select strategy for  kanban control with MRP.
    I have verified that I must also enter storage location mrp indicator equal to 1 in order to select strategy control without MRP.
    If i enter storage location mrp indicator equal to blank why the system donu2019t check only material master mrp type ?
    Thanks.

    Not answered.
    Closed.

  • Replenishment strategy in kanban

    Hi,
    I have created replenishment strategy for maintaining in control cycle of kanban.
    1) In house production strategy
    2) external procurement strategy
    3) stock transfer strategy.
    But while creating control cycle I couldnot view the strategy 1) and 2).
    I could see only 3rd stratgy.
    Pl. tell me what could be the reason.

    Hi
    The Problem is that the Strategy created is not allowed for storage location that is included in planning.
    Error msg no PK192
    Solution
    Change the MRP indicator for the storage location in the material master record.
    In MM02 for the material , Plant and Storage location combination  select the ind 1 for SLoc MRP indicator in MRP-4 view and chk whether the newly created Strategies are appearing in PK01 or not.
    Regards
    Brahmaji

  • Selection of suitable planning strategy

    Hello All
    Here is a requirement for deciding the planning strategy of the material, material is produced when the actual order arrives for it, but procurement of sub assemblies can be done beforehand, to this material belongs 5 subassemblies, out of which 4 are procured before sales order arrival & 1 is procured after sales order arrival, this is so because the assembly which is procured after sales order arrival depends upon the order, i.e. the specification for this assembly depends upon the order itself. I decided strategy 52 for the material but in case of this strategy all the downlevel assemblies are procured before sales order arrival, but in my case one of the assemblies is procured after sales order arrival and remainng procured before. Kindlysuggest the suitable stratey for the material. Expecting your positive & prompt response.
    Regards,
    J K Tharwani

    Hello Pradeep
             Thanks for replying to my query, Individual/Collective requirement indicator dosnt work because it only passes the requirement of header material individually or collectively depending upon the setting done in the material master of component, if we have set it to 1 then it passes the header level material requirements individually i.e. for each requirement of  header material planned order will be created for component immaterial of the sales order arrival, and if we set it to 2 the requiremets of header level material are clubbed into one requirment and only one planned order is generated for the component.to. Shall look forward to your valuable input.
    Regards,
    J K Tharwani

  • Suitable pln strategy

    hi all,
    wha is the prompt planning strategy for the bike manufacturing company.
    here the planning is taken care by the MPS /MRP
    FERT MATRL -MPS
    OTHER COMPONENTS - MRP
    what is the step to run the planning run
    whether i want to run first MRP for the COMPONENT
    then i proceed with THE MPS or fert material
    here how the sales order requirment trigger in the planning
    i need ur inputs
    with regards
    vbakyaraj

    so when will the scenario  come  as like SAP STANDARD run the MPS first and then the MRP run.
    one mor doubt that if i run the mps it will plann for the level 1 materils
    suppose i want to plan the fert of 100 qty. if i run mps then it will give the plnned order as 100 for fert and its sub-assemblies.
    after whether it will consider the sub-assembly components in to plan
    or we have o run mrp separately
    why i ask is, how the requirment is come from the fert (mps run) to the
    sub-assembly components(mrp run)
    i maintain sub -assemblies as a bom
    pls explain
    rajv

  • Kanban Replenishment

    Hi
    I am creating the control cycle( Classic KANBAN ) with replenishment strategy External Source , I am not allowed to do.
    I am checking the drop menu and error message is coming no suitable replenishment strategy found.
    Please maintain the replenishment strategies in Customizing for Kanban
    It is surprising because Replenishment stratigies are maintained for the plant when I check the Customizing.
    Any help is appreciated.
    Regards
    Ankur

    Hi,
    It may be very very late to answer you, but it may be useful to other users.
    If you selected the external source strategy in the control cycle, you need to inform in the material master, in the screen MRP 4, in the field 'SLoc MRP indicator' the value '1 - Storage location stock excluded from MRP'. Make sure to access the material informing the center and Storage location, otherwise this field will not be visible.
    You do this because the kanban will act as the 'new' MRP for this material.
    Regards,
    Alejandra.

  • Purchase Order E-mailing with Release Strategy

    Hello,
        We are experiencing an issue when e-mailing a Purchase Order which has a release strategy. When the order is released, the confirmation e-mails are going to the person who releases it when it is supposed to go to the person who has created the P.O. We are using a Smartform P.O. based on /SMB11/BL_MM_PO_L and print program /SMB40/FM06P. I must note that there was a bug found in the aforementioned print program and before that was fixed e-mailing would not work at all.
      We have also attempted to use all combinations of standard unmodified print programs and standard unmodified smartforms and have had no luck at getting the confirmation e-mail to send to the correct person this way either.
      SAP has recommended that we use program SAPFM06P with form Medruck. While this combination does work correctly, Medruck is not a Smartform. Has anybody here used a smartform Purchase Order with a release strategy and had the confirmation e-mail send to the created and not the releasor?
      Below is a list of the print programs and forms we have tried in various combinations. We are running ECC6/Basis 7
    Print Programs:
    /SMB11/FM06P
    /SMB40/FM06P
    SAPFM06P (Sapscript Only)
    Forms:
    /SMB11/BL_MMPO_L
    /SMB11/MMPO_L
    /SMB40/MMPO_L

    Hi,
    Purchase order via e-mail in SAP sys,the configurations and pre-requisites are follow:
    1. You must maintain an e-mail address in the address in the vendor master.
    2. The same applies to your own user master. You also have to specify an e-mail address there in order to identify the sender.
    Note that it is not possible to change the e-mail address of the vendor via the SAP purchase order transaction (ME21N, ME22N, and so on). The system only uses the e-mail address of the vendor that is maintained in the vendor master!
    3. For the output type for default values, a communication strategy needs to be maintained in the Customizing that supports the e-mail. You can find the definition of the communication strategy in the Customizing via the following path: (SPRO -> IMG -> SAP Web Application Server -> Basic Services -> Message Control -> Define Communication Strategy). As a default, communication strategy CS01 is delivered. This already contains the necessary entry for the external communication. Bear in mind that without a suitable communication strategy it is not possible to communicate with a partner via Medium 5 (external sending).
    4. Use the standard SAP environment (program 'SAPFM06P', FORM routine 'ENTRY_NEU' and form 'MEDRUCK') as the processing routines.
    5. In the condition records for the output type (for example, Transaction MN04), use medium '5' (External send).
    6. You can use Transaction SCOT to trigger the output manually. The prerequisite for a correct sending is that the node is set correctly. This is not described here, but it must have already been carried out.
    7. To be able to display, for example, the e-mail in Outlook, enter PDF as the format in the node.
    For more details, check SAP note:191470
    Regards,
    Biju K

  • Kanban: in-house production. relation kanban - replenishment order

    Dear Experts,
    We are investigating the posibilities of using kanban for in-house production. We work with production orders. I have set the test system so it works with classic Kanban and a replenishment strategy that will create PP production ordres.
    The system works OK. When the KANBAn is set to EMPTY (in the kanban board for instance) , a replenishment element is generated. The relation is 1 KANBAN - 1 Production order.
    Is it possible to "assign" two KANBANS to a single replenishment element (productio order in my case)? In some cases two or more kanbans will be emptied at the same time (in the KANBAN board for instance), and this would reduce the "noise" in the system.
    Somehow in the documentation "PP-KANBAN" manual, inside "KANBAN control. in-house production" some other option to reduce the amount of production orders is mentioned, but not very clearly explained how to do this.
    Thanks for your answers,
    Arturo

    Hello,
    Your question is not clear to give correct feedback. Do you want to wprk with multiple KANBANS with production orders?
    I am not understanding about the sentence "reduce the amount of production orders"
    If you want to work work minimum production orders then you can automate the KANBAN replinishment through MRP.
    Raegards
    TAJUDDIN

  • Send purchase order e-mail with release strategy

    Hi!!
    I have a problem with sending e-mails in purchase order that are blocked with release strategy.
    I create a purchase order that is block for the release strategy, then I release it. This is working OK, but I can't send an e-mail with this released puchase order, to do it, I have to modify something in the purchase order.
    Somebody knows what is happening?
    I would like to send e-mails without previous modification of the purchase order.
    Thanks for your help.

    Hi,
    Purchase order via e-mail in SAP sys,the configurations and pre-requisites are follow:
    1. You must maintain an e-mail address in the address in the vendor master.
    2. The same applies to your own user master. You also have to specify an e-mail address there in order to identify the sender.
    Note that it is not possible to change the e-mail address of the vendor via the SAP purchase order transaction (ME21N, ME22N, and so on). The system only uses the e-mail address of the vendor that is maintained in the vendor master!
    3. For the output type for default values, a communication strategy needs to be maintained in the Customizing that supports the e-mail. You can find the definition of the communication strategy in the Customizing via the following path: (SPRO -> IMG -> SAP Web Application Server -> Basic Services -> Message Control -> Define Communication Strategy). As a default, communication strategy CS01 is delivered. This already contains the necessary entry for the external communication. Bear in mind that without a suitable communication strategy it is not possible to communicate with a partner via Medium 5 (external sending).
    4. Use the standard SAP environment (program 'SAPFM06P', FORM routine 'ENTRY_NEU' and form 'MEDRUCK') as the processing routines.
    5. In the condition records for the output type (for example, Transaction MN04), use medium '5' (External send).
    6. You can use Transaction SCOT to trigger the output manually. The prerequisite for a correct sending is that the node is set correctly. This is not described here, but it must have already been carried out.
    7. To be able to display, for example, the e-mail in Outlook, enter PDF as the format in the node.
    For more details, check SAP note:191470
    Regards,
    Biju K

  • Planned Replenishment with Message no. /SCWM/REPL008

    Hi experts
    I can run Planned Replenishment with the old material and system can created the warehouse task. but for the new product created today, after excuted the REPL program and it shows the related replenishment quantities, but when click "perform replenishment"  system alway says "Replenishment run started in whse no. W202 with replenishment strategy Planned Replenishment. Message no. /SCWM/REPL008". I have compared the product parameters and they are same, some backgroud as below:
    1, I use the consign stock for vendor,
    2, have assigned the fix bins to the new material.
      please advise.
    Leo

    I have get the answer from SAP, notes 1784164 can solve this problem.
    the Symptom is "If stock determination is active for such a batch product and no batch is specified in the delivery, the system may not find any stocks even though stocks do exist"

  • Replenishment for random bins

    hello all,
    I would like to verify the steps below that i am planning to use for random bin management in a storage type.
    1. I am planning to use mvmt. type 319 and assign it to particular storage type in configuration,
    2. I am using only the Minimum and replenishment quantity for the particular storage type without specifying any fixed bins in the material master.
    3. planning to use t- code LP24 to carry out random bin replenishment.
    4. also, i would like to what is the difference between "Transfer orders immediate for fixed bins and Transfer orders Immediate for random bins" in configuration under replenishment method for storage type.
    pl. let me know if all these steps are correct and if i want to carry out any more additional steps.
    Thanks,
    Maxx

    The differnece in configuration is that in field V_T331M-REPLT you set "1" (immediate TO, fixed bin) or "2" (immediate TO, random).
    In case of fixed bin:
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/fd/90fbf4b3cd11d3b2ad0050045571f7/frameset.htm
    1. Immediate TO Creation for Fixed Bins
    With this replenishment strategy, the system checks the stock situation in the bin during transfer order confirmation. It uses the quant data and the material master data from the storage type view. A replenishment transfer order determines the fixed storage bin of the material in this storage type as the destination storage bin.
    In case of random bin replenishment:
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/fd/90fbf4b3cd11d3b2ad0050045571f7/frameset.htm
    2. Immediate TO Creation Random Bin Management
    With this replenishment strategy, the system checks the stock situation of the material in the entire storage type during transfer order confirmation. All the quant data of the material in this storage type and the material master data from the storage type view are used by the system. If the entire stock in this storage type falls below the minimum quantity after transfer confirmation, the system creates a replenishment transfer order. The destination storage bin is determined through the putaway strategy for this storage type. Maintenance of a fixed storage bin is therefore not required in the storage type view of the material master.
    So, as you can see, the differences are:
    - stock situation --> system checks only the (destination) fixed bin (fixed bin) / system checks the (destination) storage type (random)
    - destination bin --> fixed bin (fixed bin) / determined based on the putaway strategy of the storage type (random)

  • Transfer Requirement not getting created

    Hi All,
    My query as below;
    Production order is created using KANBAN (Control Cycle/Supply Area is defined) using classic KANBAN.
    WM is in place and all the setting related to TR/TO creation for WM movement type 103 is in place.
    When i am trying to receive this Production after completion it is not creating the TR/TO, while as material document is getting generated and shows the stock directly in interim storage type 901 without creating TR and TO.
    Further i checked there is indicator in Production order i.e "Kanban indicator" that gets checked automatically when Production order is created using KANBAN Processs and if i remove that indicator forcefully, TR and TO is getting created normally.
    Please provide some inputs where can be the problem and how TR and TO can be created normally eventhough KANBAN indicator is checked in Production order and where i can found the setting related to "KANBAN INDICATOR".
    Appreciate your help.

    Hi Maddy
    Thanks very much for your response.
    1. When you use KANBAN, you define separate KANBAN storage location, which is different from WM-managed replenishment storage locations, and separate KANBAN interim storage area with storage bin.
    Yes different storage location is defined which is not WM-managed in supply area.
    As you said Control Cycle is defined, see if the interface is properly defined for both of these Sloc.
    Where i can check whether interface is properly defined or not.
    2. See if you have defined the KANBAN replenishment strategy with Control type Transfer Requirements from a Storage Location which is being controlled by WM in the Customizing for Production under KANBAN > Replenishment Strategies > Define Stock Transfer Strategies
    Actually for a material two strategies are defined like;
    1) In-house Production strategies-0003-
    supply area is defined with storage location which is IM managed.
    And when this order is completed and i am trying to receive this in WM SLOC (usally whatever SLOC we have defined in supply area it proposes that SLOC at the time of receipt but i am changing this manually to WM managed SLOC) using transaction MIGO, it is directly taking the stock to 901 interim storage type and in total the stock increases but the problem is when TR is not getting created i am not able to take this to the storage bin as per strategies defined.
    2) Stock Transfer Strategies-This is working fine and in that TR/TO is working fine.
    3. For TO to get created automatically by the system from the transfer requirement, see if an indicator Automatic TO creation in the replenishment strategy is set or not. Yes this is set for stock transfer strategies but i didn't find option to check the TO creation automatically for in-house production strategy
    4. Also, check that you have set up a suitable replenishment movement type for KANBAN in the Customizing for Warehouse Management under Activities > Transfers > Define Movement Types (i.e.standard is 350 for KANBAN replenishment)-Yes this is also defined correctly.
    Appreciate your more inputs on this.

  • KANBAN - STO (error : Goods movement not possible with mvmt type 351)

    Hi,
    I have configured KANBAN STO in the system which is working fine.
    I am able to empty the bin and create STO (purchase orders)
    But when I select a bin and try to make it full, system gives error message:
    "Goods movement not possible with mvmt type 351"
    In KANBAN STO replenishment strategy, I have used movement type 101,
    I m little confused from where this 351 movement type is coming from.
    Please help resolvethis issue.
    Pavan

    Hi,
    Below is the entire message:
    Goods movement not possible with mvmt type 351
    Message no. M7096
    Diagnosis
    You have entered a movement type that has not been defined for this transaction/event.
    Procedure
    Choose another movement type.
    You can choose the movement type as follows:
    If you know the movement type, enter it directly in the Movement type field.
    Choose the movement type via the menu option Movement type.
    Choose the required movement type from the possible entries.
    If you do not find a suitable movement type, exit this function and choose a different goods movement from the Inventory Management menu.
    Pavan

  • Need help to deploy IP Multicast in private network

    Hi,
    I am currently working on a project where there is an urgent requirement to deliver an IP multicast solution.
    The network itself is fairly simple.
    IP Cameras as connected to pairs of Catalyst 2960 switches in 'access nodes'. There are 8 cameras per node, 4 on each switch. There are multiple nodes, 3 at the moment in our testing environment, all trunked together, so 24 cameras in total.
    The Catalyst 2960 switches are trunking to a Core node, which consists of a pair of Catalyst 3750 switches with MHSRP configured for each of 8 VLANs, with 2 DCs and 2 Video storage servers for storing camera footage attached to access ports on those switches. We also have workstations attached to the core node switches which have software installed to view live images and manage the cameras across the network.
    We have no routing - the access switches have default gateways pointing to the VLANs SVIs configured on the core switch, and each function has its on VLAN. InterVLAN routing is enabled on the 3750s and connectivity is working fine.
    I wish to send a TCP stream to the Video Storage servers for storage, and to multicast to the workstations so that the software can see multiple streams from multiple cameras.
    Could someone please suggest a suitable deployment strategy, including how to configure the cameras and switches appropriately to allow this to happen? I am struggling to understand what type of configuration is required.
    Much appreciated. I'm actively viewing this thread for assistance.

    Paul
    I don't think IP Base supports any PIM mode other than PIM stub routing (unless you know otherwise) so your solution wouldn't work. Or perhaps i am not understanding ?
    Martin
    I think the only way forward is to test what we have already covered.
    I didn't realise this was a test environment so at least you can try all things out without worrying about the production network.
    The thread i linked to suggested that you can get the routing working even without a L3 device capable of running full multicast routing but at the moment the question concerns those extra commands you can't enter. Can you verify they are not available in config mode ?
    An additional problem is because PIM is passive on the SVIs no IGMP queries are being made so there is no way for the switches to work out which ports needs the multicast stream and so it will be flooded.
    There is a function, supported on the 3750s called the IGMP querier function which allows the switch to make IGMP queries per vlan without PIM enabled. We may be able to use this but i have absolutely no idea how it will work with the L3 multicast routing config.
    I recommend you try and get multicast routing working first. If you can get to the stgae where you can send a multicast stream from one vlan to another then you should be able to use wireshark to then see each port in the destination vlan receiving the stream (even when you don't want it to).
    If you can get to that stage we can then try the IGMP snooping querier to see if we can restrict the stream to only those ports that need to receive it. It may be we can't in which case -
    a) you could statically configure the multicast mac address to the relevant ports but this is no scalable and does not allow clients to dynamically join and leave the multicast group
    or
    b) simply allow the stream to be flooded to all ports within the destination vlan. Not ideal and kind of defeats the purpose of multicast but you may have no choice.
    I doubt whether any of this would be supported by Cisco though as i think their position would be to simply upgrade to an IP Services license although in understand this may not be possible for you because of cost.
    Jon

Maybe you are looking for

  • I need to install cc on two macs. My Macbook Pro and my Imac. Can I use the same account?

    I have two machines I use. One primarily for photography on the move and another for mostly Indesign work. Question is can I use the same account on both as it will never be simultaneous. Derek

  • Why does my Macbook Pro tell me that I only have 1GB of memory, when I have 2GB?

    Hello all, I'm a new user so forgive me if I'm asking something already asked. I'm looking to download OSX Lion on a 2010 Macbook Pro, 13 inch.  When I tried to download it, an error message came up saying that Lion needs 2GB of memory.  I checked "A

  • Mail configuration in GP

    Friends,      I am using EP 7.0 . I am trying to send mail from GP . There ther are three options to send a mail such as  Notification mail,Background mail and Send a mail.Here Send a mail is not working .When i try to send mail thru this option i sh

  • Eliminate the border

    hi,     In iframe control i am getting blinking text in that iframe control but the thing is in the output screen, box is coming in that box it displays html content i dont want that box it seems like input field . how it eliminates the box.         

  • Azure RMS

    Dear Sir, I got an experienced for the RMS with iPhone.  I have enrolled an account for RMS evaluation from aadrm portal.  I have registered two acounts for testing purpose.  First of all, I have download the apps from apple store and install it on m