Non-working day setting affects in MM

Hi,
in case Saturday and Sunday are defined as non-working days in factory calendar, what funtions are possible in MM on non-working days? Is it possible to perform physical inventory, create and post deliveries, create purchase orders and so on?
Br,
Tapio

done

Similar Messages

  • How to create orders and deliveries on Non-working day.

    Greeting all,
    We set up all our national holidays and Sundays as non-working day in our working calendar for Japan(OY05) .
    But I have a request from Sales Dept that only one customer wants us to deliver products on the holidays.
    We don't want to affect other customers delivery date so we are thinking we have to change the holiday to working day on the day before the holiday for the customer.
    But we need a complicated procedure to change the calendar in our company IT rule so I am wondering if there is any other good solution that we don't have to change the calendar so often.
    Does anybody have the same situation like this?
    I will appreciate any kind of suggestion.
    Thank you very much for your help in advance.
    Best regards,
    Miki

    George,
    I understand that is simple and correct procedure but I wanted to consider other possibilities to ship on non-working day because it is NOT working day here.
    Finally, our management have decided we don't change the calendar and ship with date the system proposes. They explained the customer and our distributor center that shipping date is one day ahead because of the calendar.
    To all,
    Thank you very much all of your advice.
    Best regards,
    Miki

  • Create absences on non-working days.

    Hello Time Gurus,
    I have a scenario in which the employees can record absences on a non-working day.
    The scenario is as follows-
    I have a Work Schedule -
    Sun(working) Sat(working) Mon(working) Tue(off) Wed(off) Thu(off) Fri(Working)
    The working days have a planned working hours of 9 hours and off day has planned working hours of 0 hours.
    I have two sets of employees (ESG) - Salaried and Hourly.
    The hourly employees should to be able to record absence on non-working day (non-working for me includes the public holidays as well).
    I have set the input checks for the absence type OFF on non-working day. I am able to record absence but with 0 absence hours, even though I input some absence hours...the absence hours turns zero because of the planned working hours maintained as zero on non-working day.
    How can I achieve this?
    Thanks & Regards, Swapnil Mishra

    Swapnil,
    How can I now configure so thet the hourly worker on non-working day...can record some absence...
    how will we overcome the planned working hours as zero abd convert the same to working using the sleection rules for daytype....
    I still don't understand why you want to put an absence on non working day.
    Suppose the first week of Jan is as below in period work schedule 01.01 to 07.01
    NORM NORM NORM NORM NORM OFF OFF
    NORM will have 8 working hours and OFF will have zero working hours. Suppose say that 03.01 is a public holiday.
    In DWS NORM planned hours will be 8 hours but still due to day type rules it will be a holiday(non working day) day type = 1
    So now 03, 06 and 07 are all non working days for both salaried and hourly class.
    Now do you want that for hourly employees these days should be considered as working? and the same days should be non working for salaried?
    AJ

  • Highlighted non-working days questions

    I have set up a calendar for a Project that has no non-working days (apart from holidays) and yet in the Gantt chart it will still show each Saturday and Sunday with the brown bars of a non-working day.  is there a way to get these to not display?
    the actual task does count the weekends as working days, this is just a superficial change I was wondering about.

    You can change the non-working time display to reflect the calendar assigned to the project.  
    Right click in a blank area of the Gantt Chart to show the shortcut menu.
    Select Nonworking Time... from the menu to show the Timescale dialog.
    On the Non-working time tab, select the appropriate calendar from the Calendar drop down.

  • Non working days in Deployment

    Hi all
    When running the deployment, system is proposing a non working date in the deployment order although a shipping calendar is assign to the location.
    Saturdays and Sundays are non working days in the shipping calendar.
    Does anybody knows how to fix this issue?
    thanks so much

    Hello,
    The problem should not be with deployment.
    Deployment only "confirms" the planned distribution demands created by heuristic (or other planning run).
    You must first make sure that there's no distribution demands created in non-working days by the planning run before deployment.
    Please make sure that you have set the calendars correctly and run the planning run again.
    Best Regards,
    Ada

  • HR-TM: Two Holiday Calendars That Have Different Non-working Days?

    Dear All,
    Please help me on the predicament below:
    I need to create two holiday calendars.
    Holiday Calendar 1 will have Saturday and Sunday as non-working days.
    Holiday Calendar 2 will have Friday and Saturday as non-working days.
    And both holiday calendars are used in the same country.
    Then, there is one holiday which is assigned to both holiday calendars such as New Year Day.
    How can I configure so that
    1) if New Year Day falls on the first non-working day of each week of each holiday calendar, the holiday will be moved to the previous day?
    2) if New Year Day falls on the second non-working day of each week of each holiday calendar, the holiday will be moved to the following day?
    Should I create two lines of data for New Year Day so that each of them assigned to different holiday calendar?
    Or I can just use one New Year Day in both holiday calendars?
    Thanks.

    I've got my answer.
    First calendar, i use fixed date and floating date for the public holiday based on the real situation.
    Second calendar, i use floating date for all the public holiday, then set the date every year once.

  • How to enter a Absence on a Non- working day?

    Hi All,
    In our company we dont have exact work schedule rules. So we have the need to be able to enter a Absence on a Non- working day for Salaried employees. when i try to enter an absencen on-working day, the number of hours are zeroed out.
    What configuration settings I need to do So that the system will take a Absence on a non working day.
    Thanks in Advance!!!

    Hello,
    I am having the same problem currently.
    When an absence that is less than one day is entered on a non-working day with a given start time and end time (we are using CATS for entering the times) along with some attendance records, there are collisions as the system tries to create the infotype 2001 record as a full day record, and the start time and end time is not taken into account, so we are not able to transfer these hours correctly to SAP HR.
    I checked all the settings regarding the day types, but could not find the trick..
    The days we are trying to create the absences and attendances for are not public holidays, just ordinary weekends with no working hours, so I don't think Holiday Class is relevant here at all.. 
    If anyone has a solution, please update the thread..
    Best regards,
    Nihan

  • How to create an absence on a non-working day?

    Hi HR experts,
    Is it possible to create an absence on a non working day or holiday? I tried to do so and I get all these information messages, until it finally saves. But it wont accept any number of Absence hours. Is there a way to allow it to accept 10 hours of absence for a holiday?
    I'd appreciate your insight, thanks in advance!

    hello annalyn,
    I think you have got 2 possibilites.
    you have to change the absence definitions for entering on free-days
    table: V_T554S
    are you using TM?
    if yes, you can change in a rule the working hours.
    or second solution would be changing T556C for this absence. also and this i have not tested changing the day type.
    regards
    Stefan

  • Planned orders scheduled on Non working days

    Hi,
           Planned orders scheduled on Non working days no Planning calnder assigned to the Material

    Hi
    Just go to transaction code MD26 and check the what calender is assigned to plant and validity period of the calender. If the calender is not valid in the MRP run period then also planning may differ
    Krishna

  • Team Calendar non-working days

    Hi Gurus,
    Is there a way we can configure the team calendar to show non-working days for the employee (public holidays, days off in part-time/shift work-schedules) in green for example?
    I haven't seen any configuration options for this, but I would expect it to show them somehow!?  Will we need to do custom development for this?
    Many thanks,
    Russell.

    Hi Russell,
    You can check this<a href="http://help.sap.com/saphelp_erp2005vp/helpdata/en/2f/d7844205625551e10000000a1550b0/frameset.htm">SAP Help</a> for additional info on the Team Calendar iView..
    ~Suresh
    Russell,
    I didn't think the "10 points offer" was open to all.. ideally, it should be to Duxton only.. You could probably open a customer message in OSS & seek SAP's clarification on Team Calendar
    Message was edited by: Suresh Datti

  • Factory Calendar to prevent delivery on a non-working day

    Hi Guys,
    You may have already come across this problem and hence requesting your inputs on the same.
    I'm able to create a delivery for a sales order on a week-end even though they happen to be 'non-working days' in my Factory Calendar. I have gone through the search forum and the 2 things that most of them said was to attach the Factory Calendar (having Sat and Sun as non-working days) to the Plant and Shipping Point, which I have already done, inspite of which I'm able to create a delivery for a schedule line date which falls on a non-working day.
    My business scenario requires that even though a Sales Order may be created on a non-working day, the delivery should only be possible on the next working day, even if stock is available on those non-working days.
    Your thoughts/suggestions/ideas would be useful.
    Regards,
    Shripad

    Hi Shripad,
    In Customer Master, General Data , We have  Unloading Points  Option. There we can opt for the delivery to the cutomer.
    Then we can stop delivery for that day.
    Award points if it adds information.
    Thanks
    Mohan

  • Non - working day problem

    Hi all,
    We can insert other type into non-working day by choose Input type W or I or null in T554S. But I can not insert the number of hours. So how to do?
    Thanks a lot,
    Quanglv,
    Edited by: Quang Le Vinh on Oct 9, 2009 11:44 AM

    done

  • Editing Working Days/Non Working Days in the base Project Calendar PWA

    Hello Experts,
    I am attempting to edit working days/non working days in the base project calendar PWA 13. I receive an error message when I attempt to open the base project schedule.
    I click the "edit" button under "Enterprise Calendars" page.  The error message states:
    "This Project Web App feature requires at least Microsoft Internet Explorer 8.0"  (using Chrome)
    Attempting to Opening PWA in I.E. I receive a different error message stating that I need Project Professional installed on my computer and it cannot find the current project.  
    I have Admin rights, I have project pro, and Im able to access any project or function using PWA and Project Pro. Can you tell me what I am missing (detailed steps--kinda new to PWA)
    Thanks so much.  

    If you allow me to jump in, I'd advice you to first open MS Project Pro and then try again.
    Also check that your MS Project Pro URL account do not finish with /default.aspx.
    Finally ensure that your PWA URL is in the trusted site and eventually add it to the compatibility sites.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • URGENT: Add Non-working day value to the next working day

    Hello expertz!
    I have a requirement were i need to shift the values of the non-working days to the next working day. The report allready works, showing only the values for the working days, but for example if i have the amount of 100 on 06.12.2009 (saturday) i want that this value is added to the amount of 09.12.2009, which is the next working day.
    Does anybody knows a solution to do this? Is this possible in BEx?
    Please advise if you think this is not possible.
    Thanks for the help.
    Nuno

    Hi Anil,
    I really appreciate your suggestion, but i'm still not getting the point. How to store the value of the non-working day in a variable and then add it where? Can you please clarify?
    Thank you very much for your help.
    Nuno

  • NON-WORKING DAYS

    Hi Gurus
    when SD and MM persons are doing their transaction on non working days (Sundays & public holidays).the system should restrict the posting.what i need to do if any configuration left pl z help me to restrict.
    Thank 's
    With Regards

    Dear Experts,
    I am also facing the same problem.  I have done all the necessary configuration settings in public holiday calendar and factory calendar. But when MM people are trying to raise a purchase order and do goods receipt on a non working day, the system is allowing them to do so, and even not showing any warning message and the same problem exists with SD people when they do any sales and deliver goods on a non working day.
    What additional settings should I do in order to make the system to throw an warning message atleast.
    Thanks & Regards
    Shankar

Maybe you are looking for

  • Problem creating Purchase Order with Bapi_po_create  Return Message is ""

    Hello everybody When I get to create PO with bapi_po_create . I get this message in the return parameter :"Enter the PURCH_ORG". I think that I have implemented it very well but I don´t get the results that I was expected : No PO was created. Please

  • Adobe Acrobat Standard and Pro - dialog prompt when opening PDF from Internet Explorer 9

    Good morning. I am having an issue where our ends users that have either Adobe Acrobat X Standard (AAXS) or Adobe Acrobat X Pro (AAXP) cannot open a PDF within Internet Explorer 9 without being prompted by a dialog box to OPEN, SAVE or SAVE AS. Our u

  • Proxy to file scenario issue

    Hi, I am trying to configure a Proxy to file scenario. My sender service is ERP system and the my receiver is PI file system. These are the steps I followed: 1. Created a sender business system for Web AS abap (my ERP system) 2. Created a receiver bu

  • Query on Blanket Purchase Agreement--  Lines Agreement

    Hi friends, I have a query on Blanket purchase agreement.When a minimum release amount is provided in the Terms >Agreement controls it is holding fine and taking that value perfectly for each release. But when in the PO Lines,under the Agreement when

  • How a time entry rules based on mapping works?

    Thanks a lot in advance for your help. I need to understand a seeded time entry rule Overlapping Time Entries. it looks like this: Name: Overlapping Time Entries Description: Seeded Overlapping Time Entries Usage: Submission / Resubmission / Delete F