Non-working time for particular resources

I have reviewed the suggested answers and they don't seem to fit my case.   Project 2013 Pro.
I have a particular resource who takes three days off. These days occur in the middle of an 8 day task, fixed duration, on which he is only working 20%. He has his own calendar to deliver this information and I have checked that the days off display in Resource
Sheet/Resource Information  for that person.  The fact that he takes off three days is not shown by the bar in Gantt view. (standard time off is set to 'behind task bars'). 
If I temporarily change his commitment to 100%, the calculated hours in the task form are 40, showing that the software is recognising his time off, since otherwise it would be 8x8=64. The gap in his work time still doesn't show.  
Is there a way to show the gap so that I know (well, remember) he is not around for those three days?
Cheers
Alan 

TeamPlanner view shows the resource's nonworking time as it is seen below: 

Similar Messages

  • Displaying Non-Work time for all resources via a Calendar?

    I am looking for a way to display a calendar or a view of all resources that will show the planned vacation time for each resource based on the "non-work time" set in each resource calendar.

    Hi,
    As workaround solution, through P6 professional you can create a report with choosing
    "Resources" as subject Area and selecting "Time Distributed Data" option and,
    At "Time Intervals Field" you can select "Limit" to be distributed.
    This will give you a tabular report showing resource limit over selected period with selected intervals.
    Regards,
    Marcos

  • Note 403102 - Offset takes non-working time of resource into account

    Hello Friends,
    I have implemented the OSS notes 403102 for considering the offset value without considerding the non working time of the resource in APO system.
    but as i have implemented the sample code given there(copy & Paste) the functionality seems to be not working.
    the productive hours maintained in the transaction /SAPAPO/RES01 is 8.5 hrs.
    previously the system was considering the productive hours as 24 and was calculating.
    after implementation of the notes if I specify a 4 days offset iam getting 3.5 days offset .  for 6 days its 5 days offset.
    does anyone faced this issue.
    Any help will be highly appreciated.
    if u any code modification u can mail to me at [email protected]
    Thanx & Regards,
    Mahadev Shetty.

    Hi Rob,
    The msg was provided by SAP, but i am unable to correlate the exact code that i have to write.
    any ways thanx for the reply
    Mahadev.

  • 403102 - Offset takes non-working time of resource into account (OSS notes)

    Hello Friends,
    I have implemented the OSS notes 403102 for considering the offset value without considerding the non working time of the resource.
    but as i have implemented the sample code given there(copy & Paste) the functionality seems to be not working.
    the productive hours maintained in the transaction /SAPAPO/RES01 is 8.5 hrs.
    previously the system was considering the productive hours as 24 and was calculating.
    after implementation of the notes if I specify a 4 days offset iam getting 3.5 days offset .  for 6 days its 5 days offset.
    does anyone faced this issue.
    Any help will be highly appreciated.
    if u any code modification u can mail to me at [email protected]
    Thanx & Regards,
    Mahadev Shetty.

    thanx got the solution thru config change

  • Non working times report in pwa 2010

    how can I report out non working time for resources?

    See this similar
    post for a code oriented solution for resources.
    This
    post gives a similar code for project exceptions.
    Otherwise, select Reports | Assignment | Who Does What, edit the Report, and then within the Details Tab, select Calendar under the resource column.  It will list each resource's calendar and non working time. See reference
    here.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • How to forward support messages to SAP in non-working time automatically?

    Hi colleagues and Happy New Year!
    I have a question: how to forward support messages to SAP at non-working time automatically?
    Details:
    when a support message is created at working time it shouldn't leave my system, but when
    a support message is created at non working time, for example, on saturday night it should be sent to SAP automatically. Where in the system I can find the options to customize it to provide these requirements?
    Edited by: Helen Rudnikovskaja on Jan 3, 2009 12:36 PM

    Hi These 2 notes wil solve your problem,
    Note 1084744 - Problems with the automatic function "Send to SAP"
    Note 1225682
    Pls assign pts.

  • Hiding non-working time in Team Planner View

    Hello there.  The tasks in my project are typically between 2-5 hours over a week period.  In Team Planner View, I'm hoping to provide a better representation of free time between tasks by making my bottom tier hours in a 4 hour count.  However,
    decreasing the scale forces the Task names become cut off when the event itself shrinks.
    I was hoping to remove the non-working time (i.e., nights and weekends) from the Team Planner view to enable a better view.  I'm aware that the capabilities of Team Planner View seem to be limited, but is this type of formatting at all possible?
    Thanks for the help,
    Joe

    Joe --
    After I created my response and posted it, I wondered whether you wanted to completely remove the nonworking time periods.  This is not possible.  The best you can do is to remove the shading for nonworking time periods, but you cannot remove them
    entirely in any view.  Hope this helps.
    Dale A. Howard [MVP]

  • Non- Working Time

    In sap when i am trying to create a/p invoice based on a grpo and the posting date and due date is 06/01/08 (which is sunday) the system throws following prompt" 06/01/08 is defined as non- working time? continue. yes,no.". The calender defined for the company in the system is of yr 2006 and weekend as saturday to sunday.
    -"Valid for one yr only" box is selected
    -"Ignore weekends for payments" is NOT selected
    Also system never threw this msg when i created a po and grpo.
    please let me know why the system has thrown this prompt.

    Hi Kapil,
    The solution to this problem lies in the fact that you must have mentioned the Payment Date in the BP master data for the vendor......this window is appearing in the Payment Terms Tab in the BP master Data below Holidays.
    Use the window to define the days each month in which your customer usually pays the open invoices, or the days each month that your company pays its vendors.
    Example
    When 10 and 20 are defined in the Payment Dates window for a certain customer, the invoice due dates are calculated as follows:
    ·        If the posting date is between the 1st and the 10th of a certain month the due date of the invoice is the 10th of that same month.
    ·        If the posting date is between the 10th and the 20th of a certain month the due date of the invoice is the 20th of that same month.
    ·        If the posting date is after the 21st of a certain month the due date of the invoice will be the 10th of the next month
    Hope this helps.....reward points if helpful
    Nagesh

  • Scheduling changeover times in non working times

    PP/DS heuristics and or the PP/DS optimiser will not automatically place changeover times in non working times, however other smaller APS systems have such functionality. Has anyone come across this or have a method to use to get APO to do this? May be it should be a new development?

    Hi Thomas,
    Thanks for your reply. Yes i am aware of this setting - this is the standard approach, however do you know of a way automatically (heuristic or optimiser) schedule the set up segment of an order into non working times whilst keeping the produce section in productive time? I know you can amend the strategy and use that in the heuristic but it will schedule all parts of the order in the non working time if it can.
    Thanks
    Fred

  • Adobe PDF won't print non-working time colour in MS Project

    Adobe PDF won't print the colour chosen for non-working times in MS Project.  I have tried changing the colour, changing the style, moving non-working time in front of tasks and have fiddled with the printer properties, all to no avail.  It ignores whatever style I have for non-working time and makes a blank space, although it will take gridline changes . . . . please help!
    Shevaun

    Thank you for providing the suggestion and the Cleanup tools, however they did not help.
    I ran each version of the cleanup tool, and for each I had it clean up Reader and Acrobat (i.e. 4 separate cleanup operations).  I then rebooted the machine, and installed Reader 11.0.3.
    Still had the same behavior:  Reader will not print.  I tried printing to a second printer (that is attached via USB)...and it did not work either.  I also tried printing to a Cute PDF Writer print driver...and that did not work either.  In each case, no print data made it to the Windows print queue (as demonstrated by watching the queue while printing.)  No error was raised, but no print data was transmitted.
    I then uninstalled Reader 11.0.3, rebooted, and re-installed Reader 9:  printing works fine now.
    There is definitely something in Reader 10 and Reader 11 that breaks printing in some environments.    (As you alluded to...I have seen a number of postings online about printing problems in Reader.)
    More details about my environment:
    Windows 7 Professional N (Version 6.1, Build 7601: Service Pack 1)
    VMWare virtual machine
    Two virtual CPUs (each: Intel Core i7 920 @ 2.67 GHz, 2673 Mhz, 1 core, 1 Logicial Processor)
    Hardware Abstraction Layer:  6.1.7601.17514
    RAM:  3096 (allocated to virtual machine)
    Bridged networking
    VMware host:
    Windows 7 Ultimate, 64-bit 6.1.7601, Service Pack 1
    18 Gig RAM
    Intel Core i7 CPU 920 @2.67 GHz
    VMWare Workstation 9.0.2 build-1031769
    (but problem existed on older version of VMWare Workstation 7.x as well)

  • System Message "Define as non Working time"

    This System Message will Poup before Each A/P invoice,when i going to post it
    "23/05/09 is defined as non-working time. Continue?"

    Please check this thread:
    Non- Working Time
    Thanks,
    Gordon

  • Available working time for setup and produce activity is not the same.

    Hi,
    For some resources, there are certain setups which require high skilled operators that work less time that the machine. In the setup matrix these setups are recognized because they take much longer than the normal setups.
    How can I control that no setups with special operators are planned outside operators working time?
    Let s say the machines work along the 3 day shifts and the setup operators only one shift per day.
    I thought to use a secondary resource in the setup phase activity or adding a phase with the opertors modeled as a resource to the operation. It adds complexity to a solution the fact that setup times depend upon the setup matrix assigned to the resource so they are variable!
    First option was not good because secondary resource cannot present relationship start-start and end-end with the primary resource, moreover, which lead time do we enter in the secondary resource?
    Second option was not good either because setup times are variable for all the "special" resources and all of them use the same operators.
    CTF

    Try mapping the scenario with sub operations and assign the highly skilled labor to the sub operation and machine  to the main operations.
    Rgs - Vikas

  • Cisco ISE: Non-complaint Timer for Users

    Dear Folks,
    What is the time for the non-complaint user state? How long a user stays in non-complaint state? and how to change the time?
    Kindly respond fast.
    Thanks,
    Regards,
    Mubasher

    Posture Compliance Dashlet
    The Posture Compliance dashlet summarizes the posture compliance in percentage, and Mean Time To Remediate (MTTR) data for the last 24 hour period, as well as 60 minutes from the current system time. It refreshes data every minute and displays it on the dashlet. You can invoke the Posture Detail Assessment report from the tool tips that are displayed on the 24 hour and 60 minutes spark lines for a specific period. The stack bars display the posture noncompliance distribution of endpoints by operating systems and the reason for failures of the requirements.
    The MAC address is used as a key to calculate MTTR.
    The dashlet provides you the following distribution details for the last 24 hour period, as well as 60 minutes from the current system time.
    Posture   Compliance Dash let 
    Name
    Description
    Passed in percentage
    Displays the percentage (passed   percentage) of posture compliance of endpoints by using posture compliance   and noncompliance of endpoints.
    Mean Time to Remediate (MTTR)
    Displays the mean time difference   between endpoints moving from the noncompliant state to the complaint state   based on the unique MAC address.
    Operating System
    Displays the noncompliance   distribution by operating system that is running on the client.
    Reason
    Displays the noncompliance   distribution by failures of posture conditions.
    Please check the below link for configuration:
    http://www.cisco.com/en/US/docs/security/ise/1.0/user_guide/ise10_pos_pol.html

  • Creative X-Mod Volume Knob Doesn't Work *Time for Creative to fix th

    Just bought a Creative X-Mod and it works well except one thing.
    When I turn the Volumeknob the volume doesn't go up and down, neither does it Mute when I press it. Everything else seems to be working with it so I can't figure out whats wrong.
    . Have tested on my laptop too and there it works.
    2. Have updated everything, including motherboard drivers.
    3. Have searched the forums and there are some threads about this problem but no solution.
    4. Have tried diffrent USB ports.
    So whats wrong? Seems like it's time for a solution to be honest.
    Regards
    Jacob

    Bump and update.
    Have now pretty much gone through every USB port and all drivers which could have any impact on the X-mod. Nothing.
    Creative Support seems to know nothing as well.
    The one guy on the forums who claimed to have a fix doesn't answer PMs.
    If Creative doesn't get on top of this it's going back to the store.

  • Implementing work time for shipping points

    Hi,
      I was trying to implement work hours for shipping points and has come across a weird issue. Once I define working shifts , the calculated PGI date is one day early,
    Example:
    Without work shifts for shipping point
    Customer requested date - 08/26/2011
    Route -2 day truck
    No pick pack /loading time
    I get a PGI date of 08/24
    Work shift of 06:00 to 14 :00 hrs defined for shipping point, everything else remains the same:
    I get a PGI date of 08/23 , 14: 00 Hrs.
    The users are not happy with this; does anyone have a clue as to why SAP behaves in this manner and what is the business reason behind this calculation ?
    Thanks,
    Hari.

    HI,
    It basically depends on the working times, shifts and factory calendar.
    If your PGI falls on a Sat or Sun then SAP would calculate the PGI date on the subsequent working day.
    Regards,
    Amit

Maybe you are looking for