Not scheduling on manual creation of planned order

Creating planned order through MD11 and noticed there scheduling not done and capacity planning not done and on doing scheduling manually dates altered and capacity planned which are appearing in CM01 for the respective week
Planned order created through MRP are fine with scheduling an capacity planning .
Please let us know what could be a reason for not updating on manual creation.

Hi
This is standard behavior of SAP as when you create the planned order through MD11 manually , you need to do the detailed scheduling manually by executing schedule in Edit>Schedule.
Check this thread:
Need Automatic Lead-time scheduling in Planned Order using MD11
Regards,
Anupam Sharma

Similar Messages

  • Manual creation of planned order in REM

    Hi, 
    Can we manually create a planned order in repetitive manufacturing? I know that in case we run MRP , then planned order for finished is created with order type 'PE' due to which it cannot be converted to production order.
    I dont want to run MRP , still can i create a planned order manually with the same order type 'PE' ? I tried in MD11, but not getting option to chose PE as it is not available  in F4 of planned order profile.
    Please help..
    Regards.

    Dear,
    You cannot create a planned order with PE order type manually, because a planned order of REM related material gets order type "PE" only when it is assigned with a Production Version.
    So achieve manual creation of REM Planned order with PE type with the following options,
    I - Using MD11 transaction create a planned order with LA type and assign a suitable REM related Production version to the planned order during creation itself, now this order would automatically become "PE" order type on saving the order.
    2. In the planning table using MF50, you can directly create a planned order for a production line using F7 key.
    Regards,
    Prasobh

  • Source determination not happening during PR creation from Planned order

    Hi Experts
    We have set up source determination and we have created a sourcelist of material and a vendor is fixed, there is a inforecord alos maintined,
    I am trying to convert a planned order from MD04 to a purchase requisition, the source is not being assigned for the PR, I am alos getting an  information saying that 'the material is defined for inhouse production'
    secondly if I click the 'Assign Source of Supply', then I am getting an error 'not possible to assign  a source of supply'.
    The material is a finished material 'FERT' with procurement key 'X' so in MRP an planned order gets generated for converting a PR or a production order.
    Note - I was doing this effectively in a differnt client without any proble.  I am unable to find what I am missing, please sugest.

    Nagaraj Chaganti wrote:
    Thank you everyone for the suggestions,  The issue is resolved by testing with a new material with tproper master data.  Basically the problem occured when some user created additional inforecord for the same P,Org hence there was no automatic source detemination happening.
    >
    > Bye with regards.
    a second info record may explain that AUTOMATIC source determination ddid not work but it does not explain the error messagees you described earlier.

  • Manual creation of planned order(PE) ??

    hi ,
    whenever i creating planned order manually for REm assembly(md11), system automatically taken PE order type.
    where configure setting is there for this automatic action????

    Hi,
    It happens , when the foll setting is defined in material master MRP 4 view.
    BOM Explosion
    Selection method : 2 By production version
    When you create a planned order for the same assembly , after changing the above setting to blank ., ie
    BOM Explosion
    Selection method : Blank Selection by ord qty , then the planned order's order type will be LA.
    pls check.
    Regards,
    Sheik

  • Automatic Creation of Planned Order in PPDS Horizon

    Dear Experts,
    Kindly answer my following query.
    I have created PIRs before/inside my PPDS Horizon (its also falling outside horizon as SNP horizon is shorter than PPDS Horizon). If I check the PIRs created by me in /SNPAPO/RRP3, it also shows me planned orders corresponding to them. However, if I create PIR outside PPDS horizon then system is not automatically creating the planned order.
    Kindly let me know which master data/configuration setting is responsible for automatic creation of planned orders within PPDS horizon.
    Best Regards
    Rinju
    Edited by: Rinju Mukherjee on Sep 26, 2010 10:05 AM

    Dear Rinju,
    Check in Product Master PPDS view the Planning procedure maintained? if it is balnk check in the heuristic, the palnning procedure maintained.
    Since automatic planning procedure(3) is maintained, that is the reason it is creating order proposals, it self.
    Sree

  • Block the creation of planned order

    Dear experts
    How can I control the creation of planned order? I want to block the creation of planned order if the BOM or routing is not exist.
    BRs

    Hi,
    I think this can be done using 'Material status' try the following and let me know if it works.
    Create a new material status in transaction OMS4 (like R1 - "Created but BOM and Routing not maintained" )and in the details screen select Option "B" for MRP messages.
    You designate a material as a "R1 -Created but BOM and Routing not maintained" In the master record.
        MRP                          "B" = warning
    Please try this and let me know the result.   
    Regards,
    Prakash

  • Manual cration on planned order in Planning w/o Final Assly segment

    Hello everyone,
    Is there any way to change/create SNP planned orders manually in SNP Planning book or product view in Planning w/o final assly segment.
    I am not able to create manual order in RRP3 view in Planning w/o final assly segment. It is giving below error.
    Note: I am able to create planned order in MTS segment.
    I am not sure whether SAP has purposfully not given this functionality. However, I believe user should able to create/change planned order in planning w/o final assly segment.
    Regards,
    Abhay

    Hi,
    If the planning strategy is Make to order, planned orders should not be created manually in RRP3 view and it comes from sales order only.
    Regards,
    LV

  • Mass creation of planned order

    Hello,
    is there a way to mass creat a planned order for a finished product? having same FG mat, plant and prod version.
    Thanks

    Dear
    1.Goto MD61 with User parameters like Plant , Requirement type , Version and Planning Date .Then Select the Material Radio Buttion with FG item code .
    2.Enter the FG qty as required in each month as demand
    3.GotO MD02-Single Item ,Multi Level with indicator : NETCH , 2,1,3,3,2   and Execute the MRP to create the Planned order  for FG
    4.Check the result in MD04
    There is no SAP Standard Traction to Mass creation of  Planned Order .That is possible in Demand Creation and MRP run .
    Regards
    JH

  • Check on Manual creation of PM order

    Hi,
         I have a business requirement that the manual creation of a particular order type should be stopped i.e. when i am going to create that order type through IW31 or the generation of that order type even through a notification should not be possible.The  system should not allow that.Pls. reply.
    Edited by: ind kumar on Aug 4, 2011 3:07 PM

    Hi
    Please use the user exit IWO10009.
    we can add the condition that the field "Order Category Indicator Plant Maintenance"-AFIH-AKKNZ has below values, you can restrict them to create manualy.
    "Category
    AFIH-AKKNZ"     Short Descript.
    blank     Order created online
    1     Order created historically
    2     Order created subsequently
    3     Order from notification
    4     Order from maintenance plan
    5     Order from reference
    6     Follow-up order
    7     Generated order from IM_SM_CREATE_ORDER
    8     Order for an SD service item
    9     Order for an SD repair item (RMA)

  • Setting nedded for creation of Planned Order for Dependent Requirement.

    Hi PP Gurus,
    I have a one material for which I m running MRP which have three Components.
    I m using strategy 10 for FG and SFG also.
    When I m running MRP for FG the system is creation planned order for FG, but not for SFG even though no stock available for them.
    I m using lot size EX for all SFG.
    Please Help.
    Thanks in Advance.

    Dear ,
    You should maintain proper MRP related parameters for both FG and SFG.Check all the MMR parameters :
    1.MRP Type -PD for FG/SFG
    2.Procurement Type -E  for FG/SFG
    3.Planning Startegy -10  in FG
    4.BOM/Routing Explosion -Keep it Blank
    5.Indiviaul/Collective Indicator -not applicable as it is MTS  so keep it blank
    6.Validity of BOM /Routing should be corrcet before MRP run in MD02-NETCH , 2,1,3,3,2
    7.What is the Lot Sizing Set up-EX in OMI4-Scheduling Tab -Requirement date =Delievery Date and BOM Validity Date  .
    Ref .Re: MRP not plalned for dependent components
    8.Check in MRP4 -MRP Dept Requirement Parametre should be balnk for plalling the SFG  in MMR of FG -MM02
    I hope this issue may be with BOM explosion as per the validity and lot size -schedueling set up .
    Hope this will be useful
    Regards
    JH

  • Issue in creation of Planned Order

    Hi all,
    There is a customer requirement on 08.02.2010 and there is shortage quantity as we don't have enough stock in the warehouse to cover the cust req. So when I run the MRP, planned orders are not getting created on 8th. Can you please tell me what could be the reason?
    Regards,
    Brijesh

    Hi,
    Are you saying that the planned order is not getting created at all or is it being created for an earlier date?
    If it is not being created at all, check in your sales order, whether the schedule line category is CP i.e. MRP relevant & in MD04 you notice the demand. Also check if the material is MRP planned & has a planning file entry (check using MD21, if no entry, make an entry via MD20).
    If it is being created, but at an earlier date, then check the lot sizing procedure. It could be that the lot sizing procedure is weekly or monthly & system has combined the needs & put a supply proposal at an earlier date.
    Check the above & revert with additional info if it does not resolve the issue.
    Regards,
    Vivek

  • APO: RRP3 automate Production order creation from planned order ?

    Hi everyone ,
    I have got a business requirement in APO where in Open sale orders uploaded in R/3, needs to be converted to Planned order and subsequently to Production order in APO-PPDS tcode RRP3 at all stages. They want to automate this process rather than doing it
    manually.
    Can anyone tell how is this possible . Any BAPI or function module available to do this . Please help.
    Regards,
    Syed

    Hi,
    1.You need to run the heuristics Planning of standard lots SAP_PP_002  in /SAPAPO/CDPSB0 by specifying the time profile
       and  strategy profile, planning version and propagation range, product and location.
    2. Convert PPDS Planned Orders created to process orders thru /SAPAPO/RRP7 by specifying the product location start date of the order for production order creation.
    Out put of step 1- For sales order requirement, PPDS Planned orders gets created.
    Out put of step 2- PPDS Planned orders are converted to production orders.
    Thanks,
    nandha

  • How to find out manual deletion of planned orders in APO.

    Planned orders are created on multiple bom levels when we call CTP from GATP for sales orders. For particular sales order there is no planned ordere at lower level. Dependent requirement is there which is uncovered.
    I want to find  somebody has deleted this planned order manually in apo. How to find out the same?
    Regards,
    Santosh

    Hi Santosh,
    If you suspect that the planned order was created but later on deleted manually, there is a cross check you can do to determine that.
    In case of MATP, System uses the higher level Planned Order number to create the Dependent Demand at the lower level and only when this dependent demand is covered by a planned order it assigns the corresponding planned order number to it. So if you see the dependent demand number with same  number as the higher level planned order for which it was created, you can be sure that a planned order was not created to cover the dependent demand that you see uncovered.
    If the dependant demand number is not same as the planned order at higher level, then the planned order to cover the dependent demand was deleted.
    I guess CTP also works the same way. If you're unsure about this, test it out.
    Hope it helps.
    Regards,
    Mohan

  • Unit of measure - rounding off during creation of planned order

    Dear All,
    We have defined one material OIL in MM41 and its UoM is EA also we have put alternative UoM is L(liter).
    now we create BOM of semifinished material we use this oil as a component and enter its value in decimal points.
    e.g 0.375 EA
    During planned order creation or REM backflush system convert this quantity to 1 EA ,WE dont want this automatic conversion .
    We have uploaded all master data in production and now it is very difficult to change all BOM
    So what is the solution of this that system can not convert qty (rounding off).EA
    Kindly reply
    Sunil

    Hi Sunil,
    IN CUNI Transaction Field Decimal Places is for displaying the decimals,there is a decimal place Rounding off field below,there try to maintain 3 decimals and check whether it is working.
    One more thing is Unit EA will be used always as non decimal unit,But i dont know in your buisness how for unit EA there is a decimal qty
    Edited by: Girish  Adaviswamy on Mar 2, 2010 10:59 AM

  • Automatic creation of Planned order

    Hi,
    Would like to know how to check if a certain material is set up in MRP to automatically create planned orders or should be cretead manually.  I have verified the material type and the value is already PD (Material requirements planning).
    Thanks,
    Lyncel

    Hi,
    Based on the MRP types sytem will creates Planned Order automatically  when u run the MRP Run.
    MRP type can be  PD,VB...etc .  if it is ND  MRP will not create planned order.
    Even though u have selected the MRP type PD, based on the Planning file entry system  will include the Material in Planning Run and creates Planned order.(Md22)
    Letus explain your problem sothat help further.
    Pradeep

Maybe you are looking for

  • How To create ADF Search form in JDeveloper 11g 11.1.1.0.1

    Hi, I am using JDeveloper 11g 11.1.1.0.1 , in which i tried creating an ADF search form that has Find and Execute Buttons. I created the same ADF search form using JDeveloper 11g TP3 and TP4 wherein it works fine but not in JDeveloper 11g 11.1.1.0.1.

  • Finished sequences is wrong timebase, cant copy paste into new sequence

    I am coming onto a project finishing it for a first time editor and he cut 23.97 footage in a 29.99 seq, there are many time effects etc. I tried copy/pasting into a new seq but everything ends up in different places. I cant change my seq settings as

  • Music not playing in itunes

    Recently some of the songs I have in iTunes won't play anymore. Whenever I click on a song to play it says it can't find it even though I have it saved in my library. I get a little exclamation in a circle when it won't play. I have to manually find

  • Can we directly install windows 8.1 without installing windows 8

    can we directly install windows 8.1 without installing windows 8? Or how to install windows 8 in bootcamp using a USB drive?

  • How to reset PREPARE

    Hi all, Please ignore the post i have sent earlier... We had a major change in the things we thought. We are upgrading our BW 3.5 system to BI 7.0 (Linux RHEL 4, oracle 10.2) ,we also planned to go for unicode conversion, but after successfully runni