Not to reschedule in the MRP run.

Hello!
I have product   P000GR00000000  consisting a
component say B000GR00000000 .
               If i create production order of P000GR00000000 for DATED 30.09.2007 of 100 EA.then order will reserved -100EA for B000GR00000000 & when i take MRP run it will generare plan order of 100 EA for B000GR00000000.Similarly if i create production order for P000GR00000000  for dated 30.10.2007 of 200EA.Then MRP run will generate 200EA plan order for B000GR00000000.
      Now, i create production order for P000GR00000000 of 300 EA for dated 30.11.2007 & meanwhile the production order of P000GR00000000  DATED 30.09.2007 is technically completed then order reserved for B000GR00000000 of -100EA will be cancelled.If i take MRP run now ,then order reserved of -300 EA for B000GR00000000 will rescheduled,that i want to restrict.
   Is there any solution Not to reschedule in the MRP run if order is TECO.
please give the solution.
regards,
mangesh

Hi Mangesh
  You can define Rescheduling at plant level or MRP group level using OPPQ/ OPPR or OMDW. if you define at plant level then no need to create in MRP group and assign to material
secodly if you want to avaoid the Reschedule Exceptions then
You can  define tolerance values in additon to Resheduling horizon. for the creation of exception messages, in Customizing. These values define a time period in which no exception message is to be created, despite the fact that a rescheduling proposal may exist.
If you don't want reschedule check for production orders then you can remove the flag against production orders in the firmed elements.
if you TECO the order Normally MRP should not consider while planning!
please check onesecond and come back
But Teco will allow  you for posting (GR/GI)
hope this helps
BR
SK

Similar Messages

  • Open Purchase Orders not considered as requirement for MRP Run

    Hi ,
    We are facing a issue of Open Purchase orders not appeared in Stock requirements list and also it is not considered as requirement for MRP Run against reservation.
    As aresult for a reservation demand of 10 units we are ending with Open POs 10 units and a additional planned order 10 units.
    Material Type : ERSA
    MRP Type : PD (or VB)
    Lot size : EX (  HB if MRP Type is VB)
    Could you please throw some light to correct our settings to MRP to consider Open POs?
    Saravanan

    Can you check to see if there is a re-order point set up for this materia? That could be causing the problem too.

  • Production orders not to be considered during MRP run

    Dear SAPeers,
    i want to know how to ensure that open production orders are not considered during the MRP run.
    the following is the scenario.
    PIR for march after MRP run creates a planned order. this planned order is converted to production order. now this production order is processed but not completely confirmed and TECOed after a certain quantity has been produced.
    now we delete the old PIR and create a new PIR in the next month. now we revoke the TECO status of the production order and run MRP. I want to know how to avoid MRP from considering the open production order and create planned order for the complete PIR quantity.
    Thanks and Regards
    Srinivasan

    Srini,
    what i am worried is shortfall of raw materials in case they were to open the production order in the current month after the planning has been done. how do we allocate raw materials for both the plan as well as the open production order?
    Okay, you presumably had RM available for all of your production orders (and those RM were balanced by the reservations from the production orders).  Now, you TECO the production order.  In effect, any un-issued RM are now released and freely available for other orders/planned orders.  Now you plan the following month.  Those RM that were freed can and will be used for the new plan.  Odd business process, but OK.  Now, you re-open the production orders, and, yes, you will have a shortage unless you run RM MRP again.  This is, ah, inconsistent with any business process I have ever seen.
    The question that jumps to mind is, "Why re-open the old production orders at all?  Alternatively, why were they TECOd in the first place?"  If one knows that he intends to complete an order in production, one does not normally TECO the order, and then later reverse the TECO.
    With respect to my name, I must unfortunately keep a low profile.  Ever since I escaped from the mental institution, the thought-police have been hunting for me. I do not wish to be the recipient of any further electroshock 'treatments'.
    Rgds,
    DB49

  • Schedule lines are not coming for HALB after MRP run

    Dear All,
    I am not getting schedule line after mrp run, inspite of all required setting only purchase requisitions are coming.
    Material type is HALB and involve a subcontracting process (30). For raw material I am getting the schedule line but in the case of HALB, it is not coming.
    Pls let me know if I am missing something and guide me further on this.
    Thanks & Regards
    Kundan Kumar

    Hi,
    In transaction OMDT you have to enable the indicator create schedule lines
    In MD02 MRP control Prameter here select the Delivery schedules -3- Schedule line. Processing Key as NETCH and Planning Mode - 3 delted and recreated.
    Maintain source list ME01, in that put MRP indicator as '2' i.e. schedule lines via MRP.Put your agreement no in that.
    If u run MRP properly u will get schedule lines automatically in ME38.
    Make the schedule agreement, make it source relevent in the source list make is FIX and MRP indicator as 3.

  • Scheduling the MRP run

    I have configured in the system for a Re-order point planning MRP run. But I have to execute the MRP run manually through MD03 transaction. Is it possible to schedule it ,eans system will execute MRP run automatically at a scheduled day of a month?
    Please advice.
    Thanks
    Satya
    Edited by: Csaba Szommer on Aug 18, 2011 12:51 PM

    hi,
    I don't see any direct solution for it...
    but indirectly,
    Try to remove the line item ie. source from the source ...and try again...
    its not possible to do via changing the dates...nor any source doc...system still create the procurment...
    also try via changing the MRP indicator in the source list to NO MRP...
    let me know updates..
    Regards
    Priyanka.P

  • STO Not to be considered in MRP Run in MTS

    Dear All,
    We are facing the following problem in MRP run in MTS scenario when
    there are STOs in Plant.
    We have 2 Plants one is production Plant (Say A) and other is Non
    production Plant (Say B) from where only Deliveries will be made.
    Now after final material will be produced in Plant A it will be routed
    through Stock transport order (STO) to plant B.
    So there will be always STOs in Plant A which will be created in Plant B.
    Now we are using Strategy 11 (Gross req. Planning) for Final FERT material.
    In MRP if we have PIR of 100 Qty. and STO of 50 Qty. system is creating
    the Planned order of 150 quantity which is a normal system behavior.
    Now our requirement is that it should not include STO in Planning (MRP Run).
    Pls. Suggest.
    Regards,
    Vinayak.

    Hi,
    Go to OPJJ,
    In that select your requirement type, and click details...
    there is a tab,IN/OUTward movement.. In that deselect the box for incl.rel.order.reqs..
    If you dont want the deliveries to be taken into consideration, then uncheck thebox for include deliveries..
    hope this solves..
    karthick

  • AFS ARun: sales order not been selected for the allocation run.

    Hi,
    I am setting up the Purchase-to-Order (similar to Indiv PO item sales order) Process for SAP AFS.
    When doing the Allocation Run (trx J3AT) after Goods receipt of Sales order stock, I get an error that ARun terminated because no requirements were selected. The delivery check report (/AFS/LIEF_CHECK) indicates that the sales order has not been selected for the allocation run.
    For this process, I have set-up an Allocation type with
    1.     Requirement selection that does not exclude MTO/PTO orders
    2.     Set-up stock selection which includes physical stock type for MTO/PTO orders to the customer special stock MSKA with the segment KALAB.
    Can someone suggest what I may have missed?
    Regards,
    PD

    Hi Pankaj, I have same exact issue. How did you fix this ?
    Thanks,
    Mahesh

  • Viewing the mrp run output based on mrp groups

    Hi, please advise how to view the mrp run result based on mrp groups? also advise how to run mrp on the basis of mrp groups?
    thanks.

    Hi,
    Can you use MRP Controller instead MRP Group. Because you have option to view MRP result by MRP Controller in MD05.
    And you can execute MRP based on MRP Contoller by using user exit M61X0001 in MD01.
    Regards,
    Vishal

  • Exclude storage locations from the MRP run

    Hi all,
    Is it possible to exclude stock of specific storage location from the MRP run?
    Thanks for your help
    Thomas

    Hi,
    2 things,
    1. In OMIR for the storage location set that this location is excluded from MRP run (if am right the value to be maintained is 1)
    2. In MM02 go to MRP-4 view of the material master, specify plant & the storage location which you want to exclude & in the field SLoc MRP indicator specify that this is excluded for MRP run (if am right the indicator is 1).
    The step 1 ensures that all materials which are extended to this storage location will by default have the value 1. And step 2 ensures the materials already having this storage location view are excluded from MRP run.
    Regards,
    Vivek

  • How can I include the minimum stock of storage location in the mrp run.

    Hi all,
    I have in plant 1030 storage location 1001 and 1006.
    MRP1  Lot Size = EX
               MRP type = PD
               Reorder Point = 5
    MRP2  Safety Stock = 5
    MRP4 for 1001 is not filled
    MRP4 for 1006 Sloc MRP Ind = 2
                             Reorder point = 2
                             Replenishment qty = 3
    If no stock and I run the mrp I get
    a PurRqs for 8 with a automatic MtlRes of 3 going to storage loc 1006
    If I create a reservation in 1006 for 10 units and run the MRP again
    a PurRqs for 15 with a MtlRes of 10 going to storage loc 1006.
    I want the result to be PurRqs for 18 with a MtlRes of 13 going to storage loc 1006.
    10 for the reservation and 3 to fill storage loc 1006 with the replenishment qty.
    How can I acheive this?
    Best Regards!
    Curtis

    Hello Curtins
    Please observe what is stated on question 6 of FAQ note 550954, regarding storage locations planned separately:
    6. Question:
        A storage location should be planned separately. Is it possible to
        consider external requirements?
        Answer:
        No. The storage location MRP is a very simple reorder point planning
        procedure, during which only reorder point and replenishment
        quantity are defined. More complex settings can be implemented via
        storage location MRP areas.
    Therefore, I'd suggest you to use MRP areas to map this scenario.
    Best Regards
    Caetano Almeida

  • Change the MRP run fro Reorder Point to Forecast Based.

    Dear Experts
    My client is a battery manufacturing company, its Semi Finished product is Make-to-Stock and Finished Product is Make-to-Order. Initially the MRP was configured as reorder based and in Material master it was set as VM     (Automatic reorder point plng ). But now we need to change the MRP form reorder point to Forecast Based. The rolling forecast of the coming 3 three months is given in Planned Independent requirement (MD61) as version u201800u2019 - REQUIREMENTS PLAN.
    We have changed the MRP procedure in Material Master form VM to VV Forecast-based planning of the finished product but unable to get any result means no Automatic PR is getting generated, the we have changed all the materialsu2019 MRP procedure of that Particular BOM to have the required MRP and Automatic PR raise but still no expected result is coming.
    I would request you to provide your expert opinion to execute the Forecast Based MRP, what else should I do achieve the Linking between the Rolling Forecast and MRP instead of Reorder point. Should I have to make changes in Material Master (Only on finished product, In house developed/manufactured Product, Raw material etc), any configuration change in MPR and PR . Looking forward for your specialist advice.
    Regards
    Sony

    I have provided the demand in MD61 and make stock level of the material in such a way that it should raise the PR for MRP run but it is not generating any PR. have checked that if I put value in the forecast tab of the material master manually then it is raising the PR but I need the system to pick the value form the demand that I provided in MD61. Is there any configuration related issue to get the values form the demand and generate PR accordingly. Please guide
    Should I have to provide 'VV' at the first level of the Material at its master data or at each component of the BOM irrespective of
    the components for Semi-Finished (In house production), Raw materials (Procure from the supplier). Please suggest...

  • Workflow not triggered for PR from MRP run

    Hi,
    I have PR Release strategy workflow configured, working well when i try to create PR manually, triggers workflow.
    PR's created thorugh MRP run, triggers release strategy but not workflow.
    I checked the event trace 'releasestepcreated' event not triggered through MRP run.
    Please respond ASAP.
    Your inputs will be highly appreciated.

    The response i got from SAP.
    Please see note 67866 Purchase req. from materials planning -> no workflow
    Thanks,
    Indira

  • MD01 - in what order does the MRP run pick its materials to plan

    Hello,
    I would like to know how the MRP global run (MD01or inthe background)  picks  the sequence of its materials?
    Is it by order of material number? first number first run? or is there anyother logic?
    Thanks for any reply
    Aart

    Dear Aart,
    As well said by Dogboy49,the system plans the materials according to the low level code sequence.
    Materials may appear in several products and in several production levels of a product. The low-level code represents the
    lowest level of usage of a material within all product structures.
    It determines the sequence in which the materials are planned. The system plans materials with the low-level code 0 first and
    then those with 1 and so on. The lower the low-level code is, the higher the number assigned to the level.
    http://help.sap.com/erp2005ehp_05/helpdata/EN/f4/7d276944af11d182b40000e829fbfe/frameset.htm_
    Regards
    Mangalraj.S

  • Open requirement is not taken in considaration after MRP run.

    Hello PP Experts,
    I am facing issue with network , prod order and stockrequirement list.
    I have a network with qty 2.
    1 qty is in stock. (MMBE)
    for 1 qty prod order is created and the status is "REL PRT CNF DLV PRC GMPS MANC SECT".
    The problem is____________________
    Prd order has open requirement and prd ord is still open. The problem is that seem that MRP doesn't take in consideration this requirement as an open requirement and in MD04 it can not be seen. the requirements which we can see have  no linked to this production order but only linked to planned orders.
    Network can be seen in MD04.
    Why prd ord is not visible in MD04.
    Mukesh Chauhan

    Dear
    Why prd ord is not visible in MD04.
    It is quite logical  that SAP system is behavig correctly .You have Network qty of 2 which  has a planned order with same qty .Now in MDO4 you have converted that Planned Order partially to Production order having qty 1 and subsequyenetly , you have processed the order with REL , CRTD , GMPS  , CNF, DLV.
    Now here is the mistak happend that you have could have keep the Order Confirmation stauts as PCNF AND PDLV so that rest of the qty can be converted to same PO and also you can process CNF through CO11N and MIGO-101 for Final DLV.
    When an order is confirmaed and delivered , it will not appear in MD04 even its a partial qty .MD04 can show up the order having REL and CRTD .When the order is GMPS , CNF, DLV , TECO it will disaapear from MD04 as per the Filter set up for MD04 screen -SAP0002 in SPRO-PP-MRP-Evalution -Filter -Define Selection Rule .
    So what you need to do  either you revesre the DLV -MIGO-102 and Confirmation-CO13  and carry out PCNF,PDLV so that rest of the planned oqty can be processed with same order number .Or if  you know the Planned Order number , then got CO40 - Individual Conversion -Enter Planned Order -Convert to PO  and prcess subsequenetly
    Regards
    JH

  • Unfirmed purchase reqs not getting cancelled in the background MRP run

    Good morning,
    The system has created Purchase requisitions for 2010 due to the setting in the MRP run. we want to change it to planned orders outside the Vendor lead time and when i run a REGEN MRP with setting 2 (Purchase requisitions in opening period) its not happening. When i run indivudual MRP with MD03 with the same setting its alright, purchase requisitions are deleted and its converted into Planned orders. Can anyone please throw some light on to make backgrouond MRP run delete the Purchase requisition and create planned orders.

    Jags,
    You must delete the offensive PRs first.  Regardless of the MRP settings, MRP will still decide that the PRs are valid and will leave them alone.  It will not 'change' them into planned orders.
    Run Regenerative MRP with your new settings (Create purchase reqs as '2') but also run your MRP in planning mode '3', delete and recreate planning data.  It will delete all existing unfixed purchase requisitions, and then run MRP.
    Rgds,
    DB49

Maybe you are looking for

  • I need urgent help to remove unwanted adware from my iMac. Help!

    I need urgent help to remove unwanted adware from my iMac. I have somehow got green underline in text ads, pop up ads that come in from the sides of the screen and ads that pop up selling similar products all over the page wherever I go. Its getting

  • Read data from Object Services

    Hi , I need to display the text from 'Object Services' for a Material in a report. The Object type is 'BUS1001' for Material . Users Maintain texts in these Object services in Transaction MM03/MM02. I have to extract and display latest text entered b

  • Repeating Background Image

    Hey guys, I've been coding websites for like 4 years now and have used CSS styling long enough for it to effect the way my brain handles coding concepts. Anyway, I also happen to have a CS minor and have been playing with Java again lately. I was won

  • Wma files mystery

    hello all, heres a very strange behaviour of windows media for mac. Actually not on my imac ,but on a portable mac ( probably ibook ) using OSX 10.4 . I copied wma files from a digital recorder device using an usb cable . when the files are on the de

  • In EVERY sent email, I'm seeing a thumbnail photo that is unwanted

    I am not sure how it is getting there, but my sent emails are ALL showing a thumbnail photo at the top. It's a personal photo from photo booth. It's in the header of every email, like a stationary or something, but I can't find it in mail preferences