Dear Experts,
While creating a notification by copying an old notification (Reference Notification field), there found a difficulty that the Notification date is copied from the Reference Notification and is not editable.
Can someone suggest the solution so that the notification date could be edited to the present date.
Thank you & regards
Jogeswara Rao

IW21 Screen
-Fill Notification Type.  Fill the Reference Notification field with the Notification number you want to copy the details to your new Notiification.
Press Enter.
Your new Notification is filled with all information you wanted. You would make changes wherever you want.
But the problem is the Notification date of the 'Responsibilities' screen Area is also being copied from the Reference Notification and is Greyed out (i.e. not editable).
So if you save this notification, the notification date of your New Notification would be that of the reference Notification, which is generally not acceptable.
I hope you've followed.
Regards
Jogeswara Rao

Similar Messages

  • Can not see the option Execution with Data Change in the infoprovider?

    Hi team,
    i am using query designer 3.x, when i go into my bex brodcaster settings and schedule my report
    i can not see the option "Execution with Data Change in the infoprovider",
    i can only see 2 options
    Direct scheduling in background process
    create new scheduling
    periodic,
    is there any setting which i would be able to see the option "Execution with Data Change in the infoprovider"?
    kindly assist

    Hi Blusky ,
    check the below given link.
    http://help.sap.com/saphelp_nw04/Helpdata/EN/ec/0d0e405c538f5ce10000000a155106/frameset.htm
    Regards,
    Rohit Garg

  • Broadcast schedule with Data change to InfoProvider EHP1

    Hi all,
    We are working in an EHP1 environment and are currently trying to schedule a Broadcast from a Process Chain.
    The thing is that when we try to create the broadcast setting, under scheduling options we only get the "Direct Scheduling in the Background Processing"
    Is there a way to schedule a setting with Data Change to InfoProvider under EHP1 ? Is the option still available ?
    Waiting for your comments,
    Santiago J. Reig

    Solved.
    To be able to select the specific option in the schedule of a broadcaster setting you first need to add the Process Chain step, run the chain once, and only then the option will be available.
    Regards !

  • Client Copy (With Data/Cubes) Possible in BI 7.0?

    Hello,
    I am a basis team member (newbie and still learning) for my company and have been asked to copy our development cubes/data to our sandbox environment. We are attempting to do this through a client copy. I am using SCC9 with the SAP_APPL profile, but afterwards I do not see the cubes or any of the infoproviders etc in RSA1 in the sandbox. Is there a post processing step that I need to carry out to have this content show up or is a client copy not possible? We are trying to avoid a system copy if at all possible. Thanks for any and all suggestions/comment/help. Don't worry, I will award points for helpful answers :).
    Thanks,
    Rob

    Hello,
    See these docs,
    [System Copy Procedures |https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/50960d8f-6542-2a10-3ba8-e46dc23dd9b1]
    [System Copy and Migration|System Copy and Migration ]
    [Setting up Business Intelligence Client in NW2004s|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/007af9a7-e48e-2a10-5c85-fcac22d58e82]
    [System Copy for SAP Systems Based on SAP NetWeaver 2004s SR2 ABAP and Java|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/200ebc93-dabe-2910-c1a6-c4ec30b20e04]
    [Homogeneous and Heterogeneous System Copy for SAP Systems Based on SAP NetWeaver 2004s|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/f022aa7d-0c01-0010-20a5-c247330d47fa]
    [System Copy for SAP Systems Based on SAP NetWeaver 2004s SR1 ABAP|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/d10bf27d-0c01-0010-6995-bbdcdf0118a1]
    [System Copy for SAP Systems Based on SAP NetWeaver 2004s SR2 ABAP|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/e08502d4-dabe-2910-bbb4-c1bfc82aed73]
    [System Copy for SAP Systems Based on SAP NetWeaver 2004s SR2 Java|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/20bd5cee-dabe-2910-fb97-c082a7c9c682]
    Thanks
    Chandran

  • SYSTEM Copy with Data ( SAP Export/Import way)

    Hello ,
    There is requirement at my client site to build SAP system copy from Production System  without copying Data but
    should have Programs/ Structures / Repository/ Tables & views etc.
    Though We have thought of building SAP system with Export/ Import way and then deleting the Client from copied system
    after that running Remote client copy from Source to Target system with SAP_CUST profile
    But I have heard with SAP Export/Import way , We can have SAP data copy skipped and only structure to copy. If there is any way
    of such kind then Please help me in letting know the same
    Thanks
    Deepak Gosain    

    Hi Deepak
    Kindly refer the SCN link difference between the Client copy Export / import & Remote copy method
    Difference between remote client copy and client Import/Export- Remote client copy steps
    BR
    SS

  • E-Mail notification issue with date

    Hi All,
    i am facing following email notification issue, could please clarify.
    E-mail notification that was sent to employee this morning, March 17, 2009, but actually the email is dated February 3rd and refers to the January timecard, but she received it today, for the February timecard.
    Please let me know why this was happening. I don't know if this issue on email server or workflow design.Thanks.
    Regards,
    Prasad

    Hi,
    any updates on this issue?
    is there any possibility to resend the old notifications manually?
    Thanks,
    Prasad

  • SAP BI System Copy with only Config changes, Not Data

    Hi BASIS,
    I have a requirement from a client to build a system landscape stratagy for their SAP BI system.
    We have DEV - QA - PRD systems for SAP BI (7.0 SP 16)
    Both DEV and QA are completely out of sync with PRD. We are doing development tasks directly on PRD. Now we have decided to re-sync the DEV & QA systems with PRD.
    'System copy with Data' will be easier to implement. But our PRD DB size is nearly 3TB. The client is not ready to pay for the extra/temp. disk space for DEV and QA sync. ( We are on DB2).
    Now, we have only one option left. Capture all Config changes from PRD and transport them back to DEV & QA. This is a tedious task and cause many inconsistencies.
    Would anyone have any other ideas to bring the systems in sync with less time involved and less resources.
    I am a SAP BI person. So dont know much about BASIS tasks. Please help me with any links of best practises or SAP notes.
    Cheers

    HI Reddy,
    We came to know from our basis team that we do not have the Java Stack installed in our BI 7.x system yet.
    As it is integrated with EP which has Java, our web reports are working.
    1) But my question is still do we ned to install the Java Stack in our BI system as i do not find any Export to PDF option in EP for the reports (eventhough AS Java supports this).
    2) Or can we use the existing configuration without Java STack integrated to EP for the new tools like Report Designer and Integrated Planning?
    Regards
    Kumar

  • Address data changed after invoice is created

    Hi,
    I've a problem to solve and it's related with data changed after invoice is created.
    The scenario is the follow:
    1º - create a complete and standard sales process - order => delivery => invoice, with the standard partner scheme and without edit the address data, for any kind of partner
    2ª after the invoice is created, I change the address data on Client Master Data, for the same client that I've used on previous process
    3º I'll go to the VF03 transaction and take a look at the partner data on header level. Here I can see that the changes on the Client Master Data ar updated to the invoice document wich is already created and printed when I maked the changes
    I think that could be a program error because, once the documento is created, you only can change texts and accounts if this document is not yet created.
    And, I can't edit this kind of data on invoice creation because it must be done at order level.
    So I don't understand why it happen, but it happen on more than one client.
    I'll hope that anyone can help me to solve this issue.
    Kind regards,
    Nuno Rodrigues

    Hi Nuno,
    the adresses of all Clients are stored in table adrc. If there are no changes in the order, the system takes the standard adress of the client. That is made for not having an extra adress for each order.
    If you change the adress - the system will create a new adressnumber ( 999........ - see in VBPA ).
    If you have different adressnumbers in your orders, you are not able th collect several orders into one delivery note - for the adressnumber ist normally a split-criteria.
    Ich you will have an extra Adress for each Order, change the adress - for example by an user exit.
    But if you have different adressnumbers - the delivery and the invoice will split the different orders - if you dont do something against in an user-exit.
    Hans

  • Pre-fill the OLAP cache for a query on Data change event  of infoprovider

    Hi Gurus,
    I have to pre-fill the OLAP cache for a query,which has bad performance.
    I read a doc 'Periodic Jobs and Tasks in SAP BW'
    which suggested sum steps to do this
    i hav created the setting for Bex broadcasting for scheduling job Execution with data change in info provider
    thereafter doc says  "an event has to be raised in the process chain which loads the data to this InfoProvider.When the process chain executes the process u201CTrigger Event Data Change (for Broadcaster)u201D, an event is raised to inform the Broadcaster that the query can be filled in the OLAP cache."
    how can this b done please provide with sum proper steps
    Answers are always appreciated.
    Thanks.

    Hi
    U need to create a process chain or use the existing process chain which you are using to load your current solution, just add event change process type in the process chian  and inside it add the info provider which are going to be affected.
    Once you are done with this go to the broadcaster  and  create new setting for that query...you will see the option for event data chainge in infoprovider just choose that  and create the settings.
    hope it helps

  • Data change Event for Information Broadcasting

    Hello Forum
    This is regarding problem with "Data change Event for Information Broadcasting".
    We have integrated the evening in a separate chain which is scheduled after the transaction data load.
    In the settings for the event we have mentioned the infoprovider name based on which the reports are to be distributed.
    Now, when the process chain is executed it does not distributes any reports though the data is changed in the infoprovider.
    However when executed again its distributing it,any ideas what the problem is ?
    Regards
    Ashish

    Hi,
    Check out the t.code  RSRD_LOG.
    have a check at the below link for monitoring via email
    http://help.sap.com/saphelp_nw04/helpdata/en/44/5b2341144ba52fe10000000a155106/frameset.htm

  • System copy with Export/Import Distribyted system UNIX database, Windows CI

    HI
    we have a distributed system witch I want to make a copy of
    Oracle Database on HP-UX
    CI + SCS on Windows
    Dual stack system  ABAP/Java
    1)  I have made an system copy with data base copy tools, and that works fine.
    2)  I have made a system copy export/import of a "central system"
    If I try to make an export/import system copy on a distributed system it wont work.
    ( this work fine in a central system) I dont get anny error messages all gren checks marks ! 
    It seems like the problem are in not finding the profiles from CI ?
    It find the profiles for the sapgateway.
    I someone are more interested I have more documentation with screen shots in a word document.
    I Have used Installation Master SR3 and tryed with some older versions as well.
    I have read SAP Note 970518 - Hom./Het.System Copy SAP NetWeaver 7.0 (2004s) SR2
    SAPINST   
    Using virtual hosts for central and/or DB instances
    SYMPTOM:
    You are using virtual host names for your central instance and/or the database instance (e.g. in a HA environment). Although SAPinst finishes successfully, some export steps are not being performed.
    SOLUTION:
    Start the export with the property SAPINST_USE_HOSTNAME=<virtual host>.
    If the central instance and the database instance run on different hosts, run the database export with SAPINST_USE_HOSTNAME=<virtual host name of the DB server> and - if you run a Java or ABAP+Java system - run the central instance export with SAPINST_USE_HOSTNAME=<virtual host nameof the central instance host>.
    If you run a central system with different host names in the profiles, handle the export as a distributed export, calling SAPinst with parameter SAPINST_USE_HOSTNAME. Perform the export of the database instance on the DB server, calling SAPinst with SAPINST_USE_HOSTNAME=<virtual host of the DB server>.

    Hi I have received folloving answer from SAP:
    You're doing everything correct - besides one thing.
    When you specify the profiles during the database export it cannot be
    correct to specify the profiles of the gateway instance located on
    the same host.
    As a consequence - it picks up the wrong instance G01 and sets the
    property 'hasABAP' and 'hasJava' to 'false'...  - thus the export
    is empty. You can see this within the corresponding 'sapinst.log' file.
    The correct procedure would be to specify the profiles of the central
    instance on the Windows Machine. If you cannot access them, you should
    make them available by Samba or by any type of software which makes
    it's possible to export filesystems or directories from windows to
    unix.
    Best regards
    Bent

  • Broadcasting when data change

    hi,
    I have added the Process Trigger Event Data Change (for Broadcaster) in the process chain. In the broadcast settings I have given the authorizer as ALEMASTER.
    I have scheduled the process chain with the help of an event and the process is getting failed with an error mesage (Alemaster does not have authorization to execute the broadcast setting)
    I have changed the authorizer to my ID in the broadcast setting  and executed the process chain and i am getting an error message SDAPIYK01_BROADCAST_01: User Z57324 cannot be used for background processing.
    I have checked the authorization objects S-RS_ADMWB and S_RS_BCS and they are assigned to me with all the access and not for ALEMASTER.
    I am not sure how to schedule it in the process chain.
    Please help me in this regard.
    Raghu Reddy

    Hi Raghavendra,
    You would need the following authorizations.
    Authorization object - S_RS_BCS
    Field name - RS_EVTYPE
    Value - DC(Execution with data change in infoprovider).
    Activity - *(Full authorization).
    Authorization object - S_RS_ADMWB
    Filed name - RSADMWBOBJ
    Value - BR_SETTING
    Activity - *.
    If you are sending mails to recipients through broadcast settings, you need authorization
    Authorization object - S_OC_SEND
    Filed - COMM_MODE
    Value - INT.
    Lastly,S_BTCH_NAM u2013 User specific processing. Allows a user to specify other users for runtime authorization for a job. However, i think you are missing only the first one.
    Hope it helps,
    Regards,
    Sunmit.

  • Including an Event Data Change in a Process Chain

    There is a step called "_Execution with Data Change in InfoProvider_" in the process of including event data change in a process chain.
    How do we carryout this? should this be done in Bex or in process chain itself?

    Dear Eshwari,
    1) To get the 'Execution on data change' option, you need to have aprocess chain with the 'Event data
    change' process type which contains 'the infoprovider' (The infoprovider, over which the query is created
    which you are trying to broadcast) in the process variant of it.
    2) Further more, additional authorization is also needed in order for the user to see such scheduling options in broadcaster.
    Please assign this authorization object to the affected users.
    BEx Broadcasting Authorization to Schedule  S_RS_BCS
         Activity                       *
         Event ID in Broadcasting Frame *
         Event Type in Broadcasting Fra <== Here you should select*
         ID of a BI Reporting Object in *
         Type of BI Reporting Object in *
    3) Please also ensure the user has not only the Busines Explorer role but also Business Intelligence role in Portal,
    Regards,
    Arvind

  • Data Change in the Infoprovider-Process Chain

    Hello Friends,
                       I want to broadcast the Queries and Workbooks periodically.I want to automate the process.For this i came to know that we have to  select the EXECUTION WITH DATA CHANGE IN THE INFOPROVIDER TRIGGERED BY A PROCESS button.Can u please guide me how to do it successfully.
    Thanks
    Mohan Chand Reddy A

    Hi Mohan,
    You can achieve this using process type in Process chain creation.
    In the below links you will find step by step procedure to create this in process chain
    http://help.sap.com/saphelp_nw70/helpdata/en/ec/0d0e405c538f5ce10000000a155106/frameset.htm
    http://www.tli-usa.com/download/Taking_Charge_of_Information_Broadcasting_in_BI_7%5B1%5D.0_for_improved_report_and_data_distribution.pdf
    Regards,
    Venkatesh

  • Looking for Active Data Service samples with RDBMS change notification fire

    Hi,
    I am looking for samples/examples of Active Data Service when a server side event, like RDBMS change notification got triggered.
    The ADS samples that I found so far are:
    - Twitter http://www.oracle.com/technetwork/developer-tools/jdev/learnmore/65-activedataservicestwittersample-191314.pdf
    - http://adfwithejb.blogspot.com/2012/12/active-data-service-with-active-image.html
    - http://adfwithejb.blogspot.com/2012/12/active-data-serivce-with-data.html
    But these samples do not demonstrate how RDBMS change notification got triggered got triggered. The last two samples have a Runnable class that simulate the triggering, and the Twitter example is twitter stream notification.
    Please shed some lights on Active Data Service with RDBMS change notification got triggered.
    Thanks
    -Mina

    Hi Mina,
    Check this 2 resources, first a presentation made at OOW by Lucas Jellema: http://www.slideshare.net/lucasjellema/push-to-the-limit-rich-and-proactive-user-interfaces-with-adf-oracle-open-world-2011
    second an interesting forum thread around the the topic: ADF BC and the Active Data Service using af:table from what I know this is still valid as of today.
    After reviewing the topic there is also one more link that address this topic:
    http://technology.amis.nl/2012/06/18/notifying-adf-applications-of-database-changes-fast-and-lean-using-database-query-result-change-notification-part-one/?utm_source=rss&utm_medium=rss&utm_campaign=notifying-adf-applications-of-database-changes-fast-and-lean-using-database-query-result-change-notification-part-one
    Thanks,
    JC
    Edited by: Juan Camilo Ruiz on Jan 9, 2013 2:57 PM