Ntwk actvty 9000006262 0050 budget exceeded when creating GRN
Error:-604 Item 001 Ntwk actvty 9000006262 0050 budget exceeded
When we post Goods Receipt or Invoice using BAPI_GOODSMVT_CREATE/BAPI_INCOMINGINVOICE_CREATE we are getting the above error message.This error message generating when i call the BAPI through JCO.
I have tested from front end SAP transcation MIGO and also entered data manually in BAPI
through SE37, Goods receipt is created successfully, I feel background run created problem when BAPI called from JCO.
Please any can suggest me the solution.
Can you pelase review following sap notes..
1008235 No commitment carried forward for commitment value zero
1030078 Budget overrun with MIRO posting
734808 MIR4: Error message BP603 when simulating
1034618 BP 604: Budget exceeded with parked invoices
Hope above help you..
Regards
Siva
Similar Messages
-
604 Item 001 Ntwk actvty 9000006262 0050 budget exceeded when creating GRN
Error:-604 Item 001 Ntwk actvty 9000006262 0050 budget exceeded
When we post Goods Receipt or Invoice using BAPI_GOODSMVT_CREATE/BAPI_INCOMINGINVOICE_CREATE we are getting the above error message.This error message generating when i call the BAPI through JCO.
I have tested from front end SAP transcation MIGO and also entered data manually in BAPI
through SE37, Goods receipt is created successfully, I feel background run created problem when BAPI called from JCO.
Please any can suggest me the solution.Can you pelase review following sap notes..
1008235 No commitment carried forward for commitment value zero
1030078 Budget overrun with MIRO posting
734808 MIR4: Error message BP603 when simulating
1034618 BP 604: Budget exceeded with parked invoices
Hope above help you..
Regards
Siva -
Ntwk actvty 9000006262 0050 budget exceeded
Error:-604 Item 001 Ntwk actvty 9000006262 0050 budget exceeded
When we post Goods Receipt or Invoice using BAPI_GOODSMVT_CREATE/BAPI_INCOMINGINVOICE_CREATE we are getting the above error message.This error message generating when i call the BAPI through JCO.
I have tested from front end SAP transcation MIGO and also entered data manually in BAPI
through SE37, Goods receipt is created successfully, I feel background run created problem when BAPI called from JCO.
Please any can suggest me the solution.Try to dump the contents of all the parameters of the BAPI call into a temp table when using JCO and if you are still in development box testing this. May be your quantities are getting converted into some big amount due to decimal point placement or comma etc. Check all the conversion exits. MIGO and BAPI execution from SE37 will take care of all your conversions, but if you call it from a program or from an external system, you will have to take care of them including dates.
-
Err:Ntwk actvty 9002367 0050 budget exceeded when calling standard GR BAPI
Hi experts,
Error:-604 Item 001 Ntwk actvty 9002367 0050 budget exceeded
When we post Goods Receipt or Invoice using BAPI_GOODSMVT_CREATE/BAPI_INCOMINGINVOICE_CREATE we are getting the above error message.
and when we create manually through MIGO we are not getting this error message.
please any one explain me the solution.Can you pelase review following sap notes..
1008235 No commitment carried forward for commitment value zero
1030078 Budget overrun with MIRO posting
734808 MIR4: Error message BP603 when simulating
1034618 BP 604: Budget exceeded with parked invoices
Hope above help you..
Regards
Siva -
Internal Order Budget Exceeded when creating a PO
Dear all,
When we create a PO against an Internal Order, the system displays the message "Item 001 - order X budget exceeded". But checking that order we can see budget available.
Do you guys have idea the reason of it?
Many thanks,
AmandaHi Sreenivas,
As we are planning to send budget exceed message to responsible person in the internal order, however, from the configuration, it is find that the warning message of budget exceed will send to the budget manager only, and the definition of budget manager is by internal order type and not by individual internal order.
Please advise how can I send the warning message to the person responsible for the internal order instead of send to the budget manager for the internal order type.
Thanks,
Nina -
Order budget exceeded when creating a PO
Dear all,
When we create a PO against an Internal Order, the system displays the message "Item 001 - order X budget exceeded". But checking that order we can see budget available.
Do you guys have idea the reason of it?
Many thanks,
AmandahI,
You have to check tolerance limit for Order buget.
Go to SPRO - Controlling - Internal Order -Budgeting & avalibily contrl & ammend the Tolerance limit.
I hope it will work
Regards,
Manish
Dont forget to give point if useful ans. -
Err: Budget Exceeded(when int.order changed in asset) while creating invoic
Hi All,
Hope you are all doing wonderfull !
We have created a statistical order type and wanted to assign them to assets as we don't wanna settle thoze expenses,but needed only for statistical purpose.
It was okay, when we have changed them in asset master. However, we could not change them in already existing PO's, so when we are trying to create Invoices for the PO's having old internal order number, it is shooting us an error " item xxx order xxxxxx budget exceeded?
Please let me know how to proceed further to clear this problem.
Thanks
SriHi Sri,
Can you please elaborate a bit on your scenario. Have you assigned an internal order in asset master record.
The internal order in asset master record has different purpose. It is used when you want to post depreciation of that asset to internal order.
Regards
Chetan. -
BP604 (Budget Exceeded When posting GR) - Urgent
Dear SAP guru,
We got a problem with our system when we will post GR (BP604-Budget
Exceeded). The scenario is :
Project : NEW-DTCRW101
Our original budget is : RM 16000 (Ringgit Malaysia)
Commitment PO : RM 15564 (7000SGD with exchange rate 2.22340)
Assigned : RM 15564
Available Budget : RM 436.
When we will post GR next day or two days later , the error message BP604 appears. It seems that the system check the available budget and the exchange rate when we do the GR posting.
Many thanks in advance.
Best Regards,
Denis EvitantoHi Nies
This note is not for implementaion. It gives the formula used by the system for checking availability control for budget. Please check whether it says some thing about exchange rate for calculation budget availability. Also run CJBN and see whether you are able to post GRN. If its not working then raise an OSS call with SAP as they will be in a position to advise on the right note to implement
Asha -
Payment Budget Exceeded Message Number BP 628 & 629
Hi all,
We encountered "payment budget for year 2008 exceeded" problem when releasing the Service Entry Sheet in ML81. The message number is BP 629.
The standard SAP FM report shows that there are sufficient available budget for that funds centre and commitment item. We have also checked and verified that the necessary funds centre, commitment item have been duly created and assigned to the corresponding cost centre and G/L account.
Would greatly appreciate if you experts can help us with the solution. Many thanks.
Regards,
Nathan JanardhanaHi,
Pls check the below SAP notes:
Note 879348 - Payment budget exceeded when creating a new line item.
Thanks
Aravind
Assign points if helpful -
Budget Exceeded error with message No BP 602
Hi Experts,
I am facing a budget exceeding error: Ntwk actvty 6000001 0020 budget exceded year 2009.
following is the settings
Availability control against: Overall
Availability control against: Budget
Availability Control in the Controlling Area Currency:
Activation type: Automatic activation during budget allocation
Usage level in %: 0,00
The project is P.0001
Top lvl P.0001
WBS P.0001.1
Network Activity (External services) 6000001 0010 PR-($40000) PO($20000) & Service entery done with same amount($20000).
Network Activity (External services) 6000001 0020 PR-($1)
Actual $20000
Commitment 20001
Assigned 40001
Available $49
Now we updated the budget as below:
The original budget was 40050 in IM then modified to 45050 and distributed in CJ30.
When we try to update the Service PR with 49 or more dollars, gives error in commitments and when the log checked, the budget exceeding message is there, if the PR updated with 48 USD, it gives the budge is exhausted.
40050(Old Budget)-40001 (assigned) = 49 USD. Which means, the supplement of the 5000USD is not considered.
Run the CJEN and CJBN to reconstruct the project but no use.
Please help me out where to check and what went wrong. its in client prd.
Regards,
GaneshHi,
You said in reports and in CJ31 , it is showing 60049 as available. I am confused here......including additional budget , total budget you gave is 45000. Then how it can show 60049 which more than Original Budget ?
Have you distributed additional budget to the WBSE for which Service P.R is being raised ?
What is distributable budget at the level of the WBSE for which P.R is being created in CJ30 ?
What Is available budget against the WBSE for which P.R is being created in S_ALR_87013558. ?
May be it will be of saome help for you.
Thanks
Saikishore.Ganga -
Guys,
I need help with this scenario. Here is the scenario. When i create a purchase requisition which has an internal order assigned in it, it was counting as a commitment, we didnt want this to appear as a commitment. We applied notes 955106,1227760 and1307755 to fix the issue.
My problem is fixed for new purchase requisitions but for existing ones the commitment is being double counted and i get an error internal order budget exceeded when i am trying to create a PO
eg i had a commitment of $ 100 before i applied the notes. My available budget was $90( after the purchase req posted). When i create a PO, it should just move the $100 commitment from purchase requisition to Purchase order but system is taking commitment of $100 ( purchase requisition + $100 purchase order). Giving me the error message budget exceeded by $110 which is incorrect.
Note 1227760 talks about this exact issue which is already applied in our system but that doesnt help
Please advice how i can fix this, business is unable to create purchase ordersHi Azam,
I think in the customization settings for tolerence limit, you have maintained it for TrGr ++ as well as TrGr 01for PO.
The system will take the priority of 01; so please change the setting to ++ only with warning, error etc.
After changing the setting advisible to run CJEN and then CJBN if needed.
Hope this will solve your problem.
Regards,
Ganesh -
Budget error while creating delivery from sales order
hi Gurus,
System is throwing error PB603 "Item 004 WBS element ABC-XXX budget exceeded" while creating delivery from sales order.
I am picking material from unrestricted plant stock (not in project stock).
I am also confused as sales order has 3 line items & error shows Item 004 !Hi Kuldeep,
Check this note,
Note 159387 - Message BP603: incorrect line item is displayed
Its valid only till 4.6. Might give you some idea but.
Regards,
Gokul -
Budget exceeded BP604 (when create Invoice)
Hi All,
User got an error message budget exceeded BP604 when create invoice. How can i know what the configuration to check why system check budget( Investment management). I tried to check the configuration in SPRO (Define tolerance limit for availability control) shows that budget profile use ++ which are : (no invoice checking) but in actual it checks budget.
++ All activity groups
00 Purchase requisition
01 Purchase order
02 Orders for project
03 Goods issue
04 Financial accounting document
05 CO document
06 Budgeting
07 Funds reservation
08 Fixed prices in project
09 Payroll
Many thanks in advance.
NiesBusiness transaction group 04 (Financial accounting document) contains below transactions:
G/L account posting
FI invoice parking
Invoice verification
Goods receipt for the order
Cash budget management
Payment transfer
Down payment posting
Inventory difference
Regards
Sreenivas -
Error for Budget exceeded for Network does not show up while creating PR.
Hi SAP Gurus,
We have an issue while creating a purchase Requisition from Network. When we enter the Toatal Amount in the PR and if the total Amount is greater than the total Budget for the Network, the error "For item 001 Ntwk actvty XXX & WBS element XXX budget amount XX USD exceeded " is not showing up in the foreground by the system and hence not able to create PR. It seems that while trying 30-40 times, the system will show this error in the foreground once or twice only and we want this to be appears in the foreground consistently. Can you please advice how to fix this? Thanks,
Reagards,
Imran.Hi,
you need to maintain sufficient budget in respective WBS element by using transaction CJ30 and by releasing budget through CJ32.
Check the budget availabilty in report s_alr_87013558.
It will resolve your issue
Regards,
Sandesh Sawant -
Budget Exceed Error during creating of Purchase order in reference to PR
Hi,
I am getting the subject error (Budget Exceed Error) every time when I want to create a purchase order related to purchase requisition of my project.
Issue is that after release the project when the purchase requisition has created for non stock item under activity I found in transaction CJ31 the assign value has already updated.
Let say my budget is 400 US$, and the purchase requisition has created for 380 US$. Now when I check with CJ31I found the assigned value is 380. Now If I create a purchase order it throws an error that budget exceed.
The tolerance limits are following:
SA ZSA01 Budget Profile Overall AVAC ++ 1 90,00
SA ZSA01 Budget Profile Overall AVAC ++ 3 100,00
SA ZSA01 Budget Profile Overall AVAC 01 1 90,00
SA ZSA01 Budget Profile Overall AVAC 01 3 100,00
Please advice what will be the proposed solution for the above issue.
Thanks in advance.
With Regards,Your budget is 400$ and PR value is 380$ but you have not mentiond what is the tax value ?
when u r creating PO at that time system will check the budget against PO value considering taxes also.
eg. 380$+tax value.
after considering taxes your total PO value imay be getting updated more that 400$.
Explre you error by clicking on error information you get the exact diffrence in budget and PO value.
Hope this will sove your problem, reply after doing this.
Maybe you are looking for
-
Problem creating a PDF file from other PDF files
Normally, the process works, but sometimes produces the following error (in Spanish): El documento no se pudo archivar. Problema al leer el documento (110) Does anyone know the origin of the error? We have reviewed the security of files and is correc
-
Tried updating the software on my iphone 4 and now its stuck on recovery mode asking to restore my phone to factory settings. How can I bypass this? I don't want to lose the data, etc... Made the mistake of never backing up my phone. Please help!!!
-
24 Inch Intel iMac... may have bad Logic Board
What are my options if the Logic Board is bad? Is this something you can purchase? Dont have an Apple Store anywhere near me. Thanks!
-
XSL and Extended SQL Funtion not working in XMLP 5.0
Hi All, I am not able to get the following functions to work for FSG publishing in XMLP 5.0 11.5.10.2 apps), but they both work in XMLP 5.6.2. I am using the following function in the Segment Values Override field: <?substring(translate(@RptDetName,'
-
Hi,I use a jTable to diaplay dynamic sql. But I find only a column displayed.In fact ,I have three column . I don't know what happens. If you know or you have the same problem, please let me know. Thanks in advance. -zhou