hi gurus,
              i am getting the data upto psa level.the infosource is feeding to one ods.but i am not getting the data in ods.strictly speaking i am getting the data in newdata of ods but i am not getting in active data table.can anyone resolve this issue highly appreciated.
thanks and regards,
nataraj.

hi balaji amd pals,
                      i am getting that type of error(subsequent process).i am sending the error as follows
Subseq. processing (messages) : Errors occurred
Activation of data records from ODS object ZOPMOMCB terminated
Communication error (RFC call) occurred
Request REQU_40JA03VHZT6V9EAJTLHM7BW5H , data package 000001 incorrect with status 9
Request REQU_40JA03VHZT6V9EAJTLHM7BW5H , data package 000001 not correct 
Inserted records 1- ; Changed records 1- ; Deleted records 1-
No confirmation for request ODSR_40JABQY2GD5XKWR0TKB86GF45 when activating the ODS object ZOPMOMCB
ODS activation (change-log) : Errors occurred
Other (messages): Errors occurred
thanks and regards,
nataraj.

Similar Messages

  • ODS activation failed

    I am getting the following error message while activating ODS data
    <b>ODS object ZXXX was built incorrectly. Cannot update request REQU_9IVH8MQSZIUQEZSNSY8A0YCHG (180,120)
    Activation of data records from ODS object ZXXX terminated.</b>
    There is no error in the data staging process till new data table of ODS.
    Please advise.

    Have a look at this:
    ods activation failed---giving the messsage that "ODS object built incorre"
    Hope it helps.
    Regards.

  • ODS activation failing with the reason : ODS not built properly"

    Hai,
             I have a process chain wherein I have an ODS thats being loaded and activated. The problem is that the load is successful but the activation is failing. When I see the process monitor, it says "DataStore ZXXXX built incorrectly; cannot update request REQU_******". When I checked this ods in RSRV, in test for ODS objects, the test for "Foreign Key Relationship of Reporting-Relevant ODS Object and SID Table Characteristics " failed with the errors like :"The SID values are missing for 2 specifications for characteristic ZLPORTG"
    Can somebody suggest me how I can solve this problem? It works fine in manual execution and the ODS shows the request is activated and the id is generated after activation.
    It is clearly a SID problem. Do I need to delete all data related to those objects everywhere in the system? I deleted data from that ODS and reloaded. But still the same problem!

    Hi,
    i think you should implement -Note 965599
    also check
    Note 961556 - DataStore (activation): Columns are initialized without rule
    Note 974833 - DataStore (activation): Columns initialized without rule
    Regards,
    San!

  • Ods activation failer

    Hi
    Iam loding to ods i got this error,
    activation falier

    Hello,
    Which product is this error for?
    This forum is specifically concerning the crystalreports.com and bi.ondemand.com applications.
    Cheers
    Steve

  • ODS activation, short dump COMPUTE_INT_PLUS_OVERFLOW. How to solve?

    Hello Gurus,
    We are on BW 3.1.
    We have an issue - ODS activation failed due to a short dump.
    Runtime Error          COMPUTE_INT_PLUS_OVERFLOW
    Exception              CX_SY_ARITHMETIC_OVERFLOW
    Since the caller of the procedure could not have expected this exception
    to occur, the running program was terminated.
    The reason for the exception is:
    In the current program "SAPLRSSM_PROCESS",
    using + or 'ADD' to add the values 2137304138 and 12410267 resulted in a
    value greater than 2147483647 or samller than -2147483648. This
    leads to a whole number overflow.
    Could you please guide me to solve this?
    Please let me know if you need more details.
    Thanks,
    raj

    This dump is happening because of the overflow of the size assigned for the variable.
    This dump can be avoided by changing the declaration of the variable definition.
    DATA: variable_name type p decimals 0.  
                              OR
    DATA: varibale_name(25) type n decimals 0
    Try this. This will resolve your dump.
    regards,
    brijesh

  • ODS Activation Issue in Prod - Critical

    We are in BI 7. We have a huge ods ZXYZ in Prod. It has more than 400 million records. BEx reporting - off.
    Over the last weekend some data was added the requests were being activated and there was master data activity in parallel. The ODS activation failed with SYSTEM_EXCEPTION. Unfortunately not investigating the root cause, the ODS activation was resumed and it returned SYSTEM_CANCELED again as there was master data activity going on.
    The problem is that request is now partially activated and it became in faulty status. When trying to activate, we get the following error message.
    <i>Activation of M records from DataStore object ZXYZ terminated
    'A' and 'U' entries exist in RSODSACTREQ for request REQU_CTAKWUIM6ZAWBQC1K6Q5TVL8M - termination</i>
    When trying to delete that request which was partially activated, it fails complaining about Faulty status of the ODS.
    The problem is we are not moving forward as the request cannot be deleted/activated due to this.
    RSODSACTREQ table has Activation status 2  - Activate failed for this request.
    Can you experts please advice.

    Hi,
    I see that your message was not answered and you may not have this issue any more. But for future reference you could refer to note 947481. You might be able to use step 1 from this note to clean the failed request and reload your data.
    Hope it will help some day. It did work for us.
    Sameer Gandhi

  • ODS Activation failures

    Generally it is obesreved that the ODS activation failes with error something like 'SID cannot be determined'. Also many times we see that ODS activation goes on for 2-3 hours. In this case when we manuall activate the ods it gets completed successfully. However, can anyone tell me the reason for long activation time and the error mentioned above. It would further be helpful if you could tell me the possible preventive measures to avoid manual interventions...Thanks for help in advance

    Hi Lye
    First i will explain the reasons for long running ODS.
    1.This is probably because of too many parallel ODS activations running at the same time.
    2.some times some particular jobs running may lock your ODS activation which you can monitor in SM37 which results lock waits and dead locks.
    If you see the PID no for the job which is involved in lock waits,if you feel that particular job is not important at that point of time you can terminate the job(not ODS activation job) and repeat the job after the succesful completion of the ODS activation.
    If the ODS activation fails with SID error as you mentioned,i hope this solution may help you.
    1.Check the request for the infopackage which is loading the ODS in RSRQ
    2.give the request of the bearing infopackage or request ID and execute in RSRQ
    3.it shows whether that reqest is updated in to your target correctly or not.If its not loaded check the IP processing setting whether the reuested data is reaching in to targets are not.some times data load happens till PSA then push the data by doing process manually step.
    4.Now reapeat the ODS activation step.
    but if it is SID issue, then load the master data for that particular characteristic and repeat the ODS activation step.
    Hope may help you
    Regards,
    Venkata Lakshmikanth

  • ODS ACTIVATION Failure frequently......

    Hi,
    We r loading data from ods to cube , but ODS activation process for 3 ods is happening parallely.
    This ods activation failed sequence two times , but in logs error mesgs
    are "Activation of data records from ods object terminated,Qm status is in not green before ODS activation"…
    we are loading approx 10,000 records
    The chain is like this…
              START
    ODS1          ODS2          ODS3   à these 3 ODS are Parallel
    |          |          |     
    CUBE1     CUBE2     CUBE3
    Can anyone tell me what might be the reason…for failuring frequently.. this is a monthly chain
    -Shah

    Shah,
    1) I said "conflicting" because I thought you were loading all data to ONE ODS.. so I thought they might have some "locking" problem..But since u had confirmed me that 3 different ODSs.. this is out of scope for us..I am taking back my words..
    I do not see "technically" issue with Process chain design as all are 3 different tables now..
    It has a techincal issue, if you are loading 3 ODS parallely and Activating all 3 ODSs at a time..
    in the above scenario.. say ODS1 completed 1st and it tries to start the Activation node..( which tries to activate ODS2 and 3 also..) but still 2 and 3 are loading.. can lead to the mentioned error..
    generally.. if u schedule too many parallel jobs at a time it will occupy all available system resources and can lead to some ewrrors..
    regards,
    hari
    Message was edited by: Hari Kiran Y

  • ODS activation failures after new hardware installation..urgent

    Hi All,
    I am working in PRD.There are 10 process chains which i need to monitor daily.Daily ODS activation fails in 4 of the 10 chains.The error message for two of the failures are,
    Task 0040 during SID specification without confirmation     
    and for another process it is showing "DBIF_RSQL_SQL_ERROR" error.
    manually I am doing steps and the activation is successful.These type of errors we are getting after the new hardware installation.
    Could anyone let me know are there any patches to be applied inorder to avoid such type of errors.
    Please advice me what to do.
    Thanks,
    Manjula

    What is the patch your currently on at the moment.
    It could also be some of the settings in RZ11 have been changed. You need to work with your basis people to resolve this.
    DBIF_RSQL_SQL_ERROR is a common problem and usually due to not enough processor's available and the database gettings into a knot.
    Check SM21 and ST22 for the more information on the issue.

  • No msg from process chain on ODS activ failure

    All,
    We are loading and activating a CRM ODS (0CRM_PROH) in a process chain.  The process chain is set up to deliver a message if the ODS activation fails, but this is not happening reliably.
    For instance, yesterday a hex character came over from the source system causing ODS activation failure.  Strangely enough, the overall status of the request in the monitor was green.  Also, the activation step in the RSPC planning view was blue, not red as I would expect.  You could really only see the failure by switching to log view in RSPC, where it was clear the ODS activation had failed.
    Any thoughts on why the overall status of the request is green instead of red or yellow when the ODS activation fails?  Or, any thoughts on why no message is going out?  It's probably obvious that I'm new at interpreting the RSPC screens, so any general references on this topic would be helpful.
    Thanks,
    Bob
    P.S.  The ODS in question is set for automatic activation and automatic updating of data targets.  We are running BW 3.10.21, BI_CONT 3.30.16.

    Hello Diane
    We also had this issue, but with an older version (30B patch 7, works OK w/ patch 14).
    Anyway, to fix it:
    - create a new variant (let's call it V1 as an example) for the SAP program RSODSACT1
    - in your process chain, insert an ABAP call after the ODS load. Punch it RSODSACT1 as program and V1 for the variant
    It worked for us
    Good luck
    Ioan

  • The Job Failed Due to  MAX-Time at ODS Activation Step

    Hi
            I'm getting these errors "The Job Failed Due to  MAX-Time at ODS Activation Step" and
             "Max-time Failure"
    How to resolve this failure?

    Hi ,
    You can check the ODs activation logs in ODs batch montior >> click on taht job >>> job log
    for this first you check in sm37 how many jobs are running if there are many otehr long running jobs then . the ODs activation will happen very slowly as the system is overloaded .. due to the long running jobs ..this causes the poor performance of system ..
    for checking the performance of system .. you first check the lock waits in ST04..and check wether they are progressing or nt ..
    check sm66 .. for the no of process running on system ..
    check st22 >> for short dumps ..
    check Os07> to check the cpu idle tiem if its less tehn 20% . then it means the cpu is overlaoded .
    check sm21 ...
    check the table space avilable in st04..
    see if the system is overlaoded then the ODS wont get enough work process to create the backgorund jobs for that like(Bi_BCTL*)..jobs .the updation will happen but very slowly ..
    in this case you can kill few long running jobs which are not important .. and kill few ODs activations also ..
    Dont run 23 ODs activation all at a time .. run some of them at a time ..
    And as for checking the key points for data loading is check st22,cehck job in R/3 , check sm58 for trfc,check sm59 for Rfc connections
    Regards,
    Shikha

  • ODS ACTIVATION ERROR IN BI 7.0

    Hi,
    Iam Facing the problem in activation of ODS....
    When i loaded the data in ODS manually..The data was succesful and activation also ran well...
    But when see the same in the processs chain ....Activation of ods is in red...
    I repeated it...but still stays in the same red status...and gives the message
    ODS ACTIVATION FOR 'ODS NEME' TERMINATE.
    This is in BI 7.0...
    Can anyone p[lease guide me what is the actual problem...
    Thanks,
    Shashikanth.

    Hi Shashi,
    What's error mesg shows?
    Probably, this is becos of RFC connection failed.
    Regards
    Sanjiv

  • ODS activation

    Data is loaded correctly in ODS but it si givine RFC COMMUNICATION ERROR while activating.
    But the RFC connection OK.
    Moreover I have checked in RSRV transaction and it is successful there.
    what to do ? Please suggest.

    Hi,
    Does this ODS contain a lot of data? or have u loaded alot of data recently? Do you selectively delete from this ods? When the activation failed, were there many processes going on in the system? Did you try reactivating the ODS again?
    Usually when a lot of processes are goin on in the system activation fails with RFC communication error. If this is not the case, then I would suggest you get your Basis team to run DB Statistics on the ODS tables
    /BIC/A<odstechnicalname>00
    /BIC/A<odstechnicalname>40
    /BIC/A<odstechnicalname>50
    Check the Changelog table too.
    After stats you could try activating the request in the ODS again.
    Also Refer OSS note 559321 and 57374

  • Error during ODS activation- request deletion

    Hello Gurus,
    We had a problem during ODS activation, could you please help?
    We are on BW 3.1
    Activation of an ODS failed with the message, "Fiscal year variant MC is not maintained for calendar year 2009u201D, u201CError getting SID for ODS object ZODS_O02u201D and u201CError when assigning SID: Action VAL_SID_CONVERT table 0FISCPER."
    The expected data for 2009 didn't arrive, so the activation step in the proces chain has failed.
    What I've done is, just deleted the request from the ODS.
    But while this job was running, there was a short dump, and the same job was shown as cancalled under SM37. Though the request was successfully deleted from the ODS, it is showing as cancelled in SM37.
    I've given below the log details of the job.
    Job started
    Step 001 started (program RSDELPART1, variant &0000000003334, user ID ABCD)
    Delete running: ODS object ZODS_O02, from 310,818 to 310,818
    Delete is scheduled; Selection conditions were substituted
    Request REQU_4AZBURUGR09EXTAS8A9IRZUI4 successfully deleted from ODS object ZODS_O02
    ABAP/4 processor: MESSAGE_TYPE_X
    Job cancelled.
    Could you please clarify the reason for the short dump and for the job getting cancelled?
    thanks in advance,
    Raj

    Hi,
    As an help i suggest you can first check the corresponding message for the "Message type X" in transaction se91.
    Follow the below procedure for the same :
    1.Execute ST22 > Double click on any entries
    2.Go to Source Code Extract
    3.Locate u201C>>>>u201D and you will see Message
    i.e Message X041 (XX) in this example.
    - XX is the message class
    - 041 is the message class no. in the example above.
    4.Now open SE91.Enter the details we found from Source
    Code extract in ST22.Click Display
    5.Find the corresponding message.
    May be the message could much more elaborate your problem so it could be handeled properly.
    Thax & Regards
    Vaibhave Sharma

  • ODS activation failure due to uncaught exception

    Hello BI experts,
                              I have a issue while activation the ODS. ODS is failing to activate with the foll msg "ABAP/4 processor: UNCAUGHT_EXCEPTION"
           An exception occurred which is explained in detail below.
    The exception, which is assigned to class 'CX_SDB_ORA_PROGRAM_ERROR', was
    caught and
    therefore caused a runtime error.
    The reason for the exception is:
    An error occurred in the program:
    The occurrence of the exception is closely related to the occurrence of
    a previous exception "CX_SQL_EXCEPTION", which was raised in the program
    "CL_SQL_STATEMENT==============CP",
    specifically in line 31 of the (include) program
    "CL_SQL_STATEMENT==============CM002".
    The cause of the exception was:
    ORA-20000: Insufficient privileges#ORA-06512: at "SYS.DBMS_STATS", line
    2150#ORA-06512: at "SYS.DBMS_STATS", line 14112#ORA-06512: at line 1
    Can somebody guide me in resolving this problem ?
    Regards,
    Pradeep

    Hi All,
               Thanks for ur reply, but i want to highlight on some points.
    -> I have SAP_ALL authorization, so as per the authorization point of view i dont  find any problem.
    ->  My system has be upgraded to Support package 18.
                  So i strongly  have a feeling that  this might be a  oracle database issue. Any inputs on this reg the same would be highly appreciable .
    Regards,
    Pradeep