Old PP Orders Cancelled , but the material requirement still coming.

Dear Experts,
We are having many such orders which are cancelled in SAP but the material requirement keeps flowing.  Please suggest how to remove the material requirement flow?   as it is leading to our increasing non-moving stock without our control.
Thanks In advance.
Regards
Don

HI,
When you say "PP Orders Cancelled , but the material requirement still coming." Does it mean the dependent requirements reservation still exist in the system?
If that is the case, make sure the Orders cancelled are TECo'ed and Deletion flag is set. Teco will clear all the reservations,
If my understanding is not true , Please give more details.
Regards
Ratan
Edited by: Ratan on Jul 27, 2009 9:26 PM