Dear All,
Please advice. Is there any report (one for all ) which can show Status of project/wbs + available budget of a project. I tried cns43, cn41 and report s_alr. But it shows in different tcode/report. Hopefully there is a standard report that can show these in one report.
Many thanks in advance.
Nies

CN41 shows the Current Budget and not Original Budget.
If Available Budget in your terms means difference between Current Budget and Actual, you can include a column 'Difference' from menu.
Select the Column Budget 1st, Menu Edit>Comparison> Choose Actual Cost.
The output shows the difference and percentage. Problem now is you can't view the status.I can't think of anything standard which exactly gives the ouput columns you are expecting.
Regards
Sreenivas

Similar Messages

  • One report to check WBS and Asset number

    Hi All,
    Please advice. Is there any report to check WBS and asset number belong to ?
    Many thanks in advance.
    Nies

    Please let me know your exact requirement.
    But KOSRLIST_PR will show (if you have valid entries) the settlement receiver something like below with WBS element information and settlement details:
    WBS ISC/00002-1-02       RECEIVER WBS2-COMP 1000
    FXA 1000/700000132/0     RECEIVER WBS2-COMP 1000                   100.00  AUC        Act
    Regards
    Sreenivas

  • IDOC - Projects / WBS and Status

    Hi Expert
    In my testing I find that only realesed (I0002) project travel througth the master system into the host system.  Someone knows or has a list about the status of Project / WBS that the IDOCs takes to transfer by the master system???
    Thanks in advance.

    Hi Expert
    In my testing I find that only realesed (I0002) project travel througth the master system into the host system.  Someone knows or has a list about the status of Project / WBS that the IDOCs takes to transfer by the master system???
    Thanks in advance.

  • Is there exist report to check the job start date restriction calendar ID?

    Hi There,
    In SM37, there are many jobs list there. If we choose one job of them, and click Jobchange, then we access in the screen for change the job status. Then click button Start condition, and there is a dialog which name is Stat time will pup up. And click button Date/Time, there will be a new button appears in the bottom. Click Restrictions, You will see a new dialog box which name is Star Date Restrictions. There is a field which name is Calendar ID in selection portion Factory calendar.
    Is there exist one report to check all the jobs calendar ID instead of to check one by one?
    Thanks!

    Hi,
    please have a look into table TBTCO, restricting by field CALENDARID.
    I hope this helps. Kind regards,
    Alvaro

  • Report to check project-wbs-requesting co.code-company code in assignment

    Dear All,
    Is there any standard report to check Requesting co.code and company code (assignment tab) by project and wbs. I tried CNS43 but there is no requesting company code.
    Can we use SQ01 to create this one ? Any one can advice me how to make query for this concern.
    Please advice.
    Thank you
    Nies

    Hi,
    You can use SQ01 for this. Query the table:PRPS.
    The fields you require are:
    PRPS-PBUKR
    PRPS-ABUKR - Requesting company code.
    Muraleedharan.R

  • Is there standard report to check actual (GR) based on project/ WBS

    Hi All,
    Is there any standard report to check actual based on project / wbs. At the moment i know the tcode CJ74.
    Is there any other report ?
    Thank you.
    Best Regards,
    Denis Evitanto

    Hi,
    Report (S_ALR_87013542) is most effective report for projects as planned cost / actual cost / Project profitability will be obtained from there.
    Planed cost of the project will be obtained from the report. E.g. if you are doing project costing through Cost elements, in the mentioned report, all the cost planned through various Cost elements will be obtained. After posting actual cost to project, there can be comparison of planned cost Vs actual cost.
    Hope this will help you.
    Best Regards,
    Rakesh Pradhan

  • Report to check Standard WBS link to which standard network and activity

    Dear All,
    Is there any way or standard report to check standard WBS (cj93) link to standard network/activity (CN03).
    Normally we create project by using template existing, we would like to check the structure. Is there any way to check the standard template for it ( WBS template link to network/activity template).
    Thank you.
    Nies

    Hi,
    Please try this:
    1. Tcode : CN41
    2. Change database profile: In that in the origin check mark the Standard structure. Continue..
    3. At the bottom of the selection screen check mark the standard structures.
    4. In the selction area for the Project hit F4 and  select the project based on the standard WBS Element.
    5. Exceute the report.
    Hope this is useful.
    Reward points if found useful.
    thanks..

  • What is the BAPI Name to chg status of Project def/WBS element.

    HI ALL,
    Can anybody tell me is there any BAPI which will change the
    status of Project Definition or WBS element and  also update
    JCDS table data?
    for eg. TECO(technically comlpited)-> CLSD(closed)
    I want to do this by any FM instead of BDC.
    can anybody help me inthis regard?
    Thanks,
    MM

    Hi Deepak,
    We have tried the given BAPI, but it is only used at WBS level.
    our requiremnet is that when Project definitions system status is changed, then it should chg the system status of WBS as well as Network..  We got the BAPI for this named"
    BAPI_BUS2001_GET_STATUS.. this is used to chg the status of Project and corresponding WBS but does not chg the Network. but in this BAPI also we are passing following
    project but we are getting error  like
    Project _def: 40co-9001937
    undo_system_status: DLFL
    when execute, it given error like Error in processing FM was not executed.
    can any one tell me why i am getting this kind of error
    and also other BAPI name which will chg the status at all 3 levels like Pro Def, WBS and Network..
    Regards,
    MM

  • Standard report to check MRP status

    Hi,
    Is there any standard reports to check the materials based on the MRP status? (Eg: Materials that are under A(Free and avilable) etc etc)
    Im using SAP 6.0
    Thanks in advance.

    Hi,
    1. MD04 - Stock requirement list
    2. MD05 - MRP list
    3. MD06 - MRP list collectively
    4. MD07 - Stock requirement list collectively.
    Please see if need anything more.
    Regards,
    Anil

  • Commitments check before making project status TECO

    Hello PS Gurus,
    I have a requirement In projects. As per standard system, when we change the status of the project from TECO to CLSD the system checks the commitments, balance as well as actual cost, if all these conditions are fullfied the system allows to change the status or will not allow.
    If this same check i need to apply at the time of changing the status from REL to TECO. Is it possible? If so how can i do it?
    Either by User status ?
    Regards,
    Tushar

    Go to BS23 transaction, look for CLSD transaction and then look for business transactions that are allowed and not allowed for this system status.  After yoiu take note of these business transactions, for the user status you have created, allow and disallow the same business transaction.  This takes care of the requirement.

  • Set WBS status in Project System from CRM Status

    Hi Gurus
    I am figuring out a solution for how to influence WBS element status in Project Systems in ECC from the campaign/Marketing plan status in CRM. Has anyone done it before or is there any BADI for it.
    Your help is greatly appreciated.
    Regards
    -MP

    Your yourself answered your question.
    "Can we create our own list of system status"
    "Our own" status creation and maintenance feature within SAP in called "User Status".
    Please follow link below to have additional information regarding system status.
    link: [http://help.sap.com/saphelp_erp60/helpdata/en/a9/8a853488601e33e10000009b38f83b/frameset.htm]

  • Changing the dropdown values for one of the fields in CHECK STATUS query

    Hi,
    We are on SRM 7.1.
    In the CHECK STATUS transaction,in the selection screen(QUERY),there is a field called "ROLE" which has teh dropdown values of "APPROVE BY ME","REJECTED BY ME" and "GOODS/SERVICES DELIVERED TO ME".Is there any way some of these drowpdown values can be removed?
    Please advise.

    hi nmsrm1234
    i have a document for this issue.
    but i don´t find this document in internet. it is called : CUSTOMER-SPECIFIC UI ADJUSTMENTS IN SRM 7.0 WEBDYNRPO ENVIROMENT / META DATA HANDLING CONCEPT.
    if you can find it, you will get an idea to resolve this issue, if you will no have luck, please get me your mail, and i will send you the document.
    regards.

  • Report to do check status of sm37 jobs

    Hello,
    I wold like to create a job that checks the status of all running jobs on sm37 (the same as when we go to SM37,job, check status), can anyone tell me the name of the program that does that?
    Thanks,
    Pedro

    Hi,
    Good Day,
    TRY SM50 Transaction.  Program Name : RSMON000_ALV.
    Best Regards,
    Suresh Kumar K
    Assign Points if its useful.

  • Has anyone Connected a Crystal Report directly to a Microsoft Project file (MPP)?

    Post Author: Brian Morris
    CA Forum: Data Connectivity and SQL
    Iu2019m aware I can save Microsoft Project Files (MPP) to an Access Database, Excel document etc. and there are ways to connect to a Microsoft Project Server.
    I wanted to know if anyone has managed to connect directly to one though. Currently we use MPPs to report project status and other deliverables, and itu2019s been an annoyance to have to save the project file then export the data over into a new excel document when ever we have changes (since not all users have project or need all the data in the file).
    Preferably, a user should be able to save that project file and anyone that has the Crystal report should be able to run the report against the MPP file. In addition to this, it would be extremely helpful in getting a formalized and nicely formatted report when running reports against rational and MMP files, thus giving an alternative from SODA reports in Microsoft word, which doesnu2019t always work well.
    Thanks!

    Post Author: Brian Morris
    CA Forum: Data Connectivity and SQL
    Ok, I answered my own question on the connection issue, but I'm having issues with the predefined fields that enter into the report. The Database Expert shows the correct table names, but when I select them and look at the fields, they are all showing fields that are part of the "Project" table. when I use "Add Command" and use SQL to do a "Select * From TableName" ,where TableName is the name of the respective table, I get the data I'm looking for. Has anyone else run into this error? Is the error on Crystal Reports side or the Data provider's OLE DB driver? Has anyone with a fully patched system encountered the same errors?
    Current SetupCrystal Version: 11.0.0.1282CR Professional; Product Type:FullOLE DB Driver: Microsoft Project 10.0 OLE DB Provider
    I have pasted my findings below, hopefully other people won't have the same issues I did trying to find this information. if anyone else wants to test and see if they get the same issues I did it would be greatly appreciated.
    Connecting a Crystal Report XI to a Microsoft Project File (MPP)
    Prerequisites (as I know them)
    -          Have an installation of Crystal Reports on the machine (a given)
    -          Have Microsoft Project 2000/2003 installed OR  the Microsoft Project OLE DB provider which is installed with Microsoft Project (NOTE: Microsoft 2007 supposedly no longer supports OLE DB and requires an OLAP cube be made or a SOAP connection be used, which I donu2019t deal with personally)
    Creating the connection
    Start Crystal Reports
    Click u201CBlank Reportu201D on the start page
    in the u201CDatabase Expertu201D window, under u201CAvailable Data Sourcesu201D, Select u201C+u201D next to u201CCreate New Connectionu201D
    Select the u201C+u201D beside u201COLE DB(ADO)u201D
    If a u201COLE DB (ADO)u201D  window does not come up, double click u201CMake New Connectionu201D 
    In the u201Cprovider:u201D box Select the u201CMicrosoft Project 10.0 OLE DB Provideru201D
    The name may be different depending on the version of project you install and the patch you have on the machine
    Select u201CNext >u201D
    Under u201CDatabase:u201D copy/paste in the path and project file name
    I donu2019t believe the other fields u201CData Source:u201D, u201CUser ID:u201D, or u201CPasswordu201D need to be filled out, and in fact, I got an error when entering in data into them
    Example: u201CC:\Projects\Project Name\Current Schedule.mppu201D
    Select u201CNext >u201D
    In the Advaned information window, verify the project Name is the path of the project.
    I have not found the use of u201CEnterprise Modeu201D (default: 0), u201CAlways Loadu201D (default: 0), u201COLE DB Servicesu201D(default: -5), or u201CEnterprise RUID Listu201D (default: blank), removing them or changing them did cause errors though.
    Click u201CFinishu201D
    Adding in Tables and extracting data
    You now have a connection to the project File you listed. There is an issue Iu2019ve found though that all the tables you see listed are filling their fields in from the u201CProjectu201D Table, rather then their respective tables (Example: u201CAssignmentsu201D is pointing at u201CProjectu201D rather then the obvious connection u201CAssignmentsu201D). You can, however, use the u201CAdd Commandu201D and select the table you want with just a little SQL code:
    Select *
    From Assignments
    After creating the command, highlight it and hit u201CF2u201D. You should be able to edit the name and change it from u201CCommandu201D to something more meaningful. At the current time Iu2019m unsure if the issue with the default tables all pointing toward the project table is an error on the provider side or Crystal Reports end, and if one of the new patches will fix it. I will update this document accordingly when I have more information and do more testing. I will note however, there is no way to change which table these preset fields point to.
    Thank you for your time.

  • Need to Create a Check for Plant in WBS & Plant in Network

    Dear Guru's,
    While creating Project (CJ01) my users are creating in a Plant, and while creating network for the same project/WBS, they are using different Plant Code.
    Since my Profit center is related to the plant in CJ01,
    and because of wrong Plant in network, all my PR/ PO is going in a different Profit center, which is creating a huge problem while auditing.
    I need to Create a Check for Plant in WBS & Plant in Network...!!
    Kindly suggest me the ways to do it and how to do it...

    Hi Deepa,
    The Check you are trying to create between Plant defined at Project def and network level that should be same can be achieved through validation at the network level by using a user exit at network level.
                    While creating the network you can change the plant value not equal to the value at proj def/network profile may be one of the reason is since the network type is defined for more than one plant (OPUV).
                    While creating validations at network level we do not have the option of setting the prerequisite/check  using WBS or Proj def fields (i.e. PROJ-, PRPS- fields)    so we need to create a user exit at the network level.
    I am not sure but logically u can have a user exit for both prerequisite and check steps of the validation.
    You need to create the user exit in program ZGGBR000.
    Please take help from your Abaper for the same.
    OPSI-Network header-Validation- Step - Prerequisite u2013 Check u2013 Message.
    Prerequisite
    If Proj Profile = u2018XXXu2019 and Network Profile = u2018XXu2019 (or as per your logic if need be use a exit)
    CHECK.
    PROJ-WERKS = CAUFVD-WERKS   (This logic needs to be defined in user exit and set the same user exit at the check.)
    Once you define the user exit in ZGGBR000, it will be available in the tab u2018exitsu2019 at the Prerequisite and Check levels.
    The name of the form pool (e.g., ZGGBR000) that contains your user exit must be stored in table T80D.
    It is important that you make declare the code generation program for your user exit; how many and what type of parameters you are using for the user exit. You do this by entering your newly defined user exits in the form routine GET_EXIT_TITLES. Found in program ZGGBR000.
    Check with your Abaper to check on all the aboveu2026
    Message:
    Plant at Network level should be same as at Project def level.
    Hope it helps you,All the best..
    Regards
    Vinayak.

Maybe you are looking for

  • Enter command in Classical Report

    Hi ,   I have a classical report with one of the fields editable , when the user modifed  one of the rows and presses enter i want to do some processing , how can this be implemeted. i.e. how can i handle ENTER command in a classical report. Regards,

  • Wy does firefox open a new window when i click on "open link on a new tab"?????

    the only time i shutdown a window is when i shutdown firefox. having mutiple windows invites to mistakes. please fix.

  • Dynamic in SELECT statement

    Hi, I have a SELECT statement where I need the year to be dynamic. The user select a range of months where the script should execute and based on the input I would like to create a dynamic SELECT statement. My SELECT statement looks like: *SELECT(%TI

  • "Connection refused" when using Java client for Web Service

    I deployed a web service to Weblogic Server 7.0 running on Windows 2000. I can use IE browser to see its WSDL perfectly but when I run the Java client, the proxy method call generates the following error: java.net.ConnectException: Connection refused

  • Object locked by ALE Remote

    Hi all, My load has been fail bcoz of Object locked by the ALE REMOTE. But when i saw der r some LUWs Struct in the TRFC so i have executed them n my load is successfull. Now the issue is the request is Green in the RSMO and all the records has been