One Step Stock transfer

Hello All,
Can you please let me know the answer to the problem that I am facing.
Can we transfer the stock from one plant to another plant in one step stock transfer procedure taking the reference of STO already created ?
I know that it is done in MB1B using Movement type 301. But the question is, can I take the reference of STO created for transfering material in One step Procedure.

Thanks for Replying...
I have checked the settings for both these plants and the One step Procedure is selected and the document type is also UB.
As soon as I create a STO between plant 1000 and Plant 1200, the material starts showing in as open order quantity in plant 1200.
How to physically transfer the goods between these two plants taking the reference of STO ?

Similar Messages

  • 2 Step Stock Transfer Using WM Transport Order??

    Dear SAP expertes,
    I have a problem, I think a lot of you too; that is stock transfer in 2 steps from one storage location to another (mov. types 313-315), but using o referencing a reservation.
    SAP says that is not possible create reservations for 2 step stock transfer in MM, but also says use "Stock Transfer Orders" instead, that means use module WM.
    Do anyone could transfer stock from one storage location to another using WM Stock Transfer Orders? I tried, but couldn't make it. In anyone have documention to do this I will appreciate it a lot.
    Best regards,
    Favio.

    Hi Jürgen L.
    I was checking SAP Note  "28692 - MMIM: Reservation for a two-step stock transfer", and you were right, they say "Use the stock transport order instead of the stock transfer reservation".
    I confused with WM stock tranfer order, but I want to ask you if you have used UB transport order between storage location of the same plant?
    Best regards,
    Favio.
    Edited by: Favio Del Castillo on Sep 22, 2010 5:01 PM

  • Two step stock transfer process

    hi All,
    i want to transfer material XYZ from plant AA to plant BB  in 2 step stock transfer. Qt= 2000
    So first i am trying to remove stock from plant AA in 303 movement type.
    system throughing error message " Deficit of PL Stock in transfer 48000 PC:    XYZ       BB
    ERROR Message no. M7 021
    after analysis i found that in plant BB , in Stck trans.(plnt)  , stock is showing  (  - 50000)
    i wonder how this stock got negative.
    please help resolving this issue.
    any help will be highly appreciated.
    thanks in advance
    regards,
    Anubhab

    hi Pankaj,
    in both plant AA & BB , negative stock is allowed.
    now i found that if i put the quantity equal to or more than 50000 , then system not giving error.
    but if i put a smaller qt , say 1000, then system deducting it from 50000 & showing deficit 49000  at plant BB.
    so the question is can't i transfer less than 50000 qt to BB from AA?
    Also what is meaning of 50000 qt showing as negative in stock in transfer stock ? does it mean that with out posting 303 at plant AA , customer has posted 305 at plant BB?
    Please help me understand. thanks .
    regards,
    anubhab

  • Imovie to one step idvd transfer

    I used the easy imovie option to transfer 60 minutes of minidvd data to an external hard drive..it seems to play well..However when I then transferred the movie to one step idvd, the sound track did not transfer..or rather the track is garbled..Is there a limit to the size of the imovie..or is it the external hd that is the problem.
    Thank you

    Several ways to try to fix things:
    1) Import into iMovie and "extract audio" then try again, or even export after extracting audio to full quality DV - and use that file in iDVD.
    2) Import to iMovie. Set your camera back to 16bit in VCR mode, and then export to tape. Then re-import into iMovie.
    Or these:
    http://danslagle.dvmix.com/mac/iMovie/audio/1001.shtml
    http://docs.info.apple.com/article.html?artnum=61636
    BTW I don't think any version of iDVD liked 12 bit audio......
    John

  • Two step stock transfer

    If I want to transfer material from one storage location to another, through MRP system creates reservation with movement type 311. But I want to have reservation with movement type 313 so that it will be two step and material can be transfered to transit.
    How can I set this through configuration ?

    Hi Balaji,
    Chk the link below :
    http://help.sap.com/saphelp_46c/helpdata/en/a5/63385543a211d189410000e829fbbd/frameset.htm
    BR,
    Krishna

  • Inter Company Stock Transfer Configuration

    Hi,
                    When I assign customer in assign shipping data to plants, request is creating. So whether I have to create the request and transfer the same to production or quality or is there any other way to assign customer in either quality or production? Because I have to create the customer master data in development. Please Reply..

    The cross-plant internal procurement of materials can be carried out within one company code (inter-company) or by using several company codes (cross-company). This process can be dealt with using standard functions, such as material requirements planning, purchase requisitions, stock transport orders, transportation planning, and the handling of internal deliveries.
    Process Flow
    This scenario consists of the following steps:
    One-step stock transfer
    Creating stock transport order
    Posting goods issue for stock transport order
    Checking the status of the stock transfer
    Receiving transferred materials
    plz refer following link for detailed process
    http://help.sap.com/bp_blv1600/V5600/BBLibrary/HTML/135_EN_IN.htm
    Regards,
    eswarmanu...

  • Stock Transfer from one location to another through outbound deliveries

    Dear GURUS n EXPERTS,
    We have 5 warehouse and one manufacturing plant. Till this time we use two step Stock Transfer method to transferring stock from plant to ware houses.
    Now, we want to use Shipping & Transportation System to to calculate transportation cost. But this system consider only outbound deliveries. So, our requirement is:
    1. Create the outbound deliveries, but no billing.
    2. Receive the material at warehouse against this outbound delivery but do not go for invoice booking.
    How can we achieve it. Please guide us.
    Thanks,
    DSC

    Hello,
    You may see the IMG path SPRO->Materials Management->purchasing->Purchase Order->Setup Stock Transport Order.  Here, the most important ones are Assign Delivery Type and Assign Purchasing Document Type. Availability check, Delivery tolerances etc. are optional. You need shipping point to be created using transaction OVLZ.
    Thanks,
    Venu

  • What is Cycle or steps to create Stock transfer between plants.

    What is Cycle or steps to create Stock transfer between plants.
    Reply with T Codes & Justify

    Hello RM
    We can transfer stocks within a company code between 2 plants using 3 methods:
    1) Using single step simple stock transfer (Mvt Type 301).
    2) Using two step stock transfer (Mvt Types 303 and then 305).
    3) Using a stock transport order(STO) again it is based on 2 things:
    a) r u using STO with delivery or
    b) without delivery.
    Though the first two steps are very simple to process but using STO has its own advantages: 1) Quantity in transit can be monitored 2) delivery costs can be entered in the STO.
    First 2 steps (single step and 2 step plant to plant transfer) can be done using MIGO tcode , selecting stock transfer and entering the relevant mvt types.
    would like to tell you about STO as it is an important process.
    STO without delivery, the following functions are provided to support the Internal Stock Transfer without Delivery :
    #Create Stock Transport Order
    #Post goods issue for stock transport order
    #Post goods receipt for stock transport order
    Config Step required before processing above steps:
    Setting Up Stock Transport Order: Purchasing Document Type, the purpose of this activity is to specify which document type is to be used for a certain combination of supplying (issuing) plant and receiving plant.
    Path go to SPRO--MM-Purchasing---PO-Set up STO-----assign doc type, one step procedure, underdelivery tolerances.
    There you have to enter your supplying and receving plant with the Purchasing doc type( UB).
    Now the process:
    1) Receiving plant will create a STO towards issuing plant.
    2) Issuing plant will transfer material from their unrestricted use stock to stokc in transit using mvt type 351.
    3) Receiving plant receives the goods using MIGO mvt type 101.
    Regards
    Yogesh

  • Hai   Stock Transfer 2 Step

    Could any body explain me detailed....scenario of Two Step Stock Transfer....pls do explain with process

    Stock Transfer Will be b/w  Plant to Plant or Plant to Storage Locations.   First U go to ME21N and take as Purchase order UB and put supply plant and Purchase org. details, mention the line item details and Save it.
    2. Go to VL10B, remove the shipping points and Dates, go to Purchase Order tab give the Purchase Order no. and make Generate(f8).  It will goes to take a screen, and select that, click on Background process, show internnally it takes to make outbond delivery, Now u click on Show/Hide Delivery, immediately it gives up the Delivery no.
    3. Just Double click on Delivery no. u can enter in Delivery document.  And make PGI.
    Confirm me if i am wrong

  • Error : T161W: Vendor+subcontracting vendor not allowed for 2-step stock tr

    Hi Gurus,
    When we creating a STO to sub contractor vendor ( in the delivery address tab we are entering the vendor # and activating the SC vendor check box)we are getting the error message as "T161W: Vendor+subcontracting vendor not allowed for 2-step stock transfer".
    Message no: MEPO140
    Note:
    The STO is creating with out error in ECC 5.0 for the above scenario but when i'm  trying  the same in ECC 6.0 in another system I'm getting this error, Can any one please advice.
    Thanks in advance,
    Sai

    Hi Charlie
    I had same issue and we sloved it. but i have one more issue here.
    We have created Po and SC Vendor is not check marked. When we go into the change mode of Po i can't see the field at all. but its availalbe in disply mode.
    I am using ECC 6.0, Please suggest why this is happening. I need to put check mark for SC vendor.
    thanks,
    Raju

  • Query on stock transfer between plants

    HI guys,
    In stock transfer storage location to storage location in one step, all stock types are allowed. Whereas, in two step, only unrestricted stock is allowed. Can I know the reason why!?
    In plant to plant stock transfer either one step or two step, only unrestricted stock is allowed. What is the reason?
    Regards
    Prasanna

    in plant to plant stock transfer either one step or two step, only unrestricted stock is allowed...
    It is not true.
    In intracompany two step stock transfer you can post GI from unrestricted, QI and blocked stock as well (MIGO GI for PO, in "Where" tab you can specify the stock type) and you can choose in which stock type you want to receive the goods (MIGO Goods receipt for PO > in "Where" tab you can specify the stock type).
    So, 9 combinations are available.
    Re: Stock tranfer order with block stock
    Regards,
    Csaba
    Edited by: Csaba Szommer on May 22, 2009 12:40 PM

  • Stock transfer between plants without STO and storage locations

    Hi.
    In case of stock transfer betwen storage locations with one step it is possible to do stock transfer between different stock types. But in Two step it is only possible to do stock transfer from unrestricted to unrestricted.
    In case of Stock transfer between Plants without STO in one and two step stock transfer, it is possible to do stock transfer  from unrestricted to unrestricted.
    Is there any reason for this?

    Hi
    Thanks for your reply. But i could not understand the sentence - But this is not possibles with 2 step procedure. becasue 2 step is recored will be maintained . In 2 step it not possible. Can you please eloborate on this
    Regards,
    Vivek Swarnapuri

  • Stock transfer between plants two steps 303-305

    Dear All,
                    We are using version SAP 4.7 we are using stock transfer scenarion between plants two steps. 303-305 source plant they will remove the stock  with 303 movement in the receiving plant they will receive the goods against the 303 document number.
    at the time with 305 movement type one document generated in that document table MKPF 303 reference number should be updated but in the 305 document the reference document 303 not updated in table MKPF.
    why?...any updations required. because i want to develop an user exit at the time of Goods receipt with 305 movement in the receiving plant now it is allowing posting date as <= 303 document posting date it should be allow only >=303 document posting date at the time of 305 document generation in the receiving plant.
    in MKPF table the reference document is not updating ....any ideas....
    im using the standard Enhancement :MBCF0002
    EXIT_SAPMM07M_001.
    Regards
    Anand..

    Hi..
        then how can control.
    receiving plant 305 document posting date is should be greater than or equal to source plant 303 document posting date how can achieve this?.
    via user exit in the reciving plant 305 document the reference document not updated. how to achieve this?...
    any ideas..
    Regards
    P.Anandhakumar

  • Stock Transfer from one plant to another

    Hi Gurus,
    We have this scenario
    My client is doing Make to Order business. All materials planned under MRP and low value items are planned under CBP.
    My question is if one plant require materials from MRP planned materials then how we make the stock transfer with billing.
    Suggestions will be appreciated.
    Thanks & Regards
    Pranaya

    hi
    Follow the steps :
    1.Create a vendor for the company code of receiving plant, using account group :0007 using T-Code XK01.
    2 Assign this vendor to Delivering plant
    Go to XK02 >Purchasing view>Extras>Add. Purchasing data>Plant
    3. Create internal customer with the sales area of the vendor. Go To XD01
    4.In Pricing procedure determination relevant to STO, assign document Pricing Procedure and customer pricing procedure appropriate for STO to get the pricing in the invoice.
    5.Maintain condition records for the relevant pricing condition.
    6. Some more setting for STO: Go to MM> Purchasing > Purchase Order > Set up STO> define shipping data for plants > Go to Receiving plant >assign customer here & Supplying SA (for billing) to Receiving plant here
    7. Go to MM> Purchasing > Purchase Order > Set up STO> define shipping data for plants > Go to Supplying plant and assign the sales area of receiving plant.
    8. Go to MM> Purchasing > Purchase Order > Set up STO> assign delivery Type & Checking rule
    Assign the delivery type to document type. In this case, Delivery type NLCC is assigned to Document type NB
    9. Go to MM> Purchasing > Purchase Order > Set up STO>Assign document Type, One step Procedure, Under delivery tolerance
    Assign the document type NB to supplying plant and receiving plant
    10. After all settings , Create the STO using T-Code:ME21n and Save.
    11. Create Delivery :VL10G
    Click on the Background Button after selecting line item
    A message is flashed : See log for information> next Click on Log for delivery creation Button >click on line item>click on document button to get Delivery document No
    12. Picking, PGI:[VL02n
    13. Billing:VF01n
    Save the document and its done
    reward points if helpful
    regards
    chetan

  • Stock transfer from one co.code to another.

    Hi,
    What is the process of stock transfer order from one co.cde to another co.code (not with in the plants of a co.cde)
    Also please explain the financial effects on each steps on both side.
    for Stock transfer order i need to configue the cross company code transaction.
    Regards

    Company code to company code u have to treat the another company as Vendor/Customer in each company code books. Then the process is same.  Sale order, delivery and billing to the Customer(2nd company code i.e. stock receiving company code).  Then in receiving company code based on the delivery document of other company code GR can be made. and IV.

Maybe you are looking for