One Step Workflow Activation for Shopping cart in SRM 7.0

Dear Experts,
On working to EXtended Classic Scenario, I need to configure one step approval for shopping cart in SRM 7.0.
Currently it is providing me Auto Approval  by default and based on it PO is being created. I need one-level manager approval  shopping cart.
I am working in Demo System of Extended Classic Scenario, I need only one step approval SC without any condition.
Kindly tell me the configuration steps in SRM and please tell me one more thing is there  any need of  BADI or other coding for one-step approval?
Thanks in Advance,
Regards
Pawan Keshwani
Edited by: pawankeshwani on May 25, 2011 6:22 PM

Hi Ashutosh,
Thanks for quick reply.
As per your comment when i am tring to activate /SAPSRM/C_SC_600_001_SP04  by t-code SCPR20, But It shows me a information pop up Maintain the client role and then Activation is Cancelled.
Kindly tell me what i am missing or any other prerequisite step to do for this BC Set Activation.
Thanks
Pawan Keshwani

Similar Messages

  • Issue in One step workflow activation for Confirmation in SRM 7.0

    Dear Experts,
    On working to EXtended Classic Scenario, I am configuring one step approval workflow for Confirmation (good receipt)  in SRM 7.0
    I have standard customisation for Confirmation and activated below object for one-step approval :
    BUS2203  SAVED                 WS10400002                          Event Linkage Activated
                                             (one-step approval)
    When I am creating a Confirmation with respect to PO in portal,  It is showing Approval Pending  but  It is not going to Manager for approval. While  creation of shopping cart (one step approval) is working fine and SC is going to same Manager for approval.
    Kindly suggest me, what else required for it.
    Thanks in advance,
    Pawan Keshwani

    Dear Expert,
    I am using Application Control Workflow for both SC and Confirmation. Issue is resolved now by this link
    No workflow started. Application error occured
    Thanks for your Reply.
    Regards,
    Pawan Keshwani

  • Workflow retrigger for shopping cart

    Hi All,
    What is the procedure to retrigger workflow manually for shopping cart?and what the precautuions to be taken when retriggering workflow for SC.
    Thank you
    Regards,
    Yshu

    Hi,
    What is your business scenario, you can trigger the workflow again when you change the shopping cart once it is created.
    This can be:
    1) When users create a shop, hold and then on a later date they want to change the shop and complete the action.
    2) When the shopping cart is created always the employees need to have the change functionality till the approval takes place for that particular shopping cart.
    This can be achieved by using the different parameters in the BBP_WFL_SECURITY in the Personalization tab in the SU01 , Personalization Object Key and the authorization level 0,1,2,3,4
    Best regards,
    Sridhar

  • Is workflow mandetory for shopping carts and contracts approvals srm7

    hi
    in SRM 7 are workflows mandetory for approvals of Shopping carts  andContracts?
    I understand you need an approved workflow to turn a SC to a PO.
    is workflow required for approval of  shopping carts or can approvals be done manually
    you create the SC and you communicate and  look at  the sc and approve it
    Same type of question for workflow in contracts  for approval ?? is it mandetory or optional (manual achieve approvals)
    cheers
    alex
    Edited by: Alex Waiyaki on Apr 23, 2010 8:24 PM

    Hello Alex,
    SRM 7 has process controlled workflow and its easy to configure for simple requirement.
    Yes, Shopping cart approval will be required to change status of SC to approved. Though it can be as simple as auto approval. SAP delivers number of standard BC Set for approvals including auto approval of SC.
    SRM also has a option of adding approvers & reviewers. SC creator can add approvers & it goes for approval to added approver.
    Hope this helps.
    Thanks
    Ashutosh

  • WorkFlow Setting for Shopping Cart

    Hi All,
    I am new to SRM WF, I want to configure SC two steps WF. Please tell me how to configure it, how the approver for particular user id determined etc..
    Thanks in advance.
    Regards,
    Ajay

    What version of SRM you are working on? If you are in higher version  SRM 5.0 the the workflow needs to be configured using BRF functionality. Here is some link for your reference.
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/4c/0eae42edc6b211e10000000a155106/frameset.htm

  • Workflow retriggered for Shopping cart

    Hi ALL,
    Scenario is like SC created and approved. it was converted to PO and inovice also done. Surprise thing after one month work flow was triggered for this SC. As we know once subsequent documents are created then system will not allow you to open SC with change mode. No question of event triggereing .
    Could you please tell me some transaction to check what is the reason for work flow triggering . WF TEMPLETE IS stndard one.
    Regards
    Ramakrishnaiah Y

    hI ,
    we deleted created work items by using funcion module. we could not able to trace how those were triggered.
    Regards
    Rama

  • Dead Line Monitoring for Shopping cart approval(SRM 7.0 Process controlled)

    Hi Friends,
    I am using SRM 7.0 Process controlled Workflow. I need to do below.
    Dead Line Monitoring details are given below.
    If the approval workitem is not addressed in 3 business days by Approver, the approver would get reminder email notification. If approval Workitem is not addressed in 5 business days by the approver, then an email notification is sent to requester,approver and the workflow administrator.
    How to obtain this. Please help me.
    Thanks,
    Balaji.T.

    Hi Masa,
              Thank you for your input.
    You mean, shall we use BADI  BBP_ALERTING for deadline monitoring.?
    Infact, i have used
    SRM Server->Cross-Application Basic Settings=>Event and Event Schema for Alert Management->Define Event Schema
    In that i specified
    WF_COMPL_LATEST_END->Message(low)->APPROVAL_DEADL_NOTIFIC_NEW  : 24 hours.
    But it is not triggering for dead line Monitoring(24 hours Later).
    If any body faces this same problem, Please let me know.
    Thanks,
    Balaji.T.

  • How to re-start the workflow for Shopping carts in WAITING status

    Hi
    We are using 1-step approval work flow, and we get some strange issue. We can add approver in the workflow, but after we click order button and back to check status again, sometimes there will be "Ad-hoc agent not found" issue. Do you know how to solve?
    And one workaround for user is to re-add the approval, and sometimes the shopping cart back to normal. But sometimes, after we add the approver, the shopping cart are in waiting status:
    Workflow Item:
    Workitem-ID 000000714642
    Task WS10000276
    Text One-Step Approval: Value limit: Shopping Cart
    1000114698
    Status WAITING
    Statustext Waiting
    Date 13.06.2008
    Time 10:41:22
    So may I ask how to re-trigger the workflow?

    Hi,
    Thx for that. I need to trigger the Approval workflow to go the the approval manager.
    Can u give me the document on this? thx,  kerry.liu [at] ap.effem.com.
    Thx very much
    Kerry

  • New document type for shopping cart /PO

    Hi Gurus,
    I have created a new transaction type ZSHC for Shopping carts in SRM. I have given it a new  number range.
    while creating a shopping cart , how do i ensure that my shopping carts get created with this transaction type?
    is there any attribute which controls this ?
    Regards,
    Mangesh

    Thanks Shrini for your response.
    BADI "BBP_CREATE_BE_PO_NEW" does not exist in SRM 4.0. The corresponds BADI in SRM 4.0 is "BBP_CREATE_PO_BACK".
    The documentation of this BADI says that it can be used to change all data TRANSFERRED TO THE BACKEND SYSTEM to create a purchase order.
    I would want the document type to be selected when the PO is created in SRM and not when SRM transfers the PO to the backend. Because in that case I fear that SRM can have one doucment type and R/3 would end up having different document type for same PO.
    I will activate the BADI and keep the thread posted.
    Thanks
    Venkatesh

  • N-step approval workflow for Shopping Cart-WS14000133

    Hi Experts,
    We have 5-6 levels of approvals for Shoppoing carts.All the SC needs to be approved by 5-6 managers based on their approval limits.All the approval limits are assigned at the Role level .(We have created Z roles)
    Please let me know how and where to define the roles in BADI to activate the N-step approval workflow for Shopping Cart-WS14000133
    Thanks,
    Venky

    To add to Masa's reply.
    This Badi is well documented by the online help and it even comes with example implementations AND it is mentioned in full detail at help.sap.com
    Kind regards, Rob Dielemans

  • Problems with Auto approval workflow (WS 10000060) for shopping carts

    Hi SAP Network community,
    I have got a problem with the auto approval workflow for shopping carts.
    Basically the workflow approves the shopping cart once it was created.
    But then the related Purchase Order remains in Status held. If the PO gets ordered manually then it is not transferred to the R/3 backend system.
    For testing purposes also the one step approval workflow was activated. If the shopping cart gets approved by clicking into the detail approval screen (not by approving through the green tick box in the shopping cart overview) then the PO gets ordered and transferred to the backend system as normal.
    But if the shopping cart gets approved by using the green tick box in the shopping cart overview then the same problem occurs as described for the auto approval workflow.
    The system version is SRM 4.00
    Did anybody have the same or similar problems with the auto approval workflow and what could be the reason for this problems.
    Thanks in advance,
    Robert

    Hi
    Which SRM Workflow Scenario are you using (IS it Item level workflow or Shopping cart level Workflow) ?
    Are you using customized SRM Business workflow or Standard SRM Workflow ?
    <u>Please go through these links as well.</u>
    http://help.sap.com/saphelp_srm50/helpdata/en/2c/e68d406b305537e10000000a1550b0/frameset.htm
    http://help.sap.com/saphelp_srm50/helpdata/en/eb/289f4099852e54e10000000a1550b0/frameset.htm
    Incase you are using Standard SRM Workflow, please raise an Customer OSS message with SAP at the earliest.
    Regards
    - Atul

  • N-step WF for shopping carts

    Is there a N-step WF for shopping carts which can be used in SRM 5.0 ?
    The WF is driven by product category and not spending limits.
    Or do we have to develop a custom WF ?
    Thanks
    -Bakulesh

    Separate Determination Method for List of Approvers via BAdI BBP_WFL_APPROV_BADI in WS14000133:
    In WS14000109 the approvers are determined dependent on the total value of the SC and on the approval limits of the managers.
    However, if you use WS14000133 as an alternative, you can determine the list of approvers flexibly according to your particular requirements.
    You do this using the method GET_REMAING_APPROVERS of BAdI BBP_WFL_APPROV_BADI, with which you can integrate a logic for determining the approvers for each approval step (this can be more than one) and the number of steps in the entire approval process.
    For more details, see the IMG:
    Supplier Relationship Management  ®  SRM Server  ®  Business Add-Ins for Enterprise Buyer (BAdIs)  ®  SAP Business Workflow  ®  Determination of Approvers for n-Step Dynamic Approval Workflow.
    Go through the documentation of the BADI BBP_WFL_APPROV_BADI. It will give you a fair idea on how to about the logic you want.
    Hope this helps!!
    Krishna

  • Workflow for shopping cart

    Hi experts
    I am in SRM 7.0 and triing to use Process controled workflow, I have done some configurations for shopping cart aproval but no workflow is started and in shopping cart appear as in aproval.
    What cold be missing?
    Thanks
    Nilson

    Hi Guys
    Urgent
    In Sourcing cockpit field having morethan 1000 line item Shopping cart.  Could anyone help me to get the sourcing cockpit shopping cart entire report in a single report.
    We use to download the report morethan on hour on a daily basis.If anyone help me out for this really appriciated.

  • How to start one-step workflow..

    Hello Friends,
    we have one step approval for shopping cart. I know WF Template Id(WS10000129).
    I do not know how configure the agent assignment..
    how to configure and send workitem to agent and where you maintain agent for this workflow..
    Thanks,
    John.

    Hello Friends,
       I know how the n-step wf works.. I have been implemented in lot of cilents.. But this is the first time i suppose to implement the one step wf.. since n-step wf agent determine is from BAdi, But i don't how configure one-step wf for agent determine..
       does agent determine is from organization structure or any custom table need to develop to send agent to workflow?
       my question is how do i need send agent to workflow..
    please you have any documents please send or any url..
    Thanks,
    John.

  • Process Controlled WF for Shopping Cart

    Hi,
    We have implemented process controlled workflow for shopping cart approval.
    1. Created a bespoke schema for the approval process
    2. Defined 5 process levels in the schema
    3. changed the BRF event at the schema evaluation level. It now
    contains a constant with the name of new schema create in step 1.
    4. Decision set used is item based approval for partial documents (Type 4)
    4. The first process level is get the technical approval from bespoke
    table based on material group. For that we have first created a
    Responsibility Resolver Name - ZTECHNICAL_APPROVER.
    We have implemented the BADI - /SAPSRM/BD_WF_RESP_RESOLVER. Assigned
    the filter as BUS2121 and ZTECHNICAL_APPROVER.
    5. Now we have placed the external debugger in BADi. when we create
    the shopping cart the flow doesn't stop at the break point. The item
    reaches to the last step of Automatic approval (Rejected).
    6. We think that schema is getting evaluated, however the process
    level is not getting called.
    7. Before we created schema, all the carts wer getting "Approved" by
    automatic step. In our schema the automatic step is "Rejected", hence
    the carts are getting rejected.
    Could you please let me know what could be reason for BADI
    implementation not being called or is there any config step which we
    are missing?

    Hi,
      I think your process level evaluation id is not true, that is the reason system skips the process level.. Can you check your evaluation event-expression code. What do you see in SLG1?  For testing purpose change the evaluation id to 0EV000 and check. Make Sure you debug through the user(requester) that you are creating the SC. Please test and let me know...
    Saravanan

Maybe you are looking for

  • HELP ME! My MacBook Keeps Freezing!

    Ok, I really have no Idea whats going on, some things freeze and some things don't. Preview, Microsoft Word, started freezing first, at that time I got a pop up saying I had a courrpt font and it was going to be disabled, but I never say that again.

  • Help replacing D-Link DI-604

    Hi everybody, I was looking into replacing my DI-604 with a newer more robust router. I only have fios Internet (no tv), and have had service for about 5 years. Can I just take the d-link out and put a new router in? Do I need to transfer any setting

  • Error -049 again while trying to publish / end the project... make a .mov file

    Facts: Lion, Internal 1TB Hard disk, over 600 gigs free, all data on the HD internal. 45min video, about 20gb of data, music included from itunes and i photo. When clicking on ending project it takes 15 hours and the error 49 occurs. Can not publish

  • Z Date Types not available in WebUI

    I have created a Z Date type and assigned it to my Z Date profile which is in turn assigned to my Issue Request Transaction Type. Now when I open the UI Component SRQM_INCIDENT_H and then go to BTADMINH context node. I should be able to find my Z Dat

  • How to Change POs before to be sent to the supplier

    Hi gurus, My client needs in some cases make some changes manually in the PO (before the PO is sent to the supplier). All PO comes from SC initially, where is the WF. However, there are some functionalities that only the PO has, for instance, schedul