I want to setup MTO environment with possible delivery from stock. If I use strategy 20 (MTO) the system always generates planned orders even if there is stock, with strategy 10 (MTS) no planned orders are created.
Flow:
- when sales order is created and there is no stock --> MRP generates planned order
- when sales order is created in stock is available --> no planned order should be generated by MRP
I tried to make a new strategy but can't find settings to make our flow possible. Has anyone experience? I guess this is a situation faced in many companies.
Reward points if helpful answer.
Thanks,
jan

Hi,
I'm not totally sure this is the only strategy suitable for you, maybe you can examine this pdf material:
http://help.sap.com/printdocu/core/Print46c/en/data/pdf/PPMPDEM/PPMPDEM.pdf
Have a nice day,
Csaba

Similar Messages

  • Can MRP only create planned orders for ROH, not for FERT?

    HI all,
    Is there any way to only generate planned orders for raw materials after MRP, forbid creating planned orders for FERT?
    We want create planned orders for FERTs manually.
    Thanks,
    Harvey

    Harvey,
    Yes, that was also my understanding of your scenario. Did you try X0 for Fert?  Run MRP against the entire plant, and MRP will not create any new planned orders for the X0 parts.  It will explode the BOM and create dependent requirements in the components.  In addition, you can create FERT planned orders manually, or using an external planning system, and these manually created orders will also create dependent demand on your components.
    If you are also using Sales orders to consume your PIR, you will also have to look at requirements determination for Sales orders.  This is configured based on MRP type.  If you change existing MRP types, you may have to add SD config so as to continue to pass requirements to MRP.  Your SD resource should be able to help you through this, or I can give you basic instructions if you decide that the PIR/demand/planned order/dependent requirements works to your satisfaction.
    Rgds,
    DB49

  • BAPI_MOSRVAPS_SAVEMULTI3 creating planned order from Restricted Stock

    Hi,
       We have a requirement where we need to programmatically replicate the Push Production functionality as in /SAPAPO/RRP3 transaction. We are using the BAPI - BAPI_MOSRVAPS_SAVEMULTI3 and it is working fine for conversion of planned orders and Process Orders to component planned/process orders and dependant demand for the parent material. The issue is when we are trying to convert a restricted stock to a planned order and dependant demand using the BAPI, we are getting a message "No valid source of supply could be found". Please let us know if anyone has a resolution to this issue or if any further details are required.
    Edited by: ARKAJEET DASGUPTA on Apr 1, 2011 7:28 AM

    Hi,
        Tlane is not a field name,I wanted to say Transportation Lane(T-Lane) exist or not in the system for that product-location combination.
    For the SOURCE_NAME field, it is clearly mentioned in the documentation of BAPI that,
    Selection of sources of supply (for example, PP/DS PPM)
    ORDER_END_DATE is used as standard as the selection time for the source of supply (in-house production). If ORDER_END_DATE is empty, the value from ORDER_START_DATE is used instead.
    If a different time should be used to select the source of supply, this can be set using the EXPLOSION_DATE field.
    If a date field is not specified for an order change, the date of the last explosion of this order is used for source of supply selection.
    The entries in the MASTER<...> fields also play a role for source determination. That is, possible sources of supply are searched for on the basis of product, location, quantity, and so on.
    For the selection of sources of supply, the setting from the product master for plan explosion is used.
    If several possible alternative sources of supply are found, the system chooses one source of supply as standard.
    However, if you want to select a specific source of supply that has been found, you can use the fields PLAN_NUMBER + PPM_NUMBER, PROD_VERSION, or SOURCE_NAME. Note that only one combination may be used; you cannot use both PLAN_NUMBER and PROD_VERSION at the same time because both are valid for different source of supply types.
    Please check with the functional consultant, in plan explosion field in product master what value they have maintained.
    Because BAPI will try to get the source of supply name on basis of that field which is mentioned in the documentation.
    Regards,
    Saurabh

  • Creating Planned orders and Requisitions for a particular MRP controller and for all the others only Requisition is to be created.

    Hi Experts,
    Currently we run Program 'RMMRP000' as a batch job to create Planned orders and requisitions.
    The client wants that Planned orders and Requisitions should be created for a particular MRP controller and for all the others only Requisition is to be created.
    I implemented Exit 'EXIT_SAPMM61X_001' in the following manner by passing MRP controller to user_key.
      IF mt61d-dispo <> user_key.
        no_planning = 'X'.
      ENDIF.
    But as you can see that this will not meet my client requirement.
    If any of you has worked on similar requirement / if any one knows that this is achievable or not,
    please share your inputs.

    Moved from SAP ERP Sales and Distribution (SAP SD) to ABAP Development
    G. Lakshmipathi

  • MRP - Create Planned Orders only for Externally Procured Materials

    Dear All,
    We have a scenario that our client gives us the daily requirement schedule for the current month and a monthly forecast for future months so that we can plan our externally procured materials based on the forecast.
    Now I only want the MRP run to create Planned Orders for HALB and FERT based on my current months daily schedule and planned orders for ROH (Externally Procured) based on the next months forecast (monthly).
    I dont want the system to create planned orders for HALB and FERT from the forecast. The requirement for the ROH are however derived from the Finished Good BOM and the forecast is also given for the FERT material. I know its a long shot but is there a possibility in the system to do such a thing or a work around?

    Your business case is not clear; MRP will create planned orders for inhouse produced materials, and either planned orders or purchase requisitions for external procurement.
    You can choose to convert or release external procurement for a long time ahead (eventhough taht if you have proper lead times defined you can release by lead time), but convert inhouse planned orders to production orders only for next period (week, month). Actually this is common practice.
    So I fail to understand your problem.

  • Planned order for Negative stock

    Hi All,
    Negative stock set up is active at storage location level. Due to this setting I got some  negative stock in storage location.
    MRP is creating additional planned order specific to negative stock qty other than planned order created for that day requirement.
    How to get only one planned order for entire day requirement including negative stock?
    we have daily lot size in mat master.
    Thanks.

    Negative stock "requirement date" is immediate (day of MRP run). The other daily requirement that you may have, may be for a date other than "today", and this is why you get 2 planning proposals.

  • Deployment - setting for system not to create planned orders.

    hi
    I am executing deployment at the plant level.
    i have req. of 8000 on 26th and 9000 on 27th.
    i created a stock of 3000 on 25th.
    i am executing push deployment and maintained setting accordingly.
    After completion of deployment, system deploys the stock ie 3000 and creates Planned order for the remaining 5000 to meet the demand of 8000.
    What setting has to be maintained such that system only deploys 3000 or the stock only and does not create a planned order for the unful filled demand. ???
    in onther words system should deploy the stock and should not do anything more than that.
    Thanks.

    Hi Aswath,
    Can you answer these few questions for me? I will be able to answer your more appropriately.
    What is the order of planning runs in your system?
    1. DPR for demand at DC that creates distribution demand at the plant
    2. Deployment of the current stock at the plant
    3. Planning run at the plant to create planned order for any demand left out
    Is that the order? This does not make good sense for me but I don't know your scenario.
    What kind of deployment run are you suing? deployment heuristics or optimizer?
    In both the cases, you have "delete" and "reduce" option.
    The system deploys the stock at the DC based on the distribution demand ( coming from DC to Plant).
    If you use delete option, the system deploys for the amount of stock it has and deletes the remaining distribution demand.
    So, if you got distribution demand of 100 PCs, there is only 50 PCs stock at plant, the plant deploys 50 and deletes the other 50 PCs distribution demand at the plant. You need to rerun DRP at DC if you want to get back this demand.
    If you use reduce option, the system deploys for the amount of stock it has and reduces the remaining distribution demand.
    So, if you got distribution demand of 100 PCs, there is only 50 PCs stock at plant, the plant deploys 50 and reduces the distribution demand at the plant to 50 PCs.
    I think you have the second case and you are running planning run at the plant and it's creating orders. If you don't want the system to create them, use the "delete" option in deployment run.
    Please let me know if I am getting your point right.

  • Error while creating Planned order in SAP PP

    Hi ,
    I am creating planned order for finished material and system has given below error - Please specify the order deadlines in ascending order.
    SAP Message Error- Message no. 61009  Please specify the order deadlines in ascending order
    Very first planned order get saved and we declare the production and business completed
    Now creating second planned order , while saving system giving above error.
    I am Taking Planned Order Profile LA -Stock order
    Any solution  ...?
    Thanks in advance !!!
    Deepak.

    Hello Deepak,
    Please adjust the order dates in the scheduling of the planned order. In normal production scenario operation completed end of the night shift and order finish date is possibly moved one day in the future for this reason we need to set the operation timing in 24:00:00 format
    In your issue change date like this
    End date : 30.06.2014
    Start : 31.05.2014
    Opening date : 31.05.2104
    Check with this date, it’s work for you 
    Regards
    Umesh Mali

  • How To Automatically Create Planned Orders When Sales Order Is Saved

    I have a MTO sceanrio where we need to create planned orders when sales orders are saved without running MRP.
    I have the Planning Strategy Group set to 81 in the material master, but it didnt create the planned orders.
    Could you tell me other settings I should review to make the planned orders create automatically?

    Tony,
    At the "Requir. Classes" (OVZG) customizing screen, field "Automatic start of make-to-order in background mode" affects the automatic planning. See fields help doc. below.
        If you select this indicator, the system automatically carries out
        single-item, multi-level planning for a sales order if a sales order
        item is either created or changed.
        This function can only be used for make-to-order production.
    So check out the Req. Cl that yr Req. type (req. type is part of a strategy).
    BR,
    Elly

  • Advantage of creating Planned order first

    "The advantage of creating planned order first is the additional procurement proposal check that is executed by the MRP controllers. Purchasing can only order material when the MRP controller has checked the planned order and converted it into a PR.
    If directly PR is created during planning run, the procurement proposal is immediately available for purchasing."
    What is additional procurement proposal?
    Would anybody please explain the meaning of this with some example?
    Regards,
    VM - learning MM

    it is not "additional" procurement proposal, it is instead of requisition.
    If the planner knows that his MRP data is good and trusts in the process, then he can create requisitions right away.
    if a planner knows that his MRP data is worse, then the MRP run is better carried out with the option to create planned orders instead of requisitions. so the planner can check the proposals by sight and convert to a PR that is good.
    A buyer will not see the planned orders at all.
    Others, who dont like planned orders, create requisitions and implement release procedure to prevent that the buyer can use the requisitions.. (I dont see any sense in this alternative, because the planner would need to execute purchasing transactions, and does not have all the fuctions to check the background like he has in the usual MDxx transactions..)
    If the procurement type in material master is X for internal/external procurement, then you get anyway planned orders instead of requisitions.

  • MRP Run can not create Planned order to Sales order

    Hi,
    I have a problem with planning run to sales order. We have a configurable material which have make to order strategy. MRP Run does not create planned order to some of our sales order. I think it has relation with schedule lines but i can not understand the problem.
    If schedule line has 1 as confirmed quantity MRP run can not plan but 0 as confirmed quantity MRP Run creates planned order.  How can i solve this problem?
    Regards,
    techmastere

    Hi,
    Order for which qty is confirming, check which schedule line is determined and which requirement type system is determining.
    then in VOV6 for schedule line tick mark availability check & Transfer of requirement
    for requirement class OVZG tick mark availability check & Transfer of requirement
    Note: if schedule line is not relevent for availability check & ToR then system always defaul confirm quantity.
    kapil

  • Error while creating planned order in product view

    I am getting following error when I try to create planned order for a product in a Location  manually in product view using /SAPAPO/RRP5.
    Error occurred while creating order
    Message no. /SAPAPO/RRP251
    I checked the product and resource. Everything looks good.
    Block is available in the resource WMP1_2041_001 for characteristics specified in planned order.
    Product master and PDS look good.
    In the planning log, I see the following error message.
    Plan explosion failed for product LBRA1050-661 in location 2041
    Message no. /SAPAPO/RRP718
    I have not found SAP notes for above error.
    Can you pl let me know what this is due to?
    Thanks,
    Srini

    Srini,
    The message was created as a result of several notes, such as 1582997.  There are others.
    The implication is that you have an invalid source somewhere in your BOM.  Maybe a bad component part, maybe a bad transportation lane, maybe an invalid BOM, or maybe a bad PPM/PDS.
    If you can't find the problem using logical troubleshooting steps, have one of your programmers debug.  Have him put breakpoints in FM  /SAPAPO/RRP_PLORD_CREATE .  If you are particularly lucky, you will find a developer that understands German, because all the internal comments in this FM are in German.
    Best regards,
    DB49

  • DBIF_RSQL_SQL_ERROR while creating planned order in ECC

    Hi ,
    Recently we have done the ECC6.0  migration. Migration in the sense
    Server A ECC6.0 Maxdb to Server B ECC6.0 Sqlserver.
    we took the database export from server A and imported to Server B.
    After completing the migration we are facing a problem.
    Using Trx code MD11 I am creating Planned order. It is giving Planned order   XXXXX will be created.But when I go MD13 and try to retrive the same planned order it says the order XXXXX doesn't exists.
    when I try to go back from MD13 it shows Express document "update was terminated" received from Author ************.
    I am seeing a dump in ST22.
    Error 22.04.2010          DBIF_RSQL_SQL_ERROR              CX_SY_OPEN_SQL_DB      
    Cann't insert NULL into column "ADCODE" Table "RESB"
    Column doesn't allow NULLS . Insert Fails.
    Any Help is Appreciated.
    Regards,
    Guru.

    Hi Srini,
    Please kindly review and evaluate note 686357 for possible solution.
    686357 able pool nametab length incorrect after Unicode
    The following pools may be affected:  ATAB, GLSP, GLTP, DVPOOLTEXT, KAPOL
    Please kindly run report RATPONTC to reset the dictionary and nametab length in the note.
    Regards,
    Mauro

  • No Account Assignment when I created Planned Order to Purchase Requisition

    Hi ,
    No Account Assignment when I created Planned Order to Purchase Requisition from Funds Management , where as If i change  ( eq : PR item qty is 10 , i just changed to 0 , enter then replace back that 10 ) any thing in the PR , Account Assingment is populated and list of accountin  documents are attached to PR.
    Please suggest me , what might be the problem .
    Thanks in adv

    Hi,
    a) When you convert the PldOrd into PurReq it disappears from table PLAF, it ceases to exist. There will be no PldOrd-reference in PurReq (you will not find such field in EBAN). (if you check field RSNUM in PLAF before converting the PldOrd and you check field RSNUM in EBAN after converting the PldOrd into PurReq, you wlll find the same number)
    b) It's not easy to say. You can check PLAF-PSTMP and PLAF-PUSER and compare these with data you get from trx STAD. But this is also not an exact methode since these field are in connection with the last date of change.
    Firming indicator cannot help also since you can remove it manually... - even though the PldOrd was changed manually, no firming indicator will be seen...
    (Of course, generally firming indicator helps if the user doesn't remove it intenionally)
    Regards,
    Csaba

  • MRP: Delete Purchase Requisitions and Create Planned Orders

    Hi there,
    I have a scenario, where in a material (HALB) was marked as externally procured. MRP was run for FERT material. The dependent requirements for FERT were created. Planned orders of the HALB material were changed to Purchase Requisitions.
    Later, the procurement type of material was changed to Inhouse Production.
    Now, I want all the Purchase requisitions that were created to be deleted and Planned orders should be created when I run MRP.
    I tried all the possibilities, but of no success.
    Please lemme know if there is any possibility to delete the P.Rs and Create Planned orders by running MRP.
    Regards,
    ABC

    I Haven't read the Plan order is converted in to PR Before
    If YOU convert the plan order in to PR, system will firm the Requirement, YOU need to remove the firm indicator FIxed iD in PR Before doing the MRP Run Again
    Do the following thing in PR
    In PR Remove the  Fixed ID in Quantities and Dates tab of the item
    and Rerun the MRP with Planning Mode 3 It will create a plan order
    Edited by: Sundaresan . E. V on Oct 29, 2010 6:39 PM