Operation planning in order

Dear PM experts,
in operation tab in the PM order when i enter the duration of the operation and press enter for planning the operation the system gives me the time to start the operation and the time to end it but its not synchronized with the time i create the order , how can i synchronize the starting time of the operation with the time which iam creating the order in ?
thank you in advance
Edited by: serry1 on Mar 27, 2011 4:11 PM

Hi,
Then try to change the Work Center time from 12 AM in capacity tab, so that will give you order creation time as start time.
Also in IMG under Scheduling Parameters for PM Orders, in adjust dates select "Adjust based on Order Start date".
Then try the same.
Regards,
Maheswaran.

Similar Messages

  • How do we can change the last done dates of Planned operation by EM orders?

    Hi colleagues
    i defined four opertions for one equipment as performance based or time based plans and scheduled it for next month. then we received a EM notification for mentioned equipment. we iisued order for EM notification and  maintenance opertor carried out the orders but while he doing the EM process , he did two opertion of preventive maintenance from mentioned plan.
    we can add mentioned operations in EM orders as operations but the question is that after we confirm the EM orders and enter the actual dates , and it seems that the last done dates of assigned two operations must be change in PM plans.!
    Is there any solution for it or not?
    Thanks
    Akbar

    Hi Carlos
    thanks for ur attention
    actually i want change the last done dates of some opetions in my scheduled maintenance orders by assigning them to EM orders as operations.
    for example:
    i received a EM orders with this description : oil leakage from sight glass of hydraulic pumps
    in the proceesing of EM order , i will eliminate the leakage and also change the oil of pump .
    the changing the oils is the one of our shecduled Maintenance plan that is it would be called on next month.
    in the confirmation of EM order , i will add this operation from equipment task list ( change the oil) and enter the dates and another data.
    it's obvious that mentioned opertion should not be schedule on next month and according to it's package sequence , the new date for changing the oil must be 3 month later form the date that we entered on EM order.
    Thanks
    AKBAR

  • The FM to copy the simulated planned order to operative planning

    Hi Gurus,
    Is there a function module which can copy the long-term planing results (Simulated Planned Orders) to the operative planning environment and create a PR, like MD43?
    I found the FM MD_COPY_PLAF_LTP. But it seems too complex to be pratical. Or I just simply create the PR by reading the planned order data?
    Thank you.
    Regards,
    Felix

    Hi, I have the same requirement with you.
    Did you find the solution? Could you please share with me
    thank you.
    Huang

  • CM38 considering orders of operative planning on the simulative scenu00E1rio

    Dear friends,
    I'm trying to use the T-code CM38 to analise the capacity load of one LTP planning, but this transaction is taking into account some production orders of the operative planning.
    I already checked in T-code MS32 to be sure that my planning scenario is not considering the "receipts", and all those options is not flagged.
    I'm using the profile SAPPLAN01 or YBLTP01 to analise the capacity on CM38.
    How can I see only the capacity load of simulation orders (my LTP scenario orders) in this transaction? Is it possible?

    Hello,
    Your question should go to ERP  Manufacturing (PP)  forum [SAP ERP Manufacturing - Production Planning (SAP PP);
    This forum is for SAP Manufacturing Execution.
    Thanks

  • CM38 considering orders of operative planning on the simulative scenario

    Dear friends,
    I'm trying to use the T-code CM38 to analise the capacity load of one LTP planning, but this transaction is taking into account some production orders of the operative planning.
    I already checked in T-code MS32 to be sure that my planning scenario is not considering the "receipts", and all those options is not flagged.
    I'm using the profile SAPPLAN01 or YBLTP01 to analise the capacity on CM38.
    How can I see only the capacity load of simulation orders (my LTP scenario orders) in this transaction? Is it possible?
    Thanks in advance,
    Rodrigo

    Dear Rodrigo,
    In CM38,under detailed settings check whether this planning scenario is mentioned before entering into the capacity details.
    Also refer this thread,
    Re: Capacity planning
    Check and revert
    Regards
    S Mangalraj

  • Transfer LTP planned orders to Operational planned orders

    Hi
    Can anyone suggest how to transfer planned orders generated from LTP(Long Term Plan) to Operational Plan?
    Regards
    Pradipta Sahoo

    Dear Sahoo,
    You can transfer the simulative planned orders to operative planning using T Code MD43.
    Check this,
    Copying the Long-Term Planning Results to Operative Planning  
    Use
    Once you have optimized the results of long-term planning, you can copy them to operative planning.
    It is not only possible to copy the demand program to operative planning, you can also copy the planned orders firmed in long-term planning per material using the MRP transaction Interactive single-item planning.
    When copying the results to operative planning, you can set the system to create purchase requisitions and delivery schedules instead of planned orders for materials procured externally.
    Prerequisites
    You must firm the simulative planned orders you want to copy to operative planning. You can firm planned orders by:
    Making manual changes
    Using the planning time fence
    Setting a manual firming date
    If, when copying the data to operative planning, you want the system to create purchase requisitions or delivery schedules for materials procured externally instead of planned orders, enter the appropriate indicators in the Create pur. req. and Schedule lines on the initial screen of single-item, interactive planning (in MRP).
    When copying the results to operative planning, the system does not carry out any source determination. If you want the system to create delivery schedules and purchase requisitions to which a vendor has already been assigned, you must maintain the necessary master data in the Purchasing menu before carrying out the planning run in long-term planning.
    http://help.sap.com/saphelperp60_sp/helpdata/en/92/bf02af44bd11d182b40000e829fbfe/content.htm_
    Regards
    Mangalraj.S

  • Sales Operation Planning

    Hi All,
    In Sales Operation Planning , Can we plan a Bulk of 200 materials without Product grouping or individually.
    Please suggest if any solution available.
    Regards
    Subbu.

    Hi,
    http://sap-pphelp.blogspot.com/2010/01/sop-flexible-planning.html
    http://www.scribd.com/doc/23491525/How-to-Work-With-SIS-Structures
    1.     Create Field Catalogue MC18
    2. Create Info Structure MC21
    3. Create Update Rules for Characteristics and Key Figures MC24
    4. Activate Update Rules OMOZ
    5. Testing (Use Sales Order, Purchase Order, Material etc.) to test data
    MC30
    6. Set Parameters for Info Structures MC7f
    7. Create Planning Type for Info Structure Planning Table MC8A
    8. Generate Master Data and generate proportional factors MC9A
    9. Create Planning Hierarchy MC63
    10. Create Forecast Profile MC96
    11. Create Planning Activity MC8T
    12. Setup Mass Processing Job to generate forecast MC8D then MC8G
    13. Maintain all Material Master records with unit of measure conversions
    so that the planning table can aggregate materials into a common unit of
    measure. MM02
    14. Apply OSS patch program that enables visibility of all nine hierarchy
    planning levels in planning table. (Check version 4.5 and prior)
    15. Set up program to collect Historical transaction information (Need
    Custom ABAP program to populate the SOP table with historical data)
    16. Run Monthly Sales Forecast MC8D
    17. Transfer to COPA (if applicable)
    18. Run COPA Analysis (if applicable)
    19. Transfer forecast to Demand Management MC94 (Extra Menu -> Transfer to demand mgmt)
    20. Demand Management receive the updated Sales Forecast quantities MD61
    Regards,
    Ravi

  • Copy GOS attachment from maintenance plan to order

    Hello,
    we use maintenance plans to create maintenance orders.
    The idea is to attach checklists and other documents (excel, word, pdf) to the maintenance plan and this should be copied to each maintenance order. We attach att the moment this documents using GOS.
    Is there a standard way to copy document attachments from plan to order?
    Or has one of you realized a solution for this requirement?
    Thanks a lot.
    Kind regards
    Manfred

    Hi,
    PRT is Production Resources / Tools.
    PRT can be an equipment or a material or document or even a free text.
    Simply, it is an object/item that is required to carry a particular application.
    There are other benefits os PRT as well.
    Comprehensive documentation is available online.
    You can attach a document as a PRT by:
    1. Select the task list operation & click on PRT push button below operation list.
    2. On PRT selection dialog box, select "Document" push button.
    3. You will get relevant fields for selecting a document from DMS.
    4. Select your document & save.
    Regards,
    Vijay

  • KSPP error: Plan/SOP order &: Reference to cost center/activity typ

    Dears,
    I need to know how to correct the error: "Plan/SOP order &: Reference to cost center/activity typ" that I received when I run the KSPP.
    Error code kp603.
    Thanks in advance
    KR
    Vincent

    Hi everbody,
    I found that when we have a formula in Resource -> Costing view but no quantity ( zero ) in Standard Value for operations (Master recipe) then we face the error.
    Other tips could be found in sapnote 1770587 and sapnote 380282.
    I hope this help to solve the issue.
    Regards

  • SOP - Routing data consideration in the Sales and operation planning

    Hi,
    Please share knowledge how to take the consider routing while doing the sales and operation planning.
    I have done the resource planning in the sop and it is picking the data's from the rought cut profile also. As per sap help it is mentioned that in sop we can use routing or rate routing also to do the resource planning in sop.
    Where the setting to be done?
    If answered.. full pointed will be rewarded....
    Regards,

    Hi,
    Thanks for your reply.
    As per my knowledge T-code will be OPU4 for the Sales and operation planning.
    The T code OPU5 is applicable for planned orders not for SOP internal orders.
    I have checked the senario and reverting back to you.
    Did you checked the senarios for the resorce leveling with out creating the rough cut planning profile by t code mc35?
    Please give you yahoo or gmail messanger or telephone number ....
    Regards,
    Mahesh Garg

  • Transfer of requirement from LTP to operative planning

    Hi,
    I have run LTP for different 5 finished products by MS01 by creating one planning scenario.
    After LTP run system has planned all the raw materials required for all five finished materials.
    Now I want to transfer the planned orders for all raw materials to operative planning MD04. But I dont want to transfer the planned orders for the finised materials to MD04.
    Through MD43 I can copy planned orders of raw materials to MD04 one by one (material wise).
    Is there any way that I can transfer planned orders of all the raw materials to MD04 at once.
    Please guide........
    Nitin

    Dear Nitin,
    I dont think a direct solution is possible ,either you can copy the values from one version to another using T
    code MS64.The source version will be the inactive version and the target version will be 00.
    One more T code MS66 for copying Simulative Dependent Requirements.
    Regards
    Mangalraj.S

  • Custom exit or badi for changing the user fields in operation of process order

    Hi all
        I want to find a exit or badi to set default value to the user fields in operation of process order when COR1.
        I have tried exit 'PPCO0001', but this exit is call after commit work, so I can not change any thing
        I also tried to use badi 'workorder_update', 'before_update', but all parameters in this BADI are importing, can't be changed, I've tried to change it and then program dump.
        Do you have any solution for this question?
    Thanks

    Do a Implicit Enhancement at the PBO of this subscreen.

  • Distribution Function - To split Planned/Process orders into 10

    Have you used, or tried to use Distribution Function?
    It is assigned to the Production version and we assumed that it would divide the Planned order/Process order by the %  we have in customizing.
    We have created a distribution function DV10 and assigned to our plant. This uses the standard function S30 which has 10, 20, 30, 40, 50, 60, 70, 90, 100 in % dur and % cap fields. So you would think the planned/process order would be divided into 10 parts
    Reason u2013 if an order goes over multiple days we want the order to be broken down by day.
    Why? So that Deployment, when looking at an ATP report in R3 for multiple materials in 1 location, by day or period of days,  can see how much will be available each day
    Problem with GLEI (equal distribution) is that if an order starts today at 22:00 then we have equal distribution, we then have 25,000 PAL available today and 25,000 tomorrow, which is not a fair proportion according to the time available. Therefore, we thought that dividing by 10, for example, we would have a more accurate proportion each day
    Many thanks for any input, even if "tried and failed :("
    Cheers, Paul

    Hi Mario,
    Thanks for your input. Today we use GLEI which equally splits the same planned or process order into equally daily quantities for ATP purposes. We also have created STRT which drops the Planned/process order quantity onto the first day of the order.
    Regarding daily lot sizes this could be an option but I suppose you would then get individual orders, which the business may prefer not to do.
    Cheers, Paul

  • How to get F4 help for Standard Text Key of a operation based on Order type

    Hi Experts,
      How to get F4 help for Standard Text Key (STK) of a operation based on Order type entered in selection screen. The F4 help should give the STK of related order type. At the same time the F4 help for Task Types based on Notification type. How to acheive the above two. Please provide the table names or any search help name if exists or Function modules...
    Thanks in Advance.
    Regads,
    Bujji

    Hi Guys,
       Any help on this...
    Regards,
    Bujji
    Edited by: Bujji on Dec 22, 2008 12:42 PM
    Edited by: Bujji on Jan 5, 2009 2:00 PM

  • Scheduling issue for splitted operations in process order

    Hello All,
    I am facing problem after scheduling splitted operation in process order. The scenario is as follows.
    In process order there are 5 operations. 10, 20, 30, 40 and 50. Out of the above operations 30 is splitted and two different resources are assigned to it. Control key assigned to splitted operation (30) is also scheduling relevant. Now the flow of operations will be as below.
    1. Operation 10
    2. Operation 20
    3. Operation 30 - Operations is splitted (Resource used is A), qty to be produced - 10 kg.
    a. Operation 32 - Quantity of operation 32 is changed to 5 kg. Resource used is B.
    b. Operation 34 - Quantity of operation 34 is changed to 5 kg. Resource used is C.
    4. Operation 40
    5. Operation 50
    Relationship exists between opearion 10-20, 20-30, 40-50 and between 30,32, 34 with 40. But there is no relationship exists between splitted operations 32 and 34 with any of the previous operations for eg. 10 & 20.
    Issue is after scheduling all operations relationship remains maintained between operations 32, 34, 40 & 50. As operation 30 is splitted to two different operations equally total time for scheduling gets reduced but after scheduling of all operations all previous operations before operations 30 does not get resceduled? Scheduling type maintained for order is Backward Scheduling.
    Please check this and guide me how all operations before operation 30 can be rescheduled as per changed timing of operations 32 and 34.
    Best Regards.
    Edited by: Avinash Mohite on Mar 19, 2010 12:43 PM
    Edited by: Avinash Mohite on Mar 19, 2010 3:14 PM

    Hi,
    I hope u r doing in this way:
    In the capacity header screen enter individual capacity as 2. then click on Got( on top of same screen) and go to individual capacites. Enter the names of two individual capacities, for example 1 and 2. These are the names of two work centres where u r splitting ur operation.
    Double Click on operation 0030 and go to tab 'splitting' . Tick on ' required splitting' and enter maximum no. of splits as 2.Then go to capacity requirements assignment tab. enter the individual capacity as 1 and 2 and enter the splitted quanitites.Save and reschedule .
    Check and revert.
    Regards.