Operation status 'Fixed' in Production order

Hello all,
We are facing an issue with Operation Status 'Fixed'. If we go to transaction /sapapo/rrp3 and double click on Production Order (R).  Then clcik on Operation , say 0100, at right side you will see multiple Operation status. One of them is 'Fixed'. We can make this indicator active ny fixing the order in planning board (right click=> Fix).
Here we are facing an issue. We are not fixing any order through planning board and still I see Operation status 'Fixed'. Even I unfix it, next day it gets fixed automatically. I suspect that either any job in APO or R/3 do this activity. Please note that in this case 'Date_Fixed' indicator is not checked. Like when you fix the order from planning baord, system check the checkbox for 'Date_Fixed" and for operation status 'Fixed'. In our case only Operation status becomes 'Fixed.
Please let me know what are the different ways to fix the operation status.
Regards,
Nitin

Thanks for the reply.
As you mentioned, if the operation is scheduled at non-working hours then it gets fixed. I checked with the user and they confimred that they are not using the non production hour while rescheduling the order. It means they are not using the check box of non-working hour from DS startegy or Heuristic.
Please let me know what are the different possibilities which can schedule the operation in non-working hours.

Similar Messages

  • How to change the status of a production order

    Dear All,
    May i know how to change the status of a production order.I want to de-active the status like OPGN (Operation generated).This status is updated as there was no routing assigned to that particular production order during its creation
    Thanks and Regards,
    Varun Siddharth

    Dear,
    When you create a production order, an operation created by the system is generated automatically if no routing is used for the creation. As a result the order header receives the status HOGAN; the operation created automatically also has this status.
    If you delete the operation created automatically and then do not have the status HOGAN.
    To avoid this maintain the Routing for the material or delete the setting of default operation from OPJG.
    Regards,
    R.Brahmankar

  • Block Operation Number Change in Production order

    hello,
    How can i block the operation number change in production order if the operation status is CNF...?
    ie either disable the operation number cell or disable the entire row in the production order.
    rgrds
    Krishna.

    hi prashob
    i can't disable the column, as user need to insert operations in between
    AP, 
    I will check for this...
    regards
    Krishna

  • How to use the selection profile and status profile for production order?

    Hi expert,
       I want to know how to use the selection profile and status profile for production order. what's the usage for these two selection profile and status profile ?
      Please help me.
      thanks in advance.
      george.shi

    Hi George,
    There are are two types of statuses.One is system status and second one is user status.These statuses will tell us current situation of an order.
    We can't change system statuses.But we can create our own statuses through status profile.With this profile we can control user statuses.
    In this status profile,
    1.We define the sequence in which user statuses can be activated,
    2.We define initial statuses
    3. Allow or prohibit certain business transactions.
    Selection profiles are used to select the objects (say production orders) with different status combinations.We assign status profiles to selection profiles in BS42 T-Code.
    Regards,
    Raja.
    Edited by: Rajarao on Oct 30, 2008 6:21 AM
    Edited by: Rajarao on Oct 30, 2008 6:22 AM

  • To get the User status of the Production Order

    Dear all,
    I have a  requiement to get the user status of the production order, This is just below the Status of the Production Order,
    I was able to get the Status of the Production order using the Function Module ( REL MSPT PRC ) etc
    Can any body please help me in fetching this data.
    with rgds
    Ranjith Singh

    Dear,
    Please try with,
    FM 'STATUS_TEXT_EDIT'
    Or See function module PM_ORDER_DATA_READ
    The status maintenace is done by SAPLBSVA
    Use the Tables are :
    JEST - Pass OBJNR of the Production ORDER (AUFK, AFKO tables)
    or from
    TJ02
    TJ02T
    Please take help from technical consultant.
    Hope it will help you.
    Regards,
    R.Brahmankar

  • Display the status of the production order

    Hi Friends,
    I have a task which should display the status of the production order.
    If an order number(AUFNR) is given, it should display whether the order is available or not. Also it should display the status of the order whether it is delivered, completed, blocked etc.
    Can anyone send me the code for the above task.
    Waiting for ur reply.
    Raj
    Message was edited by: Craig Cmehil

    Please mark this post as "Solved on my own" as it is a duplicate of your post which has already been answered.  Thanks. 
    Also, please remove the email address from the subject line.
    Regards,
    Rich Heilman

  • No System Status Saved In Production Order

    Hi PP Gurus,
    We encountered a short dump when display production order.
    I have checked the system status of this production order from database, and there is NO record in table JSTO, JEST, etc.
    Why the status has not been saved in production order? How do we deal with the existing production order without system status?
    Appreciate any input here.
    Regards,
    SQ

    Thanks, Marcelo.
    Program ZPSFC008 works well in this case.
    This ticket can be closed.
    Cheers,
    SQ

  • Add/change multiple operations on a released Production Order

    How can I add/change multiple operations on a released Production Order...I know how to add them manually one by one but is there a better way to add...like copy/paste since i am adding operations from an alternate route? Please advise?

    Hy Aziz,
    In process order go to operation screen go to Operation - Include Master recipe, then one pop up comes select required Master recipe and add operations of your interest.
    But there are some restriction which doesn/t allow it if Inspection Lot, Control Recipe are created..
    Regards,
    Dhaval

  • Relation between operation and component in Production order

    Hi All
    I am new to PP. I need to get the tables which gives relation between operation and components in Production Order. I need to display in smartform the components assigned.
    Thanks and regards
    Swetabh Shukla

    Hi,
    Try with AFVV Table.
    You need to get the Details of the Filed : AUFPL from AFKO.
    Hope this helps..
    Regards,
    Siva
    Hi,
    You can get the details from Table : RESB.
    Regards,
    Siva
    Edited by: Siva Kumar M on May 23, 2008 10:49 AM

  • A FM or BAPI to update the status of a Production Order

    Hello, does anybody know if there is an interface FM or BAPI to update the status of a production order. Specifically I want change the status of PP order to LKD (locked). I want to do it programmatically from an external system.
    Thank you
    Ernesto

    Hi,
    I believe you can use the FM I_CHANGE_STATUS to update the status..
    where JEST-OBJNR = AUFK-OBJNR
    Thanks,
    Naren

  • Operation wise cost through production order

    Hi Experts,
    Is There any standard report to get Operation wise cost through production order.if it is there please provide the details.
    Thanks & Regards,
    Prabhakar

    HI,
    I don't know a standard report but table CKIS contains the costing details line item wise with the corresponding operation number (CKIS-VORNR).
    So a query/quick view using KEKO + CKIS should be sufficient.
    Best regards, Christian

  • Revoke TECO Status for CO Production Order SAP R/3 3.1H

    Hi All,
    We are still on SAP R/3 3.1H
    Recently, a user accidentally TECO a CO Production Order and now required to revoke the TECO status. There was a similar case back in 2004 and I posted the issue to SAPOSS but did not get it resolved. At that time I was told that it is not possible to revoke TECO status on 3.1H. Furthermore, I was told that a solution can be provided but it is 'billable' due to the nature of the issue which is not a system bug but more of an operational issue.
    On the recent case, the chronicle events are as follow:
    1. User A created, released, and created settlement rule for the order. This was done on month end (previous period as suppose to the current period).
    2. User A then proceed to do good receipt of the order but 'forgotten' to indicate that it was a complete delivery. This was done on current period but posting & document date is on previous period.
    3. Another user, B, try to issue settlement for previous period but failed. System return message saying order delivery is not complete and advice to 'complete technically' the order (error message is misleading).
    4. User A then proceed to 'TECO' the order without further checking. Apparently, no period selection for doing this posting; system just take the current date (current period).
    5. User B still not able to settle the order on the previous period which it is supposed to settled. Settlement only possible for current period, the period the order was 'TECO'.
    The CO Production Order is now 'stuck'; no movement type can done on it, cannot settle on previous period as required. If at all possible, 'TECO' status need to be revoke so that other posting for previous period can be done on the CO Production Order.
    Is there anyone out there know a workaround or solution, including ABAB program to revoke 'TECO' status for SAP R/3 3.1H.
    Any advice appreciated.
    Regards,
    Wilson Rotop

    Hi,
    Again, revoke TECO option not available on SAP R/3 3.1H.
    Rgds
    WR

  • How can I get status of a production order from database?

    Hi,
       I need to write a report to show user details about the production order. Because there are some customized linkages between our sales order and production order, we can't use COOIS directly.
      But I met a problem when writing this report. I found that after TECO, all lines on reservation of the production order will be set deletetion flag. So, I need to tell which orders had been TECO-ed. But I don't know from which fileds and which tables I can get the data to tell this. Please help.

    Hi Robbie,
    You can use function module STATUS_READ
    You need to pass it the object number - for a PP order header it will be something like OR000001000000
    You can also set an indicator to only retrieve active status values.
    The FM returns a table of status codes which are in the internal format and look like I0002
    Then use table TJ02T for system statuses to determine what these internal codes mean. If you have user statuses you should be able to work out where they are stored by looking at the technical information behind the configuration transactions.
    Regards,
    Monika

  • Operations Sub Contracting in Production Orders

    Dear All
      I need to do a operation subcontarcting.The requirement goes as follows
    There are 3 operations 10 Moulding in house ,20 - Subcontracting To vendor for operation &
    30 - With the received Material from Subcontractor One more Moulding operation is done.
    The bom contains only one raw material its assigned to 1st operation.
      i checked the querries posted in Sap and have done the following steps
      i have maitained 20 the operation as PP02 with purch organisation and material group
    assigned i have got a purch requstion while creating a order.
       Since we are using only one material for all operations i issued it to the po and Done final confirmation for 10 th operation.
      Then iam trying to to convert Purch Request to PO thru ME58 iam not getting it executed but while trying to create it through ME21N iam getting an error components
    not possible to get any components.
    My doubt i have already issued the raw material required how to send the raw material again to the sub contractor and i want your help in creating PO through ME58
    Shankar

    Hi shankar,
    For your case (in service subcon), check routing with operation 20 (PP02), subcontracting check box have tick, pls remove tick mark and save production order, now you convert PR to PO
    FYI, already discuessed many times for this topic, pls refer below SDN forum link
    https://forums.sdn.sap.com/click.jspa?searchID=7249879&messageID=4487712
    https://forums.sdn.sap.com/click.jspa?searchID=7109743&messageID=4056008
    https://forums.sdn.sap.com/click.jspa?searchID=7109743&messageID=4480137
    https://forums.sdn.sap.com/click.jspa?searchID=7109743&messageID=4487712
    Regards,
    Sankaran

  • Userexit for updating sales order user status based on Production Order

    Hi.
    My clients requirent is
    Sales order user status should get updated based on production order creation,GR for PO creation etc.
    Basically depending on PO & GR For PO,various user stauts in sales order should get updated.
    Can you please suggest me some userexits in PP for this requirement?
    I am a SD Consultant and not having much idaes about PP
    Thanks
    Nisha

    hi,
    if you are not going to update it in the SO..
    then you need different exits as those are different transactions.

Maybe you are looking for

  • Images that refuse to be published!

    I have 5 jpg images on my dreamweaver page that show up fine. Those 5 jpg images are uploaded in my public HTML folder for my website, ubt when I load my website that page keeps coming up with little red x's instead of the uploaded images. Can anyone

  • ESB Console Error while trying to install AIA FP 2.2

    Hi all I am installing AIA FP 2.2 and while installing I am getting the following error: "Design time cache has not been initialized" also When I log into my esb console I am getting this error: Designtime cache has not been initialized Please look i

  • Path selection acts weird

    Hi everyone, Help me please! I made a path and after selecting it the selection makes a different form than the path. Like this: This is only happening at this area, other parts are good. Do any of you have an idea what to do with it? Thanks a lot.

  • Song wont play and just jumped to next song automatically

    Hi guys, Im using MacBook Pro OS X 10.9.2, iTunes 11.1.5(5) and iPhone 4S Actually, i added my musics on iTunes library and all of them play properly in iPhone but when im going to play a specific one it wont play and automatically jumped to next tra

  • How can I determine which image was clicked in 3D carousel?

    I have been modifying some 3D carousel code that I found in hopes that I can get it such that when image "resolv2.jpg" (or any of my other images) is clicked on at the front of my carousel, it goes to a specific webpage. By just replacing "moveBack(e