Operations Sub Contracting in Production Orders

Dear All
  I need to do a operation subcontarcting.The requirement goes as follows
There are 3 operations 10 Moulding in house ,20 - Subcontracting To vendor for operation &
30 - With the received Material from Subcontractor One more Moulding operation is done.
The bom contains only one raw material its assigned to 1st operation.
  i checked the querries posted in Sap and have done the following steps
  i have maitained 20 the operation as PP02 with purch organisation and material group
assigned i have got a purch requstion while creating a order.
   Since we are using only one material for all operations i issued it to the po and Done final confirmation for 10 th operation.
  Then iam trying to to convert Purch Request to PO thru ME58 iam not getting it executed but while trying to create it through ME21N iam getting an error components
not possible to get any components.
My doubt i have already issued the raw material required how to send the raw material again to the sub contractor and i want your help in creating PO through ME58
Shankar

Hi shankar,
For your case (in service subcon), check routing with operation 20 (PP02), subcontracting check box have tick, pls remove tick mark and save production order, now you convert PR to PO
FYI, already discuessed many times for this topic, pls refer below SDN forum link
https://forums.sdn.sap.com/click.jspa?searchID=7249879&messageID=4487712
https://forums.sdn.sap.com/click.jspa?searchID=7109743&messageID=4056008
https://forums.sdn.sap.com/click.jspa?searchID=7109743&messageID=4480137
https://forums.sdn.sap.com/click.jspa?searchID=7109743&messageID=4487712
Regards,
Sankaran

Similar Messages

  • Sub Contracting for Production Order

    Hi All,
    Scenario is like this, I release Production order & deicde to sent it to sub contracting & PO Created is wth Acct assignment F with no material master.
    after this how do i account sub-contacting bills with MIGO i'm not able to make a GR.
    should i maintain a material master in purchase order, how do i send material to sub-contractor.
    Regards

    Hi,
    You have to maintain material master for both - Ordered Material & the material in the BOM of ordered material. Also you have to maintain procurement key as X - Both procurement types possible. When the planned order is created for the final product, you can convert the Planned order to PR with item category L - Sub Contracting, system prompts the material to be supplied to subcontractor in Material Component list (BOM Material). You may transfer the material to the sub-contractor via transfer posting (MB1B) movement type 541. When you post GR for final product, the BOM material is consumed for the Final product via movement 543.
    Hope the query is fulfiled.
    Reward proper points if the answer is helpful.
    Regards,
    Prashant Kolhatkar

  • Sub-contracting through Production Order

    Hai..
    We have a routing with 8 operations. The 6th operation is an external operation (PP02 control key). When the production order is released a Purchase Requisition is created. It is a subcontracting PR. But the PR does not have any component assigned to it. Also the PR line item is blank. It just shows the operation description in the Mtrl description field.
    Now am not sure what item is sent to the subcontractor and what item is received back.
    Please advice.
    Regards
    Sampath

    Hi,
    There is no real difference between purchasinf an item directly from the vendor and purchasing it through a subcontract order. The only real difference is that you have to indicate that it is a subcontract PO and not a normal one and you need the BOM to be set up for the material to be subcontracted (to list the component/s that you will be sending to the vendor).
    If you have set it to get this item from stock, be careful, because if you have these items in stock, it will simply expect a stock transfer. If you don't have them in stock then MRP will try to source them for you and this will need to use the special procurement key to ensure that a subcontract PO is created instead of a normal one.
    Perhaps you would be better indicating that it is a non-stock item and have the requirement (PR) generated automatically from the PP order.
    My PP is a bit rusty and so I am not able to be specific as to which entries you would need to make and where but bascally the PP order needs to be set up to procure it directly from the vendor as a subcontract item.
    The MM process then takes over and (normally using transaction ME2o) manages the issue of the item/s to the subcontractor and the GR of the finished product into stock.
    Steve B
    Steve B

  • Operation Sub-contracting

    Hi Experts,
    I need some clarity on operation sub-contracting.
    My input material is A and out put material is B.
    I have to do 4 operations to get B from A.
    The second operation i am doing at sub-contractor's end.
    I have assigned PP02 control key in the routing and i have given all Purchase info record details and cost element details.
    I have created a production order during which Purchase Requisition has been created for the 2nd operation.
    I have confirmed the first operation, the status updated in the production order.
    When i am trying to convert the Pur. Req. to Purchase order, system is giving the error " No components could be found".
    here my dought is,
    1. Whether i need to create a seperate material code for the 2nd operation which is done outside.
    2. When the first operation is confirmed, how will i get the stock to send the material outside?
    Please thro' some light on this.
    Thanks & Regards
    Bala

    Dear,
    Please check MRP2 view - Procurement type as X and Spl.procurement as 30?
    Steps are as,
    1.Create Purchase Info Record using T code ME11.(Vendor & material combination).
    2.While creating routing for that header material and defining operation ,For the 20th operation(2nd operation)for which outsourcing is given set the control key as PP02.After entering the control key as PP02 ,press enter -the system asks you for the purchasing info record no & check the tick mark for Sub-contracting.Here give the number which u obtained while using T code ME11.
    3.After confirming 2nd operation using CO11N,now goto the production order in change mode using T code CO02,for operation no -2,double click on that & get the PR No.(from the external processing tab).
    4.Convert this PR(Purchase requsition) into PO(Purchase order) using T code ME58 .
    5.Send the material to the vendor using T code MB1B - Movement type - 541-Transfer posting to stock with Sub-contractor from unrestricted use stock.
    6.Recieve the material from vendor using T code MIGO Movement type 101 -Good's Receipt for Purchase order into Warehouse/Stores.
    7.Now you can confirm the 2nd operation & proceed for your other operation.
    operation.
    Regards,
    R.Brahmankar

  • Block Operation Number Change in Production order

    hello,
    How can i block the operation number change in production order if the operation status is CNF...?
    ie either disable the operation number cell or disable the entire row in the production order.
    rgrds
    Krishna.

    hi prashob
    i can't disable the column, as user need to insert operations in between
    AP, 
    I will check for this...
    regards
    Krishna

  • Add/change multiple operations on a released Production Order

    How can I add/change multiple operations on a released Production Order...I know how to add them manually one by one but is there a better way to add...like copy/paste since i am adding operations from an alternate route? Please advise?

    Hy Aziz,
    In process order go to operation screen go to Operation - Include Master recipe, then one pop up comes select required Master recipe and add operations of your interest.
    But there are some restriction which doesn/t allow it if Inspection Lot, Control Recipe are created..
    Regards,
    Dhaval

  • Relation between operation and component in Production order

    Hi All
    I am new to PP. I need to get the tables which gives relation between operation and components in Production Order. I need to display in smartform the components assigned.
    Thanks and regards
    Swetabh Shukla

    Hi,
    Try with AFVV Table.
    You need to get the Details of the Filed : AUFPL from AFKO.
    Hope this helps..
    Regards,
    Siva
    Hi,
    You can get the details from Table : RESB.
    Regards,
    Siva
    Edited by: Siva Kumar M on May 23, 2008 10:49 AM

  • Operation wise cost through production order

    Hi Experts,
    Is There any standard report to get Operation wise cost through production order.if it is there please provide the details.
    Thanks & Regards,
    Prabhakar

    HI,
    I don't know a standard report but table CKIS contains the costing details line item wise with the corresponding operation number (CKIS-VORNR).
    So a query/quick view using KEKO + CKIS should be sufficient.
    Best regards, Christian

  • Problem in BOM explosion for a operation Sub Contract.

    Hi All,
    Please advise how to explode a BOM or Assign component in a Purchase order with Item category (L) for a Operation SubContract External Processing  oriented material for which no material code is created from a Series Operation production order .
    Actually in my scenario, no raw material component will send to the Sub -Contract Vendor. Only Assembled operation material lets say operation 20 from a routing ( which is not having material code ) from an In - house production from a shopfloor has to be sent to the vendor to create a operation 30 material , which is also not having a material code." How to explode a BOM or component allocation for the Non- codified Item in a PO".
    regards,
    YK

    Hi
    Change the control key of the operation to PP02. System will prompt u to PR data screen where u have to tick on Subcontracting checkbox. Enter other mandatory field like material grp, cost element, purchasing grp etc. On saving system will create PR with line items. System will trigger the components reqmt based on the assignment to operation. Example if for operation 20, materials M1 & M2 are assigned, then in the PR u will find M1, M2 in the component screen which u have to send to the vendor.
    Hope it is clear to u.

  • Operation wise Report of production order

    Dear Experts,
    I am having total 4 operations in production order .I want operation wise report ( For example ,I am having production order of 10 quantity , I want a report through which I can check how much quantity is lying in operation 10 ,20 30 & 40 )
    waiting for inputs.
    Warm Regards,
    Satya

    hi,
    Work Center
    CRHD Workcenter Header Data
    CRCA Workcenter Capacity Allocation
    CRCO Workcenter Cost Center Assignment
    CRHH Hierarchy Header
    CRHS Hierarchy Structure
    CRTX Workcenter Text
    KAKO Capacity Header
    KAZY Intervals of Capacity
    Routing
    PLPO Routing Operation Details
    PLKO Routing Header Details
    MAPL Routing Link to Material
    PLAB Relationships - Standard Network
    PLAS Task List - Selection of Operations
    PLMZ Component Allocation
    PLPH CAPP Sub-operations
    PLFH PRT Allocation
    PLWP Maintenance Package Allocation
    PLMK Inspection Characteristics
    Bill of Material
    STPO BOM Item Details
    STPU BOM Sub Items (designators)
    STKO BOM Header Details
    MAST BOM Group to Material
    STZU BOM History Records
    STAS BOM Item Selection
    STPF BOM Explosion Structure
    Thanking you

  • Sub contracting in CS order

    Hi Guys
    Any idea how to update the field subcontracting in CS order with BAPI or other functions?
    Batch input is not optional.
    Thanks in advance

    Hi,
    You have to maintain material master for both - Ordered Material & the material in the BOM of ordered material. Also you have to maintain procurement key as X - Both procurement types possible. When the planned order is created for the final product, you can convert the Planned order to PR with item category L - Sub Contracting, system prompts the material to be supplied to subcontractor in Material Component list (BOM Material). You may transfer the material to the sub-contractor via transfer posting (MB1B) movement type 541. When you post GR for final product, the BOM material is consumed for the Final product via movement 543.
    Hope the query is fulfiled.
    Reward proper points if the answer is helpful.
    Regards,
    Prashant Kolhatkar

  • Operation status 'Fixed' in Production order

    Hello all,
    We are facing an issue with Operation Status 'Fixed'. If we go to transaction /sapapo/rrp3 and double click on Production Order (R).  Then clcik on Operation , say 0100, at right side you will see multiple Operation status. One of them is 'Fixed'. We can make this indicator active ny fixing the order in planning board (right click=> Fix).
    Here we are facing an issue. We are not fixing any order through planning board and still I see Operation status 'Fixed'. Even I unfix it, next day it gets fixed automatically. I suspect that either any job in APO or R/3 do this activity. Please note that in this case 'Date_Fixed' indicator is not checked. Like when you fix the order from planning baord, system check the checkbox for 'Date_Fixed" and for operation status 'Fixed'. In our case only Operation status becomes 'Fixed.
    Please let me know what are the different ways to fix the operation status.
    Regards,
    Nitin

    Thanks for the reply.
    As you mentioned, if the operation is scheduled at non-working hours then it gets fixed. I checked with the user and they confimred that they are not using the non production hour while rescheduling the order. It means they are not using the check box of non-working hour from DS startegy or Heuristic.
    Please let me know what are the different possibilities which can schedule the operation in non-working hours.

  • Operation wise confirmation in Production order

    Hello,
    I want to make a new order type where operation wise confirmation is possible in Production order scenario Presently the std order type PP01 is used , where the user is doing the confirmation at order header level but now user want to go for operation wise confirmation by using CO11.
    I know we can put the confirmation parameters in OPK4 , but not aware exactly where we need to define about the operation wise confirmation.
    Waiting for the reply
    Regards,
    Ravindra

    Dear Ravindra,
    The general control key settings are
    PP01 - Inhouse manufactured or for the operations which are processed internally
    within the shop floor or company.
    PP02 - Externally processed operations.
    PP03 - Auto - GR,where in no need to carry out MB31.
    For each control key,you can also set whether confirmation is a mandatory or
    confirmation is possibel but not required.Check in OPJ8.You can get a better
    understanding.
    Regards
    Mangal

  • GI for every Operations, not for whole production order

    Hi,
    I have assigned the components into operation and would like to do goods issue for every operations.
    But MIGO or MB1A only do goods issue for whole production order, there is no selection fields for operation no.
    How can I only do the good issue for production order by operations?
    thank you very much.
    Best Regards,
    John H

    Hi,
    You can do goods issue for each operation using backflushing while confirming each operation.
    In CA02 that is in routing go to component allocation select the components which you want to issue for certain operation and select new assignment. In new assignment select the operation.
    In the same manner select the components which you want to issue and assignment it to operation.
    Hope it will help you.
    Regards,
    Alok Tiwari

  • Sub contracting and production time

    Hello Experts,
    My problem is related to sub contracting and how to reflect the time the subcontractor needs to produce the goods.
    My system works as follows. 
    I create a subcontacting for material A. This material has delivery time 5 days. I supply the subcontractor vendor with material B. This material has also delivery time 5 days.
    So, when I set the delivery date to ie 02.02.09 for component A, I get the requirements date for component B to 10 days less than my requirements date.
    This means that I need to have B in my stock 10 days before I get A into stock. I guess that this is caluclated using A and B's delivery time and in this case, the five days i meant to reflect the number of days from me to the vendor.
    This does not reflect my needs.
    I also need to be able to reflect the production time at the vendor. This is the number of days between he receive B and when he can ship A. As this works now, the vendor is given no time to manifacture A out of B.
    Second, the time it takes to ship B will be very different denpendent on which vendor who will receive it.
    Any ideas how this is done?
    rgds
    GAR

    Hi,
    Please define the Total replenishment lead time (in workdays) according to your requirement.
    There is no point in maintaining the Total replenishment lead time field (in MRP 3 view of material master) for materials procured externally.
    In external procurement, the system adds the processing time from purchasing (maintained in SPRO> Materials Management> Consumption Based Planning> Plant Parameters> Carryout overall maintanance of Plant Parameters-->Maintain --> External Procurement), the planned delivery time, and the goods receipt processing time ( both in the MRP 2 view of material master data or in Vendor master data) and uses this total as the replenishment lead time for an availability check with replenishment lead time.
    Hope this will help.
    Regards,
    Narayana.

Maybe you are looking for

  • ICal crashes upon entering new events

    I just purchased a new Macbook Pro and I exported iCal data from my old Mac onto my new Mac. I opened iCal on the new Mac and imported the iCal data file. All of the dates have successfully been copied to iCal on my new Mac. However, when I double cl

  • Data retrieval in Maintainess views

    Hai experts, i am unable retrive data from the view V_TVFK. it gave error *"V_TVFK" is not defined in the ABAP Dictionary as a table, projection view or database view. * thnaks sitaram

  • Help with maverick update.

    I have the late 08 MacBook and I want to install maverick on there but I am unable to install it becaus of SMART errors. Can I just format my harddrive then install it via USB?

  • Best practices for including CSS on publishing

    In order to have completely self-contained project folders, I have css in my project folder.   I don't understand why you can include .js Scripts, and have them publish automatically yet you can't do the same for css scripts.  This is truly baffling

  • IDE that works?

    Hello! I'm looking for an IDE that works..... First I tried Suns Java Studio Mobility..... it was extremely buggy....got exceptions when trying to import...... Then I tried the eclipseME plugin for eclipse..... it was even more buggy......the J2ME ca