OPM Actual Cost Process not selecting all Inventory Movements

We have completed 27 Move Immediate transactions (TRNI) but only 2 of the transactions appear in the Actual Cost Transactions View so our PMAC cost is not as expected. Those 2 transactions were in Sept '09. All other transactions happened in Apr, May, Jun of 2009. On July 7 the profile option "GMF: Include Inventory Movements in Actual Cost" was changed to YES. Does this mean that the Actual Cost Process will not pick up those move immediate transactions that occured before July 2009?
Robert Lovell

Hi Robert
Yes...exactly, since you have closed all the said periods before u run your Actual cost process, and later you changed your profile option.
If you want, that all the transactions (TRNI) to be in Actual process as View, Functionally (I mean from front end) it is not possible now, but u can make use of PL/SQL Language by means of technical help then you can open those periods from back end and then do the set up from front end, and then you may able to view those transactions.
It is purely technical help and require some gud stuff to do this.
Regards
Raj

Similar Messages

  • OPM Actual Costing (PMAC) not including AP Invoice transactions

    Hi,
    OPM Actual Costing (PMAC) not including AP Invoice transactions in 12.1.3 version. We have set profile GMF:Include Receipts in Actual Cost = 0, GMF:Include Invoices in Actual Cost = 1 still AP Invoice not included in OPM Actual costing.
    Observed, Invoices which has IPV are shown as in Actual transaction view with line source as "Invoice Price Variance". I was looking for a line source with "AP invoice" and "IPV"(if exisits) in Actual transaction view screen.
    Thanks,
    Solomon.

    Hi,
    did you run the extract AP charges request ?
    thanks .
    Ahmad.

  • Decision Pop up while starting actual cost process

    Hi,
    Can anyone help me on this?
    I am getting a Decision Pop up while starting actual cost process.
    Prior Inventory period has not been closed. Cannot proceed.
    By clicking on continue, the accept button became available and I launched the process.
    However, we are uncomfortable with that situation since it looks like that February period is closed for all inventory accounting periods under that LE. It is also the first time that we are getting that pop up decision screen since we are testing under R12. We want to understand the reason for that.
    Note: it is the first time that we were trying to close a period before fully completing it (closing Feb period on Feb 29).
    NOTE: This is in UAT. This does not occur in any other instance (Dev, PPB, CRP).
    We normally did not perform final cost update and the calendar assignments org periods will be always open.
    Let me know if you need any more details.
    Thanks & Regards,
    Kannan Jay

    Thanks for your quick response yesterday!  After chatting with our official IT guy, He lined some things out for me.  We are using SQL 2005.  We discussed working up a program to add our data directly, which is an option.  It will take some learning on my part, and I am willing to do it. 
    It would be optimal, in my mind, to use our web version in conjunction with Labview.  But the more experienced person might know better.
    When I call up our webpage on the front panel, I am able to navigate it by clicking around just like a normal browser.  Using this method, the refresh issue I mentioned in my original post is not a problem.  It refreshes with no pop-up.  BUT I lose the capability to place my data into the fields.  I am assuming the reference at the property node before the data placement is incorrect. (pictured below)
    Is there a way to physically navigate a webpage and then use Labview to find the reference of whatever page I am currently on in order to place my data?  This might be the route I need to go.

  • Actual Cost Process request run terminated with Error Signal 11

    Hi All
    Could not run Actual Cost Process as it is terminated with error signal 11. Please tell me the reason/cause if any one has come across this error before in your cost running process. Thanks in advance for your valuable suggestions.
    I am using PPAC cost method and on Release 11. I search in metalink and Apply Patch 5208603, 5475347 but But failed
    Pls Help me???

    Hi,
    Were you able to relink the executable file via adadmin successfully?
    Please see if these documents help.
    Note: 402805.1 - Actual Cost Process Fails With Error Message 'Signal 11'
    Note: 402829.1 - GMCACOST Actual Cost Process Completes In Signal 11 Error After Applying Patch 5386789
    Note: 375764.1 - Actual Cost Process terminated with Signal 11
    Note: 389970.1 - Actual Cost Process erroring out with Signal 11
    Note: 338230.1 - Actual Cost Process Failing With Signal 11 Error while processing inventory transfers
    Regards,
    Hussein

  • About Actual Cost Process Procedure

    Hai,
    I want know about , what procudure name oracle using to caluculate the Actual Cost Process item cost...Pls give me all Procedure and related table name.
    Because one Item Cost is calculate different from prevoius month.I want found all transactions for this items (OPM,Purchase,receipts ans all).
    I am using in Oracle OPM finanacials 11.5.8
    thanks,
    Thivan Syed Sulthan.

    Hi
    In the cost screen there is a menu that shows all the transactions that the item has taken for the calculations of the cost. This can be done by the user himself
    REgards
    Girish

  • Actual Cost Process - ORA-00001

    Hi
    Is the anyone knows this error ORA-00001: Unique constraint (GMF.CM-CMPT_DTL_PK) violated.
    **** sy_etrap - FATAL_ERROR ****%N%NFunction: gmfaput_cm_cmpt_dtl_insert%N%NStatement: insert from cm_cmpt_dtl_raw%N%NError: ORA-00001: unique constraint (GMF.CM_CMPT_DTL_PK) violated
    Thanks

    Hi;
    What is EBS version?
    Please check below notes which could be helpful for your issue
    Actual Cost process Error ORA-00001: Unique Constraint (GMF.CM_CMPT_DTL_U1) Violated [ID 358603.1]
    Autoinvoice Error: ORA-00001: Unique Constraint [ID 1219263.1]
    OERR: ORA 1 unique constraint violated [ID 18222.1]
    Regard
    Helios

  • Expense allocation calculations on OPM Actual costing.

    Can any body provide a Document on Expense allocation calculation on OPM Actual Costing please.
    Regards
    Raj

    Jayabalan,
    Sorry for delay. I have to check the other setups too to determine the cause of this error.
    Please check if this item is transacted in prior period (Mar 2006) and ic_perd_bal table has any record for this item-whse.
    Else we have to involve Oracle Support through TAR to verify the log file and other setups to determine the cause of this error. They may need the Actual Cost Process log file with debug level 3 (profile: "GMF: Debug Flag")
    You can contact me through mail [email protected] if you want any help in debugging more in this.
    Thanks,
    Dinesh

  • Actual cost are not updating in prodcutcost collectors ( KKF6N) - Variances

    Hi SAP's
    We are facing the problem with the Variance calculation for product cost collectors.
    The issue is When we are calulating the Variances for prodcut cost collectors the actual costs are not ( For few materials of BOM) updating.
    Because of these the variances are showing high.....If I settele this variances to COPA, my copa report is will be going wrong.....
    Please help me to comeout of this problem.
    Thanks in Advance
    PrasadReddyS
    FICO Consulatnt

    Hi Anand
    Please add the budget profile at Plant maintenance order level no need to add any substitution rule
    budget should also be control at order level
    Thanks
    trinath 

  • You did not select all the docs belonging to the cross-co code transact Message no. F5876

    Hello All,
    When Cross company document is reversed with FBU8, Only one (1) leg is reversed and another (2) is not.
    For internal audit purpose, when any document is reversed, User should attach some proofs and then he should reverse it.
    When I tried to reverse only (2) leg through FBU8, I am getting this error – “You did not select all the docs belonging to the cross-co code transact Message no. F5876”.
    Pls give me some inputs how to reverse (2) leg.
    Thanks

    Hello Kalim - I am getting error message. We can not make it to warning message, though we have option in OBA5.
    Any other alternatives?
    Thanks

  • Error while running Actual Cost Process.

    Hi,
    Currently i am trying to implement Actual Costing with calculation type as (PMAC). when i run the actual cost process it is showing the error below.
    Errors:
    Warning: Cannot find the previous cost period record.
    Warning: Total allocated GL expense amount on item MN1-004 is zero or negative.
    Do please help me in Using Gl Expense allocation process like what are the steps involved and how system will allocate the cost to items.
    Thanks
    Amit

    For the currency you are converting to: XXX
    INPUTCURRENCY dimension must have XXX as a member with "REPORTING" property set to "Y"
    and
    RPTCURRENCY dimension must have XXX as a member with "REPORTING" property set to "Y" and "CURRENCY_TYPE" property set to "R"
    It needs to be in both dimensions with the right properties.  INPUTCURRENCY is the currency dimension in the RATE cube, RPTCURRENCY is the currency dimension in the financial or consolidations cube.

  • ATV not syncing all of movies

    Just purchased new macbook 2 months ago and aTV; have installed all updates including new itunes update. Everything was working fine until yesterday turned on aTV and about 1/3 of movies in itunes not showing up in aTV and will not sync. Can't figure out why. All my movies are in the same format and were working great last week (syncing/streaming). I can add new movies to itunes and they will sync/stream just fine. I also click in itunes to create aTV movie on one movie that won't sync and it says it is allready in the aTV format. All my movies play in quicktime and itunes just fine. They all sync with ipod touch and play just fine.
    Any help would be great.

    could be a corrupted iTunes library file... (i.e. not the folder, but the text file that has all the info about the media in iTunes)
    just to get it working.. sounds like you could just go to movies in iTunes do select all (Cmd + A)... press delete (when/if asked choose.. don't move to trash) and then select all your movies in the finder and drag them back into the iTunes window again... from what you've said this will likely work too.. might try deleting one and put it back and see if that works first.
    or if you wanted to start from scratch... you could actually delete the iTunes library file (it's file in the iTunes folder that holds all the info about what is in iTunes).. remove all the content in iTunes go to movies, music etc and delete everything.. remember to choose not to move to trash. then add it all back (can just grab the containing folder (iTunes folder if that's where everything is) you can take the whole folder and drop it on the iTunes window don't need to select each file.. which would take forever) and you will have a fresh, iTunes Library file.
    remember if you have things stored on different drives and you don't want them in the iTunes Folder press ctrl as you are dragging and they will not be copied into the iTunes library and just a reference to their location will be noted in the iTunes library.
    [edit] to see the other checkbox just open up iTunes... click music or movies.. does't matter.. look at the list of any media an to the far left of the list are checkboxes... these turn off syncing to iPod and appleTV... maybe you just didn't notice them before? but just in any list of anything has this checkbox off to the far left of the list... there is a checkbox for each piece of media.
    Message was edited by: tmartine

  • Captivate will not record ALL screen movements

    I have been using Camtashia and recently move to another
    company where they want to start using Captivate. I just bought
    Captiveate and I am getting very aggrevated! Captivate will not
    record all my movements with the mouse or when a screen changes. It
    appears that everything is driven by an actual mouse click. Only
    when I move my mouse around and then click will it actuall record
    the "action".
    Please tell me there is a way for Captivate to record all
    mouse movements, keystrokes, changes in applications just as I see
    it when I am actually doing the recording.
    I dont need all this fancy highlighting and project wizards,
    I just simply want Captivate to record EXACTLY what I do and see
    while I am recording.
    PLEASE HELP!

    Hi Tmy8ster and welcome to our community
    No doubt you are frustrated if you are expecting Captivate to
    behave like Camtasia. Yes, both create similar output, but both
    accomplish it in entirely different ways.
    Perhaps the following link to a thread where I attempted to
    explain it will help:
    Click
    here to read the thread
    Cheers... Rick

  • Actual cost process

    Hello to all! I wanted to know if somebody can help me with costs of OPM. I am working in a test instance and I will make inventory transactions: Purchase receptions, Transfer among werehauses, inventory adjustments. As well as, to report in WIP of production batches. I have ready standard cost of each item and I want to know if it is enough to copy it at the current cost before beginning to make the transactions and calculate actual costs or I have to make some other process.
    rgvel@

    Hi
    I am not sure what the purpose or itention is and hence the question becomes a bit unclear. Could you please elaborate on what is it that you want to achieve. You mention about actual cost and then you say you have standard cost available
    REgards
    Girish

  • Actual Cost is not updating in Production Order & WIP

    Dear All,
    I have issue in production order and Work in Process not getting Target Actual cost in costing view CO03 & KKAY.
    Is there any settings or transaction missed out? Please guide me how to sovle the issue.
    Thanks & Regards,
    Venkat.

    Dear,
    Please check,
    For Target cost
    1. Your std cost must be released before Goods Receipt
    2. There must be goods receipt posted on the prod order
    3. You must calculate variances in KKS1/2
    For Actual Cost
    1. Post Goods receipt and Goods issues
    2. See if any mat movements are pending in COGI
    3. Ensure that operation is confirmed in PP and no entry is lying in COFC
    Also in CO03GotoCost-Analysis--Here change the lay out and check it.
    Regards,
    R.Brahmankar

  • Actual cost are not posted

    Hi all,
             I am  doing Purchase Order against project for service,assigning WBS Element in it,
    and doing service entry sheet against that P.O.
    But I am not getting plan & actual cost reflected in Project builder & reports.
    Is there any setting for getting Plan & Actual cost ?

    Have you accepted the service entry done? Actual Costs wouldn't appear unless you accept the service entry.
    If you haven't done planning (T Codes CJR2 or CJ40), Plan costs wouldn't appear on the WBS.
    You should be able to see commitments on the reports if you have the configuration settings for commitments.
    Regards
    Sreenivas