Oracle Projects integration to Primavera

Hi,
We are integrating Oracle Projects to Primavera for a construction client.
We are able to:
- Send project header and wbs information from Oracle Projects to Primavera
- Send activity and resource assignment from Primavera to Oracle
However, when we enter actual efforts and dates in Primavera, we are NOT able to interface this information back to Oracle Projects.
All setups as per 'E15794-01_PIP Integration pack.pdf' document and Project Management User Guide are done.
Has anyone done a Oracle Projects-Primavera integration, or has any clue? Thanks for your help in advance.
Regards
Balaji

Hi Dean and Dina,
Thanks for your answers. Following is the missing info:
- Yes, we are using the AIA PIP
- We are using 'Workplan enabled' projects for integration with a 'Partially Shared Structure'
- In integration options, we are only integrating 'Workplan' with a 'Working Version'
- We are trying to send only progress information from P6 to Oracle Projects, not the time card info
Iniitially, when trying to send progress from P6 to Oracle Projects, we were getting the error - 'You cannot update a published version of the workplan'
However, after checking the following flags, we stopped getting any errors in AIA/middleware and still not getting any data into Oracle Projects:
Projects --> Setup --> Integration settings:
Integrate - Workplan - Send Task - Current Working Version
Integrate - Workplan - Receive Task
Workplan --> setup:
Allow Physical Percent Complete Collection
Allow Physical Percent Complete Overrides
Thanks for your help.

Similar Messages

  • Compare Oracle Project Management and Primavera

    Hi All,
    We are using Primavera today and it is not integrated to Oracle.
    We are also currently implementing Oracle Projects Management (R12.1.3) and trying to evaluate if Primavera can be replaced by Projects Management. Based upon my little experience with Primavera - I see some advantages of Primavera over Projects Management e.g.
    a. Primavera is more user friendly than Oracle Projects Management.
    Primavera: easy to create workplan; configurable views; generate reports with gantt charts
    b. Primavera has scheduling engine to derive schedules based upon dates/duration/logic while Project Managment does not have it.
    c. Gantt charts are better in Primavera than Oracle Projects Management.
    Has anyone also done similar kind of analysis and evaluated the need of Primavera integration with Oracle Projects Management? I would appreciate if you can share your inputs.
    Thanks,
    Nitin

    Hi,
    I have used both the product. For project management i would suggest to use primavera for the same reason u mentioned.
    the only disadvanage in primavera is it is not integrated with ERP.
    Now oracle provide a AIA PIP integration package to integrate Primavera with oracle Projects(Limited integration). Use primaver for Project managment and oracle for Project Costing and Billing
    Govind

  • Oracle Project Analytics and Primavera

    Hello Experts,
    I would like to know whether Oracle Project Analytics supports Primavera?
    Thanks,
    ~ Ash

    Project Analytics only sources data from Oracle Projects in the eBusiness Suite. So, the only way that you would get planning information from Primavera into Project Analytics out-of-the-box is if you have integrated Primavera with Oracle Projects. Oracle now have a separate Analytics product for Primavera, "Primavera P6 Analytics".

  • Projects integration with Primavera

    Hi All,
    Can some ome please point me the integration doc (E15794-01_PIP Integration pack.pdf) and any other required docs to integrate Projects and Primavera.
    Thanks,
    Kiran

    Hi ORCL_Projects     ,
    I am integrating primavera p6 v8.0 with Oracle project module in E-bushiness suite and i able to send project and resource from OP to primavera side but i am not able to do the same from primavera to OP i followed the instructions of implementation guide but after pressing send to ERP button the project not getting created in OP side and i checked also the EM-console i found that there's no any process fired .
    would highly appreciated if you advised me how to solve that issue
    thanks,
    Mohmed

  • Oracle Purchasing to Oracle Projects integration - Accruals

    Hi
    The Accrue Expense Items in Purchasing Options is set to Period End. If a purchase order which is project related is receipted, will an accrual be interfaced to Oracle Projects?
    Thanks for any help
    Regards
    Sean

    Thanks Raghavender for your reply,
    I have done some testing on this since and have found that if enter a purchase order in Orcle PO uisng either Period End Accrual method or Perpetual (At Receipt Accrual method) then a commitment will be transferred to Oracle Projects. However, when the PO is receipted, only the Perpetual method will interface the accrual to Oracle Projects (and reverses the commitment) and include in actual balance there. This has been confirmed in Oracl User Guide and Oracle consulting.
    Regrds
    Sean

  • Integration Methods - Oracle Projects with Primavera using API

    Hi,
    We are trying to do manual integration in between Oracle Projects with Primavera using API, if some one can able to help us on the process and procedure that would be really helpful....
    Thanks
    Rgds,
    Vijay
    [email protected]

    Hi,
    The Primavera intergration works with the "Standard Intergration" of Oracle 11i & R12.1 with the version of P6, this is the statement was in by the market experts. Even I have not worked on this intergration part of primavera with Oracle. still, I can provide you some search engine links, which could help you in http://www.projectp.com/products/op3.php ; http://www.projectedconsulting.com/index.php/community/blog/2010/04/primavera-and-oracle-projects-integration/
    Lavanya

  • Integration between primavera 8.1 and Ebiz-Oracle Project

    Hi all ,
    I need to integrate Primavera p6 v 8.1 with oracle E-busniess suite 12.1.2 is that possible ?
    Regards,,
    Mohamed

    Please see if these docs help.
    How to Integrate Primavera with Oracle Projects E-Business Suite? [ID 1091836.1]
    Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 2.5 - Release Notes [ID 959567.1]
    Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 2.5 - Implementation Guide [ID 956562.1]
    Thanks,
    Hussein

  • ORACLE PROJECT PORTFOLIO MANAGEMENT INTEGRATION PACK FOR PRIMAVERA P6 & EBS

    Hi,
    Where can I get the software ORACLE PROJECT PORTFOLIO MANAGEMENT INTEGRATION PACK FOR PRIMAVERA P6 and Oracle E-Business Suite?
    Suggest me.
    Regards,
    Mini

    It should be possible. However I will suggest you get in touch with your local sales representative for clarifying licensing policy. It may require you to purchase full license of AIA foundation pack and SOA suite.
    Oracle is expected to release new PIP solution for P6 and R12. You may want to wait for that. Search the forum and you will find lot of threads with details.
    Sachin

  • Project Management for Primavera Integration

    Dear All,
    I hope someone completed primavera and 11i integration successfully using AIA PIP. can anyone clear that where Oracle Project management is required or an optional one to integrate with primavera , only oracle project costing and billing module is enough.
    Barathidasan

    Sachin,
    Your information is really helpful, If I am not using Project Management then where to do the "Integration Related" Settings in Project Costing module to send data to primavera. Right now we have done Integration Related settings in Project Management module.
    Barathidasan

  • Oracle Projects VS Primavera

    Hi All,
    Can any please let me know Benfits, Features between Oracle Projects VS Primavera?
    Appreciate immediate responses
    Regards
    Raghavender K

    Hi
    Primavera is a scheduling tool, where you plan the project activities, assign resources, may track resources load and update planning.
    Oracle Projects is basically an accounting system for costing and billing, which Primavera cannot do. It is integrated with other ERP modules.
    Oracle Project Management has many similarities with Primavera, but is lacking the scheduling engine.
    Dina

  • Integration Settings in Oracle Projects

    Dear All,
    We are looking to integrate Oracle 11i with Primavera, The problem is we couldn't find Integration Settings* option in the Oracle project super user responsiblity. Can anyone guide me how to enable this option.
    Thanks in advance.

    Hi Rani
    The options should appear after the patches for Ebusiness suite 11.5.10.2 are applied. The below is what the documentation lists as mandatory patches
    EBS 11.5.10 CU2 with the following patches:
    – Patch 5644830 for Oracle Projects Rollup Patch 4 for Oracle Projects FamilyPack M (11i.PJ_PF.M).
    – Patch 3485155 for 11iPJ_PF.M.
    – Patch 8979063 for 11I.MRUP4 : Projects AIA Third Party Application Integration Cumulative Checkin.
    – Patch 10189818 - EBS:P6:11i.MRUP4: CUMULATIVE CHECKIN FOR AIA 3.1 RELEASE ISSUES.
    Specifically 8979063 provides the required options.
    If you have applied the patches above then is my interpretation that something has failed.
    Regards,
    Esteban

  • Oracle Project Management for P6EPPM Integration

    Hello,
    We are working on the integration between Oracle Primavera P6V7 and EBS 11.5.10.2. Is it mandatory to have the license for Oracle Project Management. In case it is not then can you please suggest alternative methodology
    Thanks and Regards
    Shiva

    Sachin,
    Your information is really helpful, If I am not using Project Management then where to do the "Integration Related" Settings in Project Costing module to send data to primavera. Right now we have done Integration Related settings in Project Management module.
    Barathidasan

  • How to Integrate Oracle Projects(EBS-R12) with Primavera P6

    Dear All,
    As i have a requirement that i need to *"Integrate Oracle Projects(EBS-R12) with Primavera P6 for Oracle Projects Accounting ( Costing & Billing ) using Application Integration Architecture(AIA-PIP)"*.
    So kindly suggest me to do the same.
    Thanks in advance for your valuable suggestion.
    Regards,
    Saravanaa

    Vishal, I would recommend that you post this question on the CRM On Demand Integration Development forum.

  • The integration between Primavera P6 R8.2 and Oracle E-Buisness Suite

    can any one help me
    i want to knowq if that possible to integrate Primavera R8.2 and Oracle EBS
    thanks alot
    Edited by: Mona Reda on 05/07/2012 06:11 م

    You can create your own custom integration using our P6 Integration API or P6 Web Services but would also have to use the integration architecture available on E-Business Suite side.
    We also have a pre-built Application Integration Architecture (AIA) Process Integration Pack (PIP) that does this integration. General information can be found here: http://www.oracle.com/technetwork/apps-tech/aia/learnmore/index.html
    The Oracle Project Portfolio Management Integration Pack for Primavera P6 and Oracle E-Business Suite 3.1 - Release Notes can be found here: http://docs.oracle.com/cd/E26778_01/doc.112/e20583.pdf

  • MSP Integration with Oracle Projects

    Hi Dina,
    Does the integration between MSP and Oracle Projects work without any issues in R 12.1.3? We've tried using it in the past with R 12.0.6 but have to say the experience was not good. It used to work at times and fail on other times. Most of the times the first time import from MSP to Oracle Project used to work but subsequent changes to the WBS used to give issues while trying to import into Oracle Projects (even though the link to the Oracle Project existed in MSP).
    One of our new customers (Construction Company) wants to create the WBS in MSP (Microsoft Project ver 2003 or 2007) and then import it into Oracle Projects to track progress, effort and cost. Any changes to the WBS (which happens frequently) will be done in MSP and imported back into Oracle Projects. Does the above mentioned requirement work consistently in R 12.1.3? Please let us know.
    Thanks
    Regards,
    Sri

    The MSP integration requirements that you describe should work in the latest versions of 11i e.g. (FP.M RUP4) as well as R12.1.3.
    My experience is that providing all scheduling is done in MSP then the integration functionality works well.
    The recommended process flow for MSP integration is:-
    •     Oracle Projects: A project manager creates a project in Oracle Projects from a project template containing information for deliverables, work breakdown structures, and resource assignments
    •     MSP: The unscheduled resource and workplan data is downloaded to Microsoft Project for scheduling
    •     MSP: The project is scheduled in Microsoft Project based on task assignments, task dependencies, task constraints, and other attributes
    •     MSP: The scheduled workplan data is uploaded to Oracle Projects for publishing
    •     Oracle Projects: The project workplan is published in Oracle Projects
    •     Oracle Projects: After the workplan is published, the project is accessible to all team members working on the project. Team members work on their assignments and report their progress in Oracle Projects
    •     Oracle Projects: The team members' progress on the tasks is collected for updating the project plan
    •     Oracle Projects: The project plan is updated with the team members' progress
    •     MSP: The project is now unscheduled. The unscheduled project plan is downloaded to Microsoft Project for rescheduling
    •     MSP: The project plan is rescheduled in Microsoft Project and the task information is updated
    •     Oracle Projects: The rescheduled workplan is uploaded to Oracle Projects for publication
    Andy.

Maybe you are looking for

  • How to remove the lines above and below  header in sqlplus report

    I run a sql*plus report whch i want to be outputted to XLS file. But the format is not matching. I am using data->texttocolumns feature of excel , which is manual . As the headers are coming dynamically from query . i CAN NOT set header off. So first

  • Questions regarding how I pay my Line Rental Bill ...

    Hi BT,  I'm currently a BE Broadband customer,  I was a BT Broadband customer back in the days when you had BT Home Hub 1.0 and 8mb packages which i was only getting like 5-6mb, 0.3mb upload and constant speed caps on my connection to 1mb.  You guys

  • SQL Error in Open Hub Service

    Hi, I am trying to send data from an ODS to flat file using open hub service. The process of creation and activation of open hub destination etc etc went smoothly. When I tried extracting the ODS data by pressing execute button, the following error m

  • Upgrading to OS X Server 2.2 Results in Errors

    After upgrading to the new Server 2.2 app today, I received the following warning once the upgrade process had completed: An error occurred while updating your service data. Services may not function as expected The, opening the Server app, I receive

  • IT0077 Ovrview

    Hello All We have uploaded all the HRSP's for 2007 US legal change for EEO reporting and mapped Old Ethnic Orgin data with New Ethnicity and Race Code's. I can create new IT0077 records for new and old employee's but when i do overview for IT77, it i