Order recommendation must be extra than the sales order quantity

Hi Expert,
               My client is using the MRP wizard to generate the Purchase and Production order once a sales order comes from customer than MRP create the production order for parent item and purchase order for chilld items with required quantity but there is a possibility of rejection which comes to know at the end of production and to complete the quantity required some time.
                                                                                Is there any possibility that MRP generate the recommendation 10%(for example) extra than the sales order quantity.So that it will full fill the rejected quantity at the end of production.
Thanks

Hi,
MRP in B1 designed in a way that you don't need to enter many choices to select from.  To fulfill your goal, I think it is not that difficult because you could export recommended order and calculate the new total by a formula like New Qty = Recommend Qty * 1.1 in Excel and DTW the production orders using the calculated results.
Thanks,
Gordon

Similar Messages

  • The amount of down payment must be less than the invoice amount

    Hi all,
    Our customers are using SAP 2007-PL15 and SAP 2007-PL41.
    When we want to create a down payment for a sales order, and we want to pay the entire amount of the sales order, including tax, we have to put an amount inthe TOTAL field of the Down Payment window since by default, the down payment amount is the total of the invoice before applying tax.  The DPM is
    higher than 100% (strange but I think it's normal since the down payment is not planned to take the tax in consideration).
    Then, we create an incoming payment for this down payment. It's ok.
    Then, we create an invoice based on the sales order we have paid with the down payment. It's impossible to use the down payment for the invoice... why that ? We receive the error 'The amount of down payment must be less than the invoice amount'. This causes big headaches to our customers !!
    Could you explain us what to do please ?
    thanks,
    Luce

    I'm very sorry, I have a similar question in dealing with AP Down Payment Request Linked to AP Invoice,  my case like this:
    1. I created 3 AP DPRs,their amount are each 100,000 RMB(for example, their document number are 10,11,12). then do the outgoing payment fully paided.
    2. I created a AP Invoice with the amount 150,000 RMB(for example, this AR Invoice document number is 5). I use the buttom"Total Down Payment",and selecet AP DRP No.10 and 11. When I click the buttom"Add",an error shows:
    The amount of down payment must be less than the invoice amount
    and I don't know how to continue.....
    Many Thanks
    Kam
    (PS:My English is poor,forgive me please. Shall I Speak in Chinese? then I can describe this question more clearly.)

  • The activity procedure date must be larger than the system date in VA42

    Please Help me...... I am trying to update the Contract End Date in VA42 but it is not updating and through an error message
    ''The activity procedure date must be larger than the system date''
    please help me to solve the issue....
    Thanks & Regards
    Shakeel

    Shakeel Ahmed Mohammed
    Please update how you solved so that it will be helpful to others who face similar issue.
    G. Lakshmipathi

  • The determined activity date 03/24/2009 must be later than the system date

    Hello everyone!
    I am creating a contract but this error message appears when I put a validity date: "The determined activity date 03/24/2009 must be later than the system date". Where in IMG can I adjust this? Thank you.

    no one responded.

  • Reconciliation amount must be less than the balance due for this tran

    Hi,
    I received the error below when creating an outgoing payment for the invoices.
    "Reconciliation amount must be less than the balance due for this transaction."
    I have found this thread from Forum "Reconciliation amount must be less than the balance due for this trans " but that was posted in 2009 Jul.
    The database version I am using is 2007B PL 13.
    Kindly suggest if you know the solution for 2007b PL 13 for the above mentioned error.
    Thank you.
    Regards,
    Yadana

    Hi Yadana,
    The solution from that thread is still valid for you. Your version is as early as 2008.
    Thanks,
    Gordon

  • Different sales office in billing rather than the sales office in contract

    Hi,
    I have a servive contract creted for Rs. 1000/-. I have periodic billing activated in contract. When I create a billing document I have to create it for different sales office. It means my service contract have sale office X and my bill should have sales office like Y in one billing and Z in another billing.
    Please suggest how to get this done ?
    Thanks,
    Ashok S

    Hi friends,
    thanks for your inputs..
    I need this in the scenario mentioned below.
    We have a scenario for service contracts.. Company X entered into a services contract with customer A.  Both the company and customer have offices round the country.  In a month when I am doing the periodic billing my company X knows that only 2 offices of the company have participated in providing the services to the customer at the respective locations.. It means that customer didn't get any problem in other locations.
    In the above mentioned case I wanted to segregate the bill amount to only to the 2 sales offices who have really performed the service. So that in a year ,company X wanted to know that how many sales offices involved in providing service to the customers and also in what ratio..
    Thanks,
    Ashok Sakamuri

  • Sales Order quantity Must not exceed Purchase order quantity

    Dear Experts,
    My requirement is when i am creating a Purchase order giving referenece as Sales Order .. system must not allow the user to enter  more than Sales order quantity.
    Ex : Sales Order 1234
            Material : AAAA
            Quantity : 100
    while creating a Purchase order for Mat AAAA giving  reference of Sales order i.e 1234 and quantity 150 system must not allow user to enter more than sales order quantity . If user wants to create PO for 150 he must have to ammend the sales order from 100 to 150  is it possible.
    Kindly do the needful
    Regards
    abhi

    Dear Abhinav,
    First of all, Purchase Order will get created with reference to Purchase requisition (T. Code: VOV7 --> Item Cat.: TAS --> Tab: Transaction Flow --> Field: Automatic PO Creation), and not with reference to Sales Order.
    This is Purchase requisition, which gets created with reference to Sales Order; based upon settings in:
    T. Code: VOV6 --> Schd. Line Cat.: CS
    Order Type            NB    Purchase Requisition
    Item Category         5     Third-party
    Acct Assgt Cat.       X     All aux.acct.assgts.
    Now, coming to your requirement (based up on my inputs),
    My requirement is when i am creating a Purchase order giving referenece as Sales Order .. system must not allow the user to enter more than Sales order quantity.
    To Restrict Purchase requisition quantity in PO, then in T. Code: OMCQ
    Or, Path: SPRO > img > MM > Purchasing > Environment Data > Define Attributes of System Messages
    Here make following messages as Error;
    06 076 Materials of requisition & item & alr. ordered in full
    06 254 Order quantity greater than requisition quantity
    Now,  in Purchase Requisition, if it is created for 100 qty (with ref. to Sales Order) and if you adopt the same in Purchase Order and try to change the qty to 150, then system will not allow you change and throws the error.
    Best Regards,
    Amit

  • SALE ORDER QUANTITY LESS THAN DELIVERY QUANTITY ? NO CECK IN SAP ??

    Hello friends,
            I created a sales order of quantity  10 , having two material codes each having quantity 4 and 6 . i created delivery for the one by putting delivered quantity 4 and save , then i created delivery for second and put delivered quantity 8 which was greater than the sale order quantity left ,system saved the delivery and didn't popped any error message.  
                                     Does SAP have options to over come this mistake by end users.
    regards

    Dear Joshi,
                      Please get in touch with your abap er as there user exits which can be written to avoid this situation.
                      Let me explain you further one more situation.
    First one, Your query is if for  item A ord qty is 6 the system saved the delivery with 8 qty which is greater than ordered quantity.  I know the gives a warning doing this.
    Second Situation :
    Say item A ordered qty is 5, and i made a delivery for 3 and saved it. Now the open quantity on the order is only 2. (5 -3 =2).  But one of our users reduced the ordered quantity to 2 despite saving a delivery with quantity 3.
    so the situation is ord qty is 2 and delivered is 3 qty. which is again wrong. But while reducing the ordered quantity less than the delivered quantity the system gives a warning message telling "  ORDERED QUANTITY IS LESS THAN DELIVERED QUANTITY ".
    Also just imagine we made delivery for qty 5 and invoiced it.After which you reduced the delivered quantity to say 3. So delivered is 3 but invoiced is 5.
    Hence for these kinds of practical problems we have addressed them through user exits with the help of our ABAP'ers by turning those warning messages into error messages by selecting the suitable message class.
    Hope the explanation helps you. And thanks for all your patient reading.
    Reward points if useful.
    Thanks & Regards
    Sadhu Kishore

  • Restricting prod order quantity from being higher than sales order quantty

    Dear Experts,
       I create production order interactively through co08 ( prod order with respect to sales order). the prod order automatically picks up the quantity in the sales order which is desired, but this order quantity field in the prod order is editable (i.e can be made higher or lower). Please how do I restrict this prod order quantity from being  higher than the sales order quantity?i mean what should be done to make system disallow the prod order qty being fixed higher than thesales order qty?

    Hi,
    Even though you create the production in refernce to the SO, the order quantity can be alter.
    This is a normal behaviour of the system.
    To restrict any change in the order quantity, you can use tarnsaction variant for CO08. T code is SHD0.
    Secondly you can use the following enhancements to restrict the same,
    PPCO0006
    PPCO0007
    Hope this helps you.
    SmanS

  • Delivery quantity is greater than schedule line confirmation quantity (sales order)

    I am creating a sales order with 30 Mt. I confirmed 10 Mt (partial confirmation and based credit block) in schedule line Now I am going to create the delivery system automatic taking 10 Mt but when I am going to change the delivery means when I increase the delivery quantity (20 Mt) then system allowing to do the further process.
    As per my understanding system should not allow to increase the delivery quantity m     ore the sales confirm quantity.
    Please suggest how I can restrict.
    Thanks & Regards
    Sujit

    Thanks for your reply,  As you suggest "B" is there. But its not working.  For ref. screen shot is attached.
    For reference I am providing some more details:
    => We are using "Make to order" process. After creation of sales order we assign the stock to sales order using T-code MB1B , Movement type 412E, 
    => Auto credit check applicable
    => Confirmed quantity in schedule line based on credit limit.(Auto credit check at Sales order level)
    => Avail. Check is 02 and check. rule is "AE" .
    Thanks and Regards
    Sujit

  • Sales order- Quantity Contract

    I need your expert advice.
    When we generate a sale order (using T-code VA01) against a quantity contract system will givee error message if you exceeds quantity  contract's order quanity.
    How can SAP generate error message (pop-ups) in this situation. where can we have these control in configuration.
    Similarly i want this control between our cistomized sales documents.
    Regards,
    Sumith

    Hi,
    Its very normal that you can enter order quantity more than the reference contract quantity flowing from the contract. This is standard functionality.
    Additionally it is not recommended that you change the standard SAP standard messages from warning to error etc.
    Better you should go for an exit. Use following details:
    Goto SE38 & enter include MV45AFZZ
    Then goto user exit "USEREXIT_SAVE_DOCUMENT". In this you should tell your ABAPer to write code such that it compare the previuosly refered quantity & hence does not allow to enter quantity more that that in contract. You will get error message while saving the document & system will thus prevent extra entry of quantity in sales order.
    Hope this solves your requirement
    Regards,
    Dhananjay

  • Sales Return Quantity to be adjusted in original sale order

    Dear All,
    We have a scenario, where Customer provides fixed quantity PO and we have to supply the items as per the schedule until the PO qty is completed and we have to supply additional quantity in case if there is any Sales return.
    Say the customer rejects 10 nos, we inward the item through sales return process. But we require these 10 nos to be reduced in the original sale order schedules, else we do not have track about the customer rejections and have to manually keep track to send the additional sales return quantity.
    Please guide how to accomodate the Sales Return Quantity in original sale order.
    Regards,
    Vinoth.

    Dear Vinoth,
    You can always create a return delivery without referencing a Sales Order.
    Goto the delivery type LR is the standard return delivery type.
    You could copy this delivery type and create your own delivery type.
    After copying then select the newly created delivery type and click on Details.
    Under the order reference , select No preceding documents required  for the order required field.
    Click on save.
    Now you can use this Delivery type to create return deliveries by using transaction VL01NO.
    Note :- The above solution is provided for your question but is not recommended as Best Practices.
    Thanks
    Murtuza

  • Automatic production order creation for remaining sales order quantity

    Hi All,
    My requirement is to create automatic production order for a particular material when the available quantity ( Stock in MD04) is less than the sales order / Delivery quantity.Automatic production order should only be created for deficit quantity.
    For example if i have stock of material A 100. I have recieved a sales order for 120 pieces. Now automatic production order should be created for 20 pieces only.
    Any inputs/ suggestions, please let me know.
    Thanks in advance !!
    regards
    Pawan.

    Hi Pawan
    In Material Master MM01 / MM02, you need to maintain 20 in MRP3 --> Planning --> Strategy Group.
    If you maintain this, items can be produced only against sale order you are creating.
    Dont forget to reward if this helps you.
    Regards
    G. Lakshmipathi

  • Material master table/field that can store a value that indicates the sales

    Hello Gurus....
    My Client is looking for a material master table/field that can store a value that indicates the sales volume (quantity) of a material. If the sales volume of a material falls within the top 80% of the total sales volume, then the material will have an indicator of "A", 15% will be "B", bottom 5% will be "C". Business wants to use this field to drive the automatic putaway into different pick zones.
    We cannot use ABC Analysis field (MARC-MAABC) or CC phys.in.ind. (MARC-ABCIN) since they are used for ABC analysis and cycle count based on value, nor volume. Using these fields will limit our future use of the true SAP functionality.
    field in Purchasing view in the material master called Mfg Part Profile. However, this is also against the original functionality of the field.
    Other than, this any other field we can use it? or the only option is to do a custom field?
    Regards,
    Kumar

    Hi
    I think the only option is to have a custom field.
    Regards
    Prasad

  • CFBundleVersion must be higher than previously uploaded version

    I got this error and cannot figure out how to resolve it.  In my info.plist file I set the Bundle version to 1.8.  My current binary on the app store is 1.7 and yet when I try to validate in the Organizer, I get the error that the CFBundleVersion must be higher than the previously uploaded version.  I tried changing the bundle version in Xcode and in parallel iTunes Connect to 1.9, to 2.0, to 1.80, to 2.01, to 2.8, and 3.8, but with no success.  The new version of the app is currently waiting to upload.
    Any ideas how I can get the app to validate properly in the Organizer.  I have never had this problem before and it is very frustrating.

    Dear xnav,
         Thank you!  I actually figured it out right after I posted and now it works just fine.  My misunderstanding was that I was trying to send a past archive thinking this was the new archive.  Thanks to you, I now understand this much better.  Then my problem was that "Archive" was greyed out.  All I needed to do, which you mention, is to select the build for an iOS Device rather than the simulator.  Then "Archive" showed up in the menu and it worked just fine.  I was able to archive the 1.8 version and upload it.  Thank you for all of your help.

Maybe you are looking for