Original Budget change KO22
Hi All,
My problem is I want to maintain the budget Periodically. But in planning profile & Budget profile two options i m getting one overall value & other annual value.
Please tell me where we maintain the setting for maintaining periodic budget values.
Any help will be appreciated.
regards
Meenakshi
Hi
You can maintan Budget periodically for cost center by using T code KPZ2
but it is not possible in case of order
Thanks
Ansuman
Similar Messages
-
Hi all,
I use transaction KO22 in order to change original budget amount allocated to IO, but here we have to enter IO each time to see the budget and change it.
Is there any other transaction which displays list of IOs and relative budgets and gives the possibility to change them simoltaneously?
Thank you in advance.I think it would be possible if you use 'Order group' and maintain multiple order under it and then do KO22. Foe change supplement,return you can use KO24, KO26.
Explore more on order group and let us know if it helps.
Thanks -
In original Budget crossing the limit for a particular order no error procd
Hi
In budget where the amount exceeds the original budget without showing any error message for budget exceeding. for example order no:xxxx amt 100000 and posting amt 200000 without error system proceeding. But generally system don't allow if we crossing the limit for a budget. here there is no error. I have to make it to appear error. Any solution is to rectify..
Thank uYa I am using Transaction group ++ and i am not using any exempt cost element. In quality its working if budget exceeding its showing error properly not alowing to post. Bust in production its not showing any if budget crossed limit allocation.
Its showing in ko23 : eg Budget 2012:23000, Current budget 2012:23000, Assigned 25000
I dont know why its like that in production. Please give me any idea whether any problem in order
But its working good in quality not in production. I checked starting to end all configuration.
Please give all idea as soon as possible. -
BAPI for budget change and update
Hi,
I am looking for a BAPI which can update the SUPLLEMENT field(budget change) for transaction CJ37.
The importing parameters are the following : Project Definition, WBS element, period and supllement value.
The BAPI BAPI_EXPENDITUREPROGTREE_CHVAL doesnt have the importing parameter (definition, WBS element).
Please help.Hi,
There is no BAPI for FM9K.
Regards
Abhii... -
Please I need to know about tables associated with the original budget date for PROJECT SYSTEM.
Thanks for your help.
Best regardsHi,
Try below:
Pass Objr of WBS to this tables
BPEG Budget revision header
BPEJ Budget revision header
BPGE Overall/annual budget
BPJA Overall/annual budget
Raghav -
Unable to post FR50 (Original Budget) for New Fund Center
Dear All,
We are in ECC6.0 and using Former Budgeting, Our business team created a new fund center and assigned it to cost center in the derivation rule.
Before they granted original budget using FR50, the business users started posting various invoices, expenses, POs, PRs against the cost center accordingly the Available Budget became Negative.
Now they are trying to post Original Budget for the new fundcenter using FR50, however system gives an error saying Payment Budget exceeded.
Please advice how to grant budget in such situations, we had an alternative to reverse all commitments and actuals posted against the fundcenter and grant budget, this worked in our test environment. However in Production we will not be able to do this due to too much volume already posted.
Is there a way to fix this, note that Availability control is active and not sure why system allowed to post without budget.
Any pointers, is this how standard SAP behaves or are we missing something.
We have also checked on master data elements of commitment item/fundcenter.. everythign looks fine.
request your inputs.
regards
DiwakarHi,
I believe you are using Former Budgeting. Please check below if this is not the cause for your issue:
Please check the following customizing that you have done in your system:
SPRO -> Public Sector Management -> Funds Management Government -> Former Budgeting -> Availability Control -> Define Parameters for Availability Control
See if you have set the flag: Check on lowest budget object with budget in your customizing.
Please check the documentation about this flag, specially this part:
"If you do not set the indicator, availability control runs against the first budget object, even if it has received NO BUDGET. This is the setting in the system as delivered."
You can check also report BPINDAN2_NEW.
This means that the budget is going to be checked in the first object with budget in your budget hierarchy.
If this is your case, you have only two options:
1.- Remove the negative budget you have in the combination of funds center/commitment item.
2.- Add the Combination funds center/commitment item to the exemption list of AVC.
I will prefer that you do the first option, as for me sounds strange to have negative budget, but this is one decision that you need to discuss it internally in your company.
If you choose any of the 2 options above, please do not forget to reconstruct your budget and assigned values AFTER you have done one of the options above, with the following transactions (in this order):
1.- Run transaction FMBV in order to reconstruct Budget values.
2.- Run report RFFMRC04 in Test mode in order to check if there is still some inconsistency.
3.- If RFFMRC04 shows inconsistencies, then run this report in Update Mode.
4.- Reconstruct distributed values with transaction FM9P
5.- Reconstruct Total values with transaction FM9Q
6.- Reconstruct assigned values with FMBV again.
I hope this helps.
Best Regards,
Vanessa. -
Urgent - Business Object for Original Budget in Project Systems
Hi,
I am working on a workflow for original budget release in Project Systems.The transactions used are CJ30 (Original budget creation) CJ32( Budget release).
I have to send a workitem fo release the original budget for a user. But I am not able to find out any business object relevant to Budget.
Can any one helo me in this...????
Thanx,
Sivagami.RHi,
I have tried that option already. But I could not find any.
Any update????
Thanx,
Sivagami.R -
Original regions change like copie!
Hi there, I'm stuck with a problem: when I change a copied region (eg length), the original region changes as well! This also happens when I re-load the file from the audio window. Does anybody know how to solve this?
iMac G5/10.3.9/1.8ghz/768Mb I'm stucksorry, or add a bit of silence from another region (file) and glue them together then select create (when asked) for a new file.
-
BOR for CJ37, CJ34 - Budget change document (BPDK)
Anyone can tell me the BOR object for Transaction CJ37, CJ34
or for Budget Change document (BPDK)
I want to trigger my workflow whenever and budget update is happened. I used BUS2054 but this not relevent and not able to create even for change document in SWEC with BOR BUS2054 as it is not relevent with BPDK.
Please tell me the BOR for Budget Change document (BPDK), or Cj37 and cj34see error details
Trigger Location of Runtime Error
Program SAPLKBPS
Include LKBPSU03
Row 76
Module type (FUNCTION)
Module Name KBPS_GET_CURRENCY
Source Code Extract
Line SourceCde
46 ENDIF.
47
48 TABLES FM01.
49 IF FIKRS <> FM01-FIKRS.
50 SELECT SINGLE * FROM FM01 WHERE FIKRS = FIKRS.
51 IF NOT SY-SUBRC IS INITIAL.
52 RAISE FIKRS_NOT_FOUND.
53 ENDIF.
54 ENDIF.
55 MOVE FM01-WAERS TO TWAER.
56 IF NOT FIKRS_PERIV IS INITIAL.
57 MOVE FM01-PERIV TO PERIV.
58 ELSE.
59 MOVE FM01-CA_PERIV TO PERIV.
60 ENDIF.
61
62 "*** Anzahl Dezimalstellen bestimmen
63 PERFORM DETERMINE_DECIMALS USING TWAER
64 CHANGING OP_DECIM.
65 EXIT.
66 ENDIF.
67
68 *-----Waehrung direkt
69 IF NOT I_WAER IS INITIAL.
70 "*** Anzahl Dezimalstellen bestimmen
71 PERFORM DETERMINE_DECIMALS USING I_WAER
72 CHANGING OP_DECIM.
73 EXIT.
74 ENDIF.
75
>>>>> RAISE NO_PARAMETERS.
77
78 ENDFUNCTION.
79
80
Please sujjest the solution -
Copying a button - original copy changes too!
When i copy a button, every changes i do to that button, it
wil also change the oringal button i copied from. What gives?!
i want to copy it and not have to worry about the original
copy changing as well. How do i tackle this problem?
For example:
I have a button.
I copy it into a new scene.
I change the copied button (of course)
then when i go back to orignal button, it changes as
well!The easiest thing to do is create a seperate button in your
cast window.
You could write some code to change various properties of the
button (such
as the text of the button) but that is more trouble than it's
worth. What
you are doing is copying sprites (not the button per se), so
when you chnage
the button it affects all instances in your program.
Does that make sense? -
BAPI/FM for KO22 (Change original Budget)
Hello All,
I am trying to load Budget informations into SAP using KO22 transaction.
Can you please provide me the BAPI/FM name with which budget informations can be loaded.
Thanks in advance.
Regards,
Ramesh K.Hi,
Mine is 4.6c.
I am not able to view BAPI_0050_CREATE.
I will be uploading the internal number, fiscal year, overall amount and currency type in table BPJA and BPEG.
Thanks in advance.
Regards,
Ramesh K. -
Send mail if original budget was changed ( CJ30 )
Hi,
Is there a BADI, Customer Exit or something else that allows me to send a mail to the project manager if the budget was changed in transaction CJ30?
A project member changes a budget in a subordinated WBS-Element for example. The project responsible has to be informed about that.
I don't mean availability control.
I've thougt about an workflow too. But I found no business object or an event.
Thanks. UliHi Uli,
U can try below soltuion.
If you have configured SAP connect ( Tcode : Scot ) , you will be able to send mails from yr SAP system.
Then you can decide whether you want change the standard program to trigger the mail while the budget is changed or schedule a custom program which checks whether budget has been changed and triggers a mail to concerned people.
Regards
Balaji -
Hi there,
I am considering up grading to lightroom 5. But first I need to be sure I can retrieve my original library, which has been replaced by images from iphoto I hadn't slected. I currently use a lightroom 3 and have spent countless hours as a professional photographer improving my original photographs. Can I speak to someone regarding this matter?
I would really appreciate your help in resolving this matter asap.
Kind reagards
PabloMorning Geoff,
Hope you slept well. I have been busy looking into many of the things you
have told me.
Where should I start so much info.
There are 7 Ircat folders. Some empty some contain approx 7000 images. Some
of the images /altered on lightroom are here few maybe 50. Although they
are missing or offline and now in the CR2 format ( photoshop elements),
which is very strange. I think this an issue as to why it may have all
gone, changed? In another Ircat folder many images are in the condition I
left them although not all of them, the latest 2013 are missing. Also in
another extension Ircat folder many of the images are there I imagine the
same 7000 but cant be seen?
On my hard drive there is a folder I cannot open, it reads in progress and
says no App to open document, search App store for Application. Perhaps
this is the key, I also have little storage space on my hard drive.
Many images under 2012 on hard drive have the tiff image, with altered
version created on lightroom some now show as CR2 version to view the photo
photoshop elements opens up automatically, which I never use. I do feel
this is a major reason/ issue?
Also under certain folders with dates my images appear pixelated or blurry.
Under another heading the jpg version is great approx 73 some are missing
the latest and most important, unfortunately I want in Tiff.
Under another folder on hard drive I have many of the images I am chasing
approx 60 but the size is a concern 2-2.5mb, should be around 40mb?
In another folder all are in CR2 photoshop elements.
Time Machine, which I'm sure was inactive tells me it could not back up
disk?
Under thumbnails it looked promising all in DNG many missing and in CR2
format.
I thought I would let you know in case I haven't already that the memory on
the imac is very low, hence why I began trashing/ deleting images yesterday
thet are saved on my hard drive this is when all this mess occured.
Are there short cuts I can use to remove images that are duplicates without
lightroom becoming tempermental?
Were too next? I am hoping the originals can be found and installed in
their original form.
I really appreciate all of your help and time, please help me
Cheers mate
Pablo
On Mon, Dec 29, 2014 at 8:06 PM, Pablo Hughes <[email protected]> -
Original picture changed while saving the edited one
Hi,
I am an absolute beginner using Camera Raw.
I just edit a picture in Camera Raw 5.7. When I was finished I saved the edited picture using a new name. Unfortunatly the original picture has also changed. So now I have two identical edited pictures with different names but the original picture is gone. How can I keep the original?
Regards, NicoleThe original image is still there...it's just had processing parameters added to the raw file. If you really don't want them you can either go into Bridge, Edit, Develop Settings and hit clear. But if you do that you will loose all the work you put into making the adjustments...you might be better off going back into Camera Raw and create a snapshot of the settings them you can reset the image to it's default settings...
-
Budget Changes 2011 - Note 1568264
Hi Experts,
While doing customizing changes mentioned in Note 1568264. I stuck with a issue
Steps mentioned in NOTE 1568262:
1. Execute transaction code 'SE11'.
2. Select the 'Domain' option and enter the domain name as 'PIN_SLTYP'.
3. Select 'Change'.
4. Choose the 'Value range' tab displayed on the next screen.
5. Enter a new line item with the fixed value as:
Field Val.
Short Description
V
Income tax rates for very senior citizens
6. Save & Activate
When I am doing 6th step system creates Local Change request which is not transportable to QAS and PRD client. It is not creating Customizing request.
Please revert with your valuable suggestion on this issue.
Thanks
LalitHi Lalit,
Try this -
Go into change mode and change the 'Short Description' of data element or domain. Try to save it now, it will ask for the workbench request. Save it under that and then again reset the Short Description to the original one. Now activate it.
This practice is just to lock the object under workbench request so that you can transport it.
- Praveen
Maybe you are looking for
-
Can I use a USB hub to connect more than 1 hard drive/flash drive device to the EA4500?
Can I use a USB hub to connect more than 1 hard drive/flash drive device to the EA4500?
-
Whenever I save an MS Excel file to my desktop, it creates an icon on the screen. But when I try to open it, I get a popup that says "There was a problem sending the command to the program." This happens with all Excel files - but MS Word and other f
-
Errors in code that captures images from webcam
Here is the code import javax.swing.*; import javax.swing.border.*; import java.io.*; import javax.media.*; import javax.media.datasink.*; import javax.media.format.*; import javax.media.protocol.*; import javax.media.util.*; import javax.media.contr
-
HT4993 I can not send mms or email photos
Ive been on carrier data and wifi. Ive reset the phone mulitipul times. Ive turned on data roaming. Photos still upload to facebook and the like but i cant email or mms. i have a 5s...issue started 2 days ago.
-
Hi all, I have some problems adding a logo. I wonder where /i/ points by default. the manual says contact your administrator, but I am the admiistrator and doesn't know :)). I installed the ORACLEXE beta release. If i understand this correct /i/ shou