Overruling of planned delivery time in inforecord

Dear Experts,
for certain materials we have defined planned delivery Times within the respective material info records.
This is working as expected.
However, in certain cases the real delivery time for a material could differ from the one stored in the inforecord (be shorter).
Is it possible, that the end-user can overrule this planned delivery time during the PO creation, or do we have
to maintain the info-record for this (keeping in mind, that only as an exception the delivery time should be overruled).
Thanks for your Support on this and best regards.
Jan

Of-course they can change the planned delivery time at the time of PO creation.
System will fetch the default planned delivery time and delivery date as per defined material master.
But when you change the planned delivery time (in delivery tab), then system will calculate the delivery date automatically.
If this will happen very exceptional, then no need to maintain in info record or material master. Just change the planned delivery time at the time PO creation, system will change the delivery date accordingly automatically.

Similar Messages

  • Planned delivery time Pickup from inforecord not material master data

    Hi,
    Currently the delivery dates of the orders are calculated with the delivery time which is marked in MM02. Since the purchasing integrates this information in the info record, we want the delivery date to be calculated with delivery time of the info record instead of calculating it with the data of MM02
    Please suggest any config.
    Thanks
    Shital D

    Hi,
    Try like this, ME21N, put the vendor, material , plant and other Org elements, hit enter, and check P.O what is the planned delivery time that you are seeing, also is the same PIR also appearing in the P.O when you scroll to the right?
    Also note.. that system might be picking 3, maybe saturday and sunday holiday is coming, check that too
    Regards
    Shailesh
    Edited by: Shailesh Rajan on Jul 7, 2011 7:00 PM

  • System is not considering Planned Delivery time

    Dear Gurus,
    As iam planning for the month of January and running the MRP,schedulelines are getting generated but system is not condering Planned Delivery time maintained in the material master ie. 7days.Following is the example:
    I have a FERT-X with a component A-1PC in its BOM and its planned delvery time from vendor is 7 Days.If iam running the MRP on 13/12/2010 for FERT-X  100 PCS for January1,2011 then the schedule lines are getting generated for for component A is on 01/01/2011.But PDT is maintianed in material master is 7 days and same has been maintianed in vendor inforecord.But system is not considering it.
    Kindly help to resolve the issue.
    With Regards.

    I have one ROH which has two different vendors.
    Two scheduling Agreemnt with target qty 100000 kg each.
    Two different Vendor info record with Min. order qty maintained.V1-1000Kg,V2-6000Kg.
    One source list with two vendors and with respective scheduling agreement.
    Quota arrangement is there in which SOB is maintiained 50:50.
    I hv the requirement of 3084 kg of ROH.
    I run the MRP and two diiferent schedule lines are getting generated with 50:50 qty as mentioned in Quota arrangement.
    Not considering the minimum order qty maintiained in vendor info record.
    The above process is correct
    Only One doubt In Quota Arrangement?
    IS two schedule line is created after MRP run?
    Generally System will  select a vendor Whose Quota value is less
    quota rating   = quota base quantity + quota-allocated quantity/ quota
    Edited by: Sundaresan . E. V on Dec 14, 2010 3:26 PM

  • Planned delivery time in purchase agreement (contract)

    Hello,
    When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
    Can anybody explain why? And how to prevent this?
    Thanks,
    Isabel

    Hi,
    If you enter planned delivery time in Info record, it automatically copied to contract.  Make the planned delivery time in info record as blank.  Or you can remove the planned delivery time in Contract when creating it
    ~Thanks!
    Rajesh

  • Planned delivery time in purchase agreement

    Hello,
    When I create a material contract for a material master without an existing info record, the system leaves the field "planned delivery time" blank. When there is already an inforecord for the material, the system copies the planned delivery time from the inforecord in the contract.
    Can anybody explain why? And how to prevent this?
    Thanks,
    Isabel

    deleted

  • Planned Delivery Time from Material Master instead of PIRs

    Hi SAP Gurus,
    Do you know if there is a way to have MRP look at the Planned Delivery Time from the Material Master (MRP 2 tab) instead of the PIR?
    We would like to create global PIRs with a PDT of 1 and have the Material Master PDT set to a different number (example 5).  So when MRP runs it will read 5 instead of 1.
    Any additional information is appreciated.
    Thank you
    -nic

    Hi Nicholas,
    In Standard SAP will consider Planned delivery time maintained in Inforecord and than time maintained in Material master. Inforecord has higher priority than material master. When a requisition is manually created, the Planned Delivery date will always be taken from the material master.
    For MRP you can make setting OMDT for your plant or MRP group to determine planned delivery time.
    Deactive the flag 'Scheduling according to purchasing info record or agreement' in Customizing (Plant or MRP group). and test the same.
    Regards,
    R.Brahmankar

  • Planned delivery time in PO

    Hi All,
              Can you please let me know how the planned delivery time is calculated in a STO. Is it possible to change it manually in the PO?
    Regards,
    Ashwin.

    Hi Ashwin,
    Bydefault it is taken from the Inforecord in Standard and in STO with Billing.
    In STO w/o billing it is taken from the Material Master.( UB Doc Type )
    Regards
    Ramesh Ch

  • MRP - Auto creation of del schedule lines based on planned delivery time

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Nirav,
    This subject has been discussed repeatedly in this and other forums.  I must assume that you overlooked the rules of engagement, which state that you should first search the forums and other public sites, before posting questions here.
    Standard SAP MRP cannot be made to generate multiple items in a Purchase requisition.  The functionality you seek is usually achieved when converting purchase reqs to Purchase orders, where many single purchase reqs can be adopted into a single Purchase order.
    You also might want to investigate use of Vendor Scheduling agreements.
    Best Regards,
    DB49

  • Planned delivery time in Scheduling agreement and MRP

    Hello,
    Do you know is it possible to determine system so that MRP run will consider the planned delivery time from the scheduling agreement line instead of material master? Now the system read planned delivery time from material master when creating schedule lines automatically by MRP-run.
    Regards, jaana

    This can be customized in
    SAP Customizing Implementation Guide
    -> Production
    --> Material Requirements Planning
    ---> Planning
    > Procurement Proposals
    > Define External Procurement
    Here you can select the indicator "Scheduling according to purchasing info record or agreement" either at plant or MRP group level.

  • Planned Delivery time in case of Scheduling Agreement

    Hi All,
    Does system consider the planned delivery time in case of Scheduling Agreement for Vendor like in normal Purchase order and requisition?
    I am doing the MRP run, but system is taken planned delivery time into consideration. I have one material that is Inhouse produced material for plant X and Y Plant needs this material for further making of a finished goods.
    Y plant have scheduling agreement for STO from plant X. After MRP Run required Delivery date in plant X for Material is same as plant Y. but from Plant X to Y, it take 4 days to reach. So Ideally in Plant X this delivery date should be less than 4 days as plant Y.
    Please look into the issue and reply if you have some answers.
    Thanks
    Pavan

    Hope you have maintained different Planned Delivery times in plant X and Plant Y as per your requirement. For procurement in Plant Y the system would consider the planned delievry time maintained in Plant Y. If you want in-house production time to be considered with Basis date sheduling during MRP run in PLant X then enter the in-house production time approprietely. Else if ou want to consider the exact routing times then consider Lead time scheduling in plant X.
    If the above are maintained properly then you should get the desired result.
    Regards
    Ramanujan

  • Is planned delivery time is considered in scheduling agreement ????

    Hi experts
    problem is that the schedule lines (for external procurement) generated from MRP are not taking the "" Planned delivery time into consideration"". System is only taking the G.R processing time.
    I have mentioned the Planned delivery time in .
    1) Scheduling agreement for 1 day.
    2) In material master for one day.
    3) In info record 1 day.
    e.g Suppose req date is 13.07.2008. MRP run date 4.07.2008.
    a) Planned delivery time = 1 day . B) G .R processing time = 3 days.
    Now when i run the MRP on 4.07.2008.
    Schedule line is generated on - 10.07.2008
    Please Guide . How i can take care of that time which is requiered at vendor ends.
    Regards
    Rahul Bhardwaj

    Go to OPPQ for that plant
    Click on "External Procurement " tab and check if you have maintained any planned delivery time?
    Tick indicator " Scheduling info record/agreement " (This will take Planned del time specified in scheduling info rec or agreement)

  • How planned delivery time effects delivery creation?

    Dear All,
    Some time before, while placing order thro' CRM, we came across a typical error (hard error).
    "date (11/12/2011) lies afterthe end of validity calendar". 
    we could not place order in CRM but in SAP we could create save the order despite of same error but soft. However system didn't allow to create delivery for same order & same error message populated"
    Later it was found that it is because for material  " Planned Deliv. Time  maintained for say "X "days in material master MRP2 view" & was corrected.
    How planned delivery time effects delivery creation?
    For material even though planned delivery time was maintained as say for 500 days, sales order requested delivery date & delivery date in order schedule line got determined as order date (Considering avaliability of funds & material).
    i.e order date/req. delivery date/delivery date in schedule line are same as date on which order is placed.
    Regards
    Suhas W

    Hi,
    Extended your factory calender in SCA3.
    Regards,

  • Planned delivery time issue

    Hello Experts,
    We have below requirement.
    Created sales order for a particular material. Planned delivery time is picked from info record for that material and PR has been created.
    We are converting PR into PO and the planned delivery time is fine. Now we are updating the ASN from vendor with some prior dates. In MD04, the same got updated. However the sales order still shows the old planned delivery time only. How to get the new planned delivery time  in the sales order based on the ASN updated in PO.
    Example:
    Material: A
    Planned delivery time is 10 in info record
    Created sales order. Planned delivery time in the sales order is 10. PR created with fixed vendor and planned delivery time is 10 days from the date of creation.
    Converted PO.
    Now we received the ASN from Vendor that the vendor will deliver this material in five days. So accordingly we are updating the ASN in PO with delivery date.
    In MD04, we could the new planned delivery time based on the ASN. However sales order delivery still shows the previouls delivery date only.
    How to get the new delivery date in the sales order based on the ASN update?
    Regards
    Bala

    This is not standard SAP logic. Required delivery date on the original line item stays as it was when you issued the order. Then you create a confirmation (ASN) that is relevant to MRP with the updated delivery date. Planning sees the new date and acts accordingly, and also in the order you can see both "old" and "new" (in the confirmation tab).

  • Planned delivery time

    Hi,
    I have created a sale order on 1/7/2009 with a material which has planned delivery time of 4 days.
    Now when I go to the schedule lines screen I see that the delivery date corresponding to the confirmed quantity is 1/8/2009.
    Why is not SAP taking the 4 days into considerations while determining the delivery date?
    Please see below the screen shots:
    Scheduling configuration in material master:
    [http://i40.tinypic.com/14b2fyc.jpg]
    Schedule lines screen shot:
    [http://i44.tinypic.com/9pxkzc.jpg]
    Sincerely.
    Ketan

    Hi,
    You seems confused with planned delivery time in MRP 2 view of material master to Sales order delivery date.
    Material master Planned delivery time is for the material which is procured externally  through PR -- PO process.
    In Sales order the delivery date is with respect the ATP--Avalible to Promise.
    If the stock is avalible in the storage location on the date of Sales order creation, then system will consider the delivery date an the basis of confirmed qty in the sales order. You can check in CO09 for confirmed qty.
    rgds
    gsc

  • Planned Delivery time not considered after MRP run for scheduling

    Dear All,
    After running MRP, the planned delivery time maintained in Purchase info record is not taken into consideration for calculating start date of the schedule line of externally procured material generated by the system.
    Planned delivery time is 3 days & Requirement of parent material falls on 15/02/2010. With this, system should calculate the start date for schedule line as on 12/02/2010 considering 3 days Planned Delivery time.
    Any idea as to what might have gone wrong?
    thx for your help in advance.
    Rgds,
    Ranjeet

    Hi,
    Determination of PLD from the Purchase info record is maintained in transaction code:OMDT. Planned Delivery time is also maintained in Scheduling agreement. However, it is not calculating delivery date as well as release date.
    Rgds,
    Ranjeet