Partial deliveries in STO

Hello,
I am rather new to MRP and ATP check.  I have already searched the forum but i could not find how to solve this issue.
Can you please help me solve the issue below?
When we were creating outbound deliveries against STO, the deliveries were not appearing in transaction MD04.
Well sometimes the delivery appears in MD04 and sometimes it doesn’t.
In the material master, the strategy group defined was 00 - Noplanning / no requirements transfer
So we have added an additional entry in transaction OVZI, with source 1 - MRP type.
After this change in customizing, the deliveries started to appear in MD04. 
However since this change, the deliveries are now being created in partial quantity (probably due to stock availability).  The client doesn’t want to have partial deliveries they want only one delivery with total quantity.
I have checked the shipping details defined in the customer and it seems to be ok.  Partial delivery are not allowed
Could you please help me prevent the creation of partial deliveries?
Thanks and regards,
Yannick

Hi,
Do refer the below OSS Notes , it explain why we can stop the partial deliveries.
842829 - Characteristics of replenishment deliveries from STOs
16239 - Complete delivery indicator is not checked

Similar Messages

  • Partial Deliveries not created for STO

    Hi All,
    There are 2 materials used in STO. One material X has stocks in the supplying plant and other material Y doesn't have stocks in supplying plant. When user try to create using VL10G or VL10B system is giving error that Mat. Y doesn't have a stock and hence delivery no. cannot be generated. When I try to delete or block Mat.Y in STO then delivery can be created for Mat.X. User wants to create partial delivery of the Mat. X which has stocks and different delivery for Mat. Y when its stocks will be available future. How and where else can we check settings for partial deliver for STO.
    I have checked settings in Ship-to party for partial delivery and it is relevant for partial delivery.
    Please let me know your thoughts on this. Thanks!!
    Mohit

    Dear Mohit,
                 In the VL10B transaction you click on Material tab there you enter Material 'X' then execute the transaction it will give the background delivery for the Material 'X' only.
    I hope it will help you
    Thanks,
    Murali.

  • Open Order Quantity by partial deliveries in 2LIS_02_SGR/CGR/SCN/ITM

    members,
    One of our customers uses now in BW the following Datasources for Purchase Orders:
    2LIS_02_SGR
    2LIS_02_CGR
    2LIS_02_SCN
    2LIS_02_ITM
    This seems to be done via the standard way of working,
    These 4 Datasources go to the DSO 0PUR_O01
    The data of this DSO goes via another DSO (ZPUR_O01) to the purchase cube ZPUR_C07
    In the DSO all values are overwritten, so you have the latest values.
    I expected the field "Current goods receipt quantity in order unit" (= /BIC/OW_AKTWE_DA) to be the total.
    But it is the latest value
    What I need is the open quantity for an order/position:
    In case of partial deliveries I see that you have the value of the last delivery.
    As I want to have the open order quantity in reports, is it necessary to make an extra field in the DSO (based on Goods receipts), but then with a summation rule?
    Or are there better options to realize this?
    I also see the field OPNQTY(= Open Amount of Schedule Line (after Goods Mvmnt Assignment)) in the Datasources 2LIS_02_SGR
    2LIS_02_CGR which is not used currently.
    I might oversee something trivial as the open order quantity is an important keyfigure report about.
    If you have any idea, let me know.
    Thx in advance,
    Ben J.

    Dear Anand
    This might be happen, when your data sources is not active in LBWE .
    Ex: You have maintained your setup initialization, at the time all the DS might not be active. Hence those DS only have the data in RSA3. In Future if you want to go with some other DS, you delete the setup table once and once again you need to fill the setup.
    Hence i request you to delete & reload the setup table, and try in RSA3
    Regards
    Raju Saravanan

  • BAPI to retrieve partial deliveries in purchase order item level

    We have implemented an invoice scanning solution for all our purchasing documents, we seem to have an issue picking up partial deliveries in our scanning interface, in the delivery schedule at item level, if the delivery is not complete, you will see this information in this tab, is there any FM available that can display this information??
    Will 'BAPI_PO_GETDETAIL' have this information??
    Regards
    mark

    Hi Mark
    If you simply put a PO number and execute you will see you have this information available in POSCHEDULE
    Nabheet

  • Inbound deliveries with STO

    Hi,
    I am currently designing an interface with an external WMS and I am thinking to use inbound deliveries but it seems inbound deliveries with stock transport order have important restrictions :
    1. inbound deliveries are created with the quantity from the STO and not from the outbound delivery => risk on stock in transit
    2. The batch numbers are not copied from the outbound delivery to the inbound delivery (it is done in GR with MIGO if you post from outbound delivery)
    3. I haven't (yet) found a way to create automatically an inbound delivery when you post the goods issue from the outbound delivery. (it seems SAP is providing special development for that ?)
    Does anyone experienced the use of inbound deliveries with STO and what are your recommendation?
    Thanks a lot,
    JP

    Hi,
    We want to create inbound delivery in order to interface with an external WMS (Warehouse Management). We are not using standard SAP "decentralized WMS" interface.
    By using inbound deliveries for the interface, we can initiate the GR in SAP and then wait for confirmation from WMS. The WMS can then confirm different quantities if some discrepancies are identified during unloading.
    Also, creating inbound deliveries allow planning for receiving (i.e yard management).
    => We do not want to post the GR first in SAP and then send it to the WMS as they can find some differences during unloading
    => We do not want warehouse operators to work in SAP
    => We need a document in the WMS which will trigger task creation for GR for warehouse operators.
    => We want to use same solution for GR for external purchase orders and STO. So if we use inbound deliveries for PO, we want to use it for STO.
    Does anyone has experienced to create inbound delivery for STO from outbound delivery with Idoc (i.e ASN with DESADV) or specific development ?
    Thanks for your help,
    JP

  • Why there is no manual creation of deliveries for STO...

    Individual(VL01N) : You can create one delivery for each sale order on the screen. There is no manual creation of deliveries for STOu2019s. Transaction VL01N
    Why there is no manual creation of deliveries for STO...
    Thank you very much.
    Hoolaa
    Edited by: Hoo Laa on Mar 28, 2011 12:28 PM

    hi ,
             you have  to create a sale order process to delivery the tcode VL10B for STO Porcess. not VL01N.
    Regards,
    A.Sithanandan

  • Combined Deliveries for STO

    Can anyone tell me the criteria for combining deliveries for STO's.., I believe the delivering plant, receiving plant and delivery data....is there anything else........where do you configure this...
    i have two STO's where the delivering plants are different but the receiving plant/shipping point/ delivery date are the same and the deliveries are combining and give me a single delivery...that doesnt seem rite...can anyone help me in this..
    Thanks,
    Michelle

    Hi Sivanand,
    Thanks for responding.., but my problem is that i do not want combined deliveries when the delivering plants are different.say I have two or more delivering plants which have the same shipping point and when they transfer to the same recieving plant, the deliveries are combining. I want the deliveries to combine if there are more than 1 delivery from the same delivering plant but a delivery split if deliveries are from different delivering plants.
    A -
    > B
    C -
    > B
    D -
    > B
    A -
    > B
    I want total of 3 deliveries going to plant B
    I want the 2 deliveries to combine going from A ---> B
    a single delivery from C----> B and another delivery from D -
    > B
    All the plants belong to the same company code.
    Thanks,
    Michelle.

  • Partial deliveries

    Hello,
    I have partial deliveries for line items in SO even after marking customer master settings (C - Only complete delivery required).This seems to be a standard SAP and not sure why there are partial deliveries. (but i can see awarning message saying "Full delivery required") Can we make this to error?
    I have come across an OSS note : 546619, can this be implemented?
    Note : Through Batchjob deliveries are created

    In the copy control VTLA, check for the source and the destination (say OR to LF), at the item level what is the Data Trasfer - Item data. If it is 101, change it to 202 and check if it works. This may work with 'Part.dlv./item = C' in the sales order item.
    Else, you may have to write a routine which will check if the order is complete to be delivered and then assign it to Data Trasfer - Item data.
    Hope this helps.
    Thanks
    Mukund S

  • Sales Order u0096 Invoice first and partial deliveries Later?

    Dear all,
    I have a situation where the customers will make an order from us and they will pay us in full upon making the order. As such, we are required to invoice them first and make the shipment later.
    They required us to ship the goods to them in partial shipments. How should we handle this in SAP?
    With what order type can I invoice in full first, then make partial deliveries?
    Best Regards,
    Junwen

    Hi Siva,
    Now I agree with you. SO -> Pro-forma -> Delivery -> Invoice. Not bad.
    I suggest them instead of adding one more step. They can customize a layout for SO so that "pro-forma" step can be eliminated
    The print-out (or output) of SO can be designed to look like a pro-forma.
    After all Pro-forma is not going to serve any other purpose.
    So we are back to square-one
    SO(with customized layout) -> Delivery -> Invoice
    Cheers
    Ashish

  • Partial deliveries not allowed by Sold to party but allowed by ship to

    I am shipping to a customer that allows partial deliveries but the sold to customer does not allow partial deliveries. As a result the sold to customer setting takes preference over the ship to.
    Do you know of any way how the ship to customer setting will take preference over the sold to setting.

    Hi Francois,
    Its a standard SAP code that runs behind that gives preference to Sold to party than Ship to party. As the sold to party is the one who is placing an order........his preference is taken into consideration as it is upto him to accept partial deliveries or not.
    More over i dont see any logic behind the disagreement on partial deliveries between a sold to party and ship to party.
    In any normal business scenario, allowing partial deliveries depends on the business requirement of the sold to party and the kind the products they are dealing with.
    Its only after a mutual consent between the sold to party and ship to party the decision is taken on partial deliveries.
    REWARD POINTS IF HELPFUL
    Regards
    Sai

  • Bdoc Error"You must activate partial deliveries before you can specify "

    Hi
    While doing the downloads of customers from ECC to CRM, I am getting an error in Bdoc "You must activate partial deliveries before you can specify a max. number" .We are running on CRM 6.0 connected to ECC 5.0  .I have checked the Note 1338378 but it is only applicable for ECC 6.0 .Please provide your Inputs to overcome the issue .
    Regards
    Vipul Singh

    Hi Vipul,
    This is a master data issue. In ECC system go to Tr. XD02 select your customer go to sales area data -> go to shipping tab and in partial delivery block correct the data. If you have selected partial delivery per item = C i.e only complete del. allowed then take out the value from the field max. partial delivery. Save your changes.
    Then you will get another Bdoc error " partner with GUID XXXXXX does not exist" ignote it.
    Bring the customer using the request load.. and you should be good.
    Thanks,
    Vikash.

  • Partial deliveries - per Material pricing group

    Hello, I need to create partial deliveris per 1 sales order - based on Materail pricing group (per batch job) - so 1 delivery will group materials with same Material pricing group.
    Is there any standard solution? I only found VL10C, but there is not Material pricing group as a selection field.

    HI,
    As per standard there in no such option..........

  • Customer master; need 3 by deafult at Max. partial deliveries

    Hello
    when i am creating Customer for account group of Sold to Party, in Sales Area Tab> Shipping >
    by default i am getting '9' as Max. partial deliveries. i need to make as 3 By dafult.
    will you please help me.
    regards
    pinal

    Hi
    Thanks for re-correcting me.Raja.  As max no of partial deliveries should be set as 3 in CMR and in that set 3 we have max no of deliveries as 9. Instead of that I have said in a different way.
    For having max no of partial deliveries as 3 we should either go with enhancement
    Regards
    Srinath

  • Why only 9 partial deliveries are available in SAP?

    Hi experts,
    In SD, up to the maximum of 9 partial deliveries are allowed.. Why SAP has fixed only up to 9?.. Kindly help me out for this..
    Thanks in advance

    In SD, up to the maximum of 9 partial deliveries are allowed.. Why SAP has fixed only up to 9?.. Kindly help me out for this..
    It is not true. You can allow unlimited partial deliveries , please check F1 help for field KNVV-KZTLF:
    Partial delivery at item level
    Specifies whether the customer requires full or partial delivery for the item.
    Use
    You use this field to control partial deliveries at the item level. If the customer allows partial delivery, you can choose from different partial delivery options. For example, you can specify whether the customer allows you to make one delivery attempt only on the requested delivery date or whether unlimited delivery attempts are possible.
    When partial delivery indicator 'D' is set, the order can never have status 'fully delivered'. You must complete each item by entering a reason for rejection. This could be applied to scheduling agreements, for example.
    Dependencies
    You can enter a value in this field only if the customer allows partial deliveries for the entire sales document.
    (option "D" is unlimited partial delivery
    Please read F1 help fully!!!
    Regards,
    Csaba
    Edited by: Csaba Szommer on Jul 15, 2009 9:09 AM

  • Maximum partial deliveries

    Dear Gurus,
    Can I set the "Max. partial deliveries" in CRM to a number above 9. We want to set it to 25. Does this need an enhancement or have any implications?
    Please advice.
    Many Thanks
    Kumar

    Yes,
    as suggested above.
    if you maintain "D" you can make "N" no.of partial deliveries.
    But you cant restrict as you expected upto 25.
    here you have to confirm, whether you want to unlimited partial deliveries or specific no.of partial deliveries.
    If unlimited- you can go by above replies ( maintianing as "D")
    or if you want to restrict upto specific no. then you need to go for enhancement.

Maybe you are looking for

  • After Effects 12.0 cannot drag and drop files into it?

    I'm simply trying to drag and drop files into the programs project files. Has worked in other ae versions, help?

  • WD Message Manager - collect messages

    Hi All, we work with 2 WD-applications reporting their message in the messagearea of WD-application#1 How can I report messages without losing existing messages? I found note 940762 in this forum saying that it is possible to collect message using th

  • Can I install my Photoshop Elements CD on my new computer?  My old computer crashed

    My computer was hit my lightning and crashed.  Can I install my Photoshop Elements 8 on my new computer?  I have Windows 7 on the new computer and I saved the DVD with Serial number on it.

  • Server to server data transfer

    Hi all, I have created BAPI for MB1A movement type 201. it gives me a list of materials in a exel file. <b>I want to upload that file into another server located at different place.</b> Uploading has to done through MB1C movement type 521. uploading

  • Compare upgraded transports

    Hi Experts, iam wrking on an upgradation from 4.7E to ECC6.0, my task is to check the upgraded transports and compare the objects in DEV and QAS (quality) systems using the tranport number, i  have a plan to check every transport no  in SE01( transpo