we want to reverse the miro doc..
by mr8m we can do it complete but not partially..
tell me for partially reversal..
Thanks & Regards
Rekha  sharma

Hi
Alternatively you can issue Credit memo for the partial amount instead of reversing and reentering the same.
Regards,
Lakshmanan Krishnan

Similar Messages

  • MIRO partial reversal

    Hi,
    Please suggest me whether partial MIRO reversal possible for planned delivery cost
    Regards,
    Balu

    Hi,
    As your requirement is to partially reverse the delivery cost, try subsequent credit funtion.
    Thanks,
    Uswin

  • Partial reversal of a goods receipt from process order

    Dear All
    Could anyone please help me with explaining how to do a partial reversal of a goods receipt from process order? If Iu2019m using trans CORS I have to cancel the entire operation, which I donu2019t want to do. If Iu2019m using MIGO and MT 102 I only reverse the goods receipts of the produced material, the corresponding components from the BoM is not reversed with MT 262 as they are if I cancel with CORS, and I donu2019t want to do a second MIGO transaction in which I cancel the components with MT 261. I have also tried to create an operation with a negative quantity, but without any success.
    Itu2019s not an option for the business to reverse the entire quantity and then perform a new goods receipt with the right quantity.

    Hi again,
    I have been trying to do the reversal with CORR but Iu2019m getting the error message u201CMixed confirmation types (time ticket/time event) are not allowedu201D, message number RU179.
    Anyone who can help me on the way?
    /WM consultant on unknown territory

  • Partial reversal of statistical posting

    Hi,
    I am using statistical posting (F-38) for posting Letter of Credit  (LC) into books of accounts. Now when LC is disbursed, part disbursement takes place over the period. So i have to reverse the LC created in part. I tried F-19 (reversal of statistical posting). But by using F-19, i am unable to reverse the document in part amount. Let me know how it can be done ?

    Hi Deepak,
    Partial reversal is not possible.
    Regards,
    Kiran

  • Partial reversal of ARE-1 certificate

    Dear All,
    Can anybody tell me, if it is possible to reverse an ARE-1 Certificate partially but not for the entire document.
    Rgds,

    Dear,
    In what business senario you want to do partial reversal. I think you want to do quantity to quantitiy amemndment in that case
    If the customs officer noted a shortfall in the quantity of goods, the excise clerk entersthe shortfall as well. Since the where abouts of the missing goods cannot beaccounted for, they no longer qualify for exemption from excise duty. Your company
    is therefore liable for the excise duty on the shortfall, plus interest, backdated to the date when you removed the goods from your premises. The clerk specifies which excise registers to pay the excise duty from.
    Regards
    RKS

  • Partial Reversal of Reservation components

    Dear Experts,
    Can anybody give us way out for following scenario.
    Scenario:
    01. Transfer posting done against reservation having say 10 components ( A, B, C, D, E, F, G, H, I & J ).
    02. Consider each Item has Qty 10 PCs
    Requirement:
    01. Partial Reversal of components for B = 2 PCs & G = 5 PC against the same reservation.
    02. We want to do the above reversal in background.
    Can anybody suggest the BAPI or anything which will help us.
    Thanking you in anticipation
    Aniruddha

    Hi again,
    I have been trying to do the reversal with CORR but Iu2019m getting the error message u201CMixed confirmation types (time ticket/time event) are not allowedu201D, message number RU179.
    Anyone who can help me on the way?
    /WM consultant on unknown territory

  • Partial Reversal or Clearace of Bill Liability in F-20

    Dear Team,
    We have new scenario & realised one bill but partly.We want to reverse
    the same in F-20 & thing is that how we can make partial reversal of
    the bill liablity because bill not realised completely.When we selected
    reference bill in F-20 but there is no option for reversing the partial
    part ..Please let me know that SAP has any such feature which we can do
    in screen of F-20..
    Thanks & Regards,
    Dharmveer

    Dear Ravilla,
    The document type used in F-20 is assigned to business transaction
    0200 + variant 0001 -> Revesal bill laib. Normally the customer invoice
    doesn't include an entry which is assigned to item category 04000 =
    Cash. Because of this assumption, the business transaction 0200 doesn't
    allow item category 04000 by system default and it is not possible to
    change this limitation.
    The workaround for this is to create a new transaction variant for
    business transaction 0000 (unspecified posting), define the splitting
    rule for the new combination, and then link this combination to the
    document type. I'd also recommend to create a new document type for
    this particular type of posting.
    Mauri

  • Fixed Assets Config - Trans type to partially reverse a previous retirement

    Hi experts,
    Is it possible to create a transaction type to partially reverse a prevous retirement?  When trying to create/define a new retirement transaction type I am unable to specify a balance type, as it appears a retirement always defaults to a credit balance.  I also tried setting up an acquisition transaction type, as this allows me to specify a debit/credit transaction assignment; however, I can not set it to belong to the retirement transaction type group.  I also tried creating an acquisition trans. type that belongs to the acquisition trans. type group and set it a debit assignment, and retirement for both the consolidation trans. type and asst hist sheet grp.  This transaction allowed me to debit the asset to reverse a previous retirement, but the transation display on the asset acquisitions report and not the asset retirement report.  We need this partial reverse retirement transaction to display on the retirement reports for tax reporting purposes.
    Our business users need this transaction type as they will retire assets in month 1, and then in month 2 recieve additional data that reveals the retirement in month 1 was too much, so they want to partially reverse the month 1 retirement in month 2 (so leave the original retirement transaction in place in month 1).  Is this possible?
    Thanks in advance for you assistance.

    Go to AB08 and enter company code/asset and select the month 1 retirement document and reverse
    And post a new retirement in month 2.
    After month end depreciation all values will be adjusted in GL accounts as well
    Srinivas

  • Bapi for reversing MIRO transaction

    Hi everybody,
    i want a bapi that i can use for reversing MIRO that is posted.
    Thanks in advance.
    Abhijit D.

    hi prabhu..
    thanks for the solution.
    this is a perfect one..
    thanks again.
    hi vikas..
    i didnt try the transaction u said
    but BAPI_INCOMINGINVOICE_CANCEL works
    fine
    nways thanks for the suggestion vikas..
    Message was edited by:
            abhijit dangat

  • Reverse MIRO document created through MRRL transaction

    Hello
    How can we reverse MIRO document created through MRRL transaction.
    Document cannot be reversed reason being -Error-Invoice doc. 5105692828/2009 was created via evaluated receipt settlement.
    Regards,
    Umesh Agrawal

    hi,
    As ERS doc. is created automatically so the data would be correct...
    Why you wanna reverse the ERS doc..
    If you have any returns/cancellation in between, make the return/cancellation document from MIGo, then again run the ERS, system will create the credit memo for the same...
    Regards
    Priyanka.P

  • Partial reverse of mov 313

    Hello!
    Can I do one partial reverse of movement 313?
    Best regards

    Hi,
    You canoot cancel partially this movement.
    What you can do is to create an opposite movement from the receiving storage location (e.g. original movement: from SLoc1000 to SLoc 2000; opposite mov. from SLoc2000 to SLoc1000).
    Regards,
    csaba

  • Partial reversal in STO

    hii all,
    plz let me know, how i can do partial reversal in STO.
    M using CIN, here, i have taken 10 items under STO Process and Delivery , Excise calculation , everything has over.
    now, i want to return 2 Items to Supplying plant. can u tell me how i can do it.

    Hi There
    Reversal of partial is not possible ,
    But you can use the Mov Type 557 and 558  to do the adjustments in Stock in transit qty
    Few more details on STO adjustments
    Hi There
    it can be settle in many ways,,,
    1. Receive the goods as 100 and Scrap the 5 nos from the received plant,,- If the receiving plant is responsible
    2.Revert the PGI/Transfer movement and send the 95 nos again from the supplying plant- of the Supplying plant is responsible,
    3.Also we have the movement type 557 and 558 without doing the above two steps you can correct the qty from stock in transit itself,,
    4. also you can check the below similar thread
    STO - material lost during tranfer from plant A to plant B
    5. Here is some more details
    557 Issue from stock in transit (adjustment posting)
    Only use this movement type (also the reversal movement type) under the following circumstances:
    Using movement type 557, you can correct purchase-order-independent stock in transit if
    - a good receipt cannot be posted to a purchase order without stock in transit, even though there is still stock in transit according to the purchase order history
    - stock in transit still exists, even though there are no open stock transfer orders for the particular material
    This movement type may ONLY be used in the cases mentioned above after careful analysis, to correct stock in transit that has rounding errors.
    This movement type may not be copied.
    Note!
    Before using this movement type, note the following:
    - 392205 Analysis stock in transit / Correction if split valuation
    Possible special stock indicators:
    E, Q
    You can use any one of the way to solve the issue, Hope it helps
    Cheers
    Senthil P

  • Partial qty MIRO and GR for import PO

    Hi,
      For import PO first we are creating PO for vendor and we enter only qty and 0%  tax for import PO  after getting material as per schedule qty we are creating new PO for the recieved qty only and we are adding all the custom condition as delivery cost in second PO then we process further like MIRO  and GR ,  but to avoid this we are trying to make only one PO on import vendor and adding all the custom codnition in that PO in development server and we process the MIRO, J1IEX, and GR process for partial qty for one material and for one material we have taken ful qty. first time it works OK  ,  now when second time we want to do MIRO , J1IEX and GR againt same PO we are facing probelm like In MIRO when we enter PO number it is showing some amount in Balance amount filed which is generally 0 ,  in MIRO it is also showing the some material for which no open qty and also for partial qty if we enter qty more than open po qty system is not giveing any error,
    Can you some stpes and tips  what configurationwe need,  actual requirement is we want that we will create import PO o etime by adding all the custom condition as delivery cost and ref. to that material we want to do MIRO, J1IEX and GR  for partial qty.
    regards,
      zafar

    Hi,
      I have two points,
    While after  recieving import material first we do the miro for custom condition in this we enter the custom vendor code in the invoicing party, and below next to PO number field we generally select option no. 3 i.e Goods / service item + planned delivery cost with this all conditions come in the miro but our requirement is only those codnition should come in which invocing party is which we have enter in the header fied of MIRO ,
      so insted of 3 option Goods / service item + planned delivery cost ,  if we select option 2 Planned delivery cost our problem get solve so i want to know what is the effect if insted of 3 option we select option 2.
    regards,
      zafar

  • STO - Partial Reversal of Goods

    Hello,
    I would like to know how to reverse the goods movement for a STO Delivery Partially. What is the movement type that i use for it.
    step 1: Create a STO.
    Step 2: Create a Outbound Delivery and do a PGI. Say 100 Units.
    Step 3: Did a GR at the receiving plant for 98 Units. 2 Units lost in transit.
    But supply plant says that they sent 100 units.
    How would i control this situation. If i will have to reverse the Goods partially by reducing it by 2 units. How can i do that.
    Thanks

    There is no way where you can reverse partial quantity against a stock transport order delivery.
    You have 2 options in this scenario
    1st option:
    1) You need to post GR for the full quantity as per the GI quantity. (this will make the document complete.
    2) Create a stock transport order back to the supplying Plant for the lost quantity.
    3) Suppply Plant needs to post GR for the lost quantity.
    4) Post a write off (scrap) document in the supplying Plant.
    2nd option:
    1) You need to post GR for the full quantity as per the GI quantity. (this will make the document complete
    2) Post a write off (scrap) document in the receiving  Plant.
    Thanks
    Sanjay

  • Partial reversal of Intra company STO

    Hi Gurus,
                 How to reverse partial quantity in the intracompany STO with delivery.
                    After make GR  we reverse the partial qty  by using mvt type 122. Then the stock will be SIT of the receving plant. How to reverse that qty in to supplying plant's stock. If we use the VF09 it reverse the whole qty.
    Pls clarify.

    Hi,
    the system behaviour is correct. With 122 you are only sending the material back from your receiving plant but the stock has not reached or been received in the supplying plant. Unlike 351, movement type 122 is not meant for stock transfer. If you see the material document you will only see one line, unlike 351 which will have a - from supplying plant & a + to the receiving plant,which is the reason why the stock goes into SIT of the receiving plant in the 1st instance.
    BR

Maybe you are looking for

  • Flash CS6 Text Disappearing

    I have been using Flash CS6 running on a Windows 7 work laptop since January. Not a single problem until last week. Say I have a text box inside a banner symbol. The text says "WELCOME".  Normally you click the symbol to edit in place, click the text

  • Elements v PS7

    This might be the wrong forum but no doubt there's someone who uses Elements and Photoshop 7. I have just "upgraded" to PS7 and not sure this was worth the expense. I do a similar project in Elements 3 regularly and tried the same project in PS7 and

  • WRTS4G, computers not detecting wireless router

    On my main desktop I can connect to the internet (obviously), but when I try to detect the wireless router it doesn't detect it and my laptop won't connect either.  Up until yesterday I've been connected with no problems at all. I've reset the system

  • Makes a hash converting to .doc or .rtf

    what's the point in exporting to .doc or .rtf if there is no fidelity to buzzword original?

  • Create a new instance on Test server running apps 11.5.10

    Hi, How do I go about creating a second instance on the same server? I would like to have a test development instance which ideally should be a mirror of the test instance on the same server. OS : HP UX 11 database: Oracle 9.2.0.5 apps: E-business su