Periodic material requirment in project

Hello Guru's,
I need your help in my project requirment :- We are working for construction project were we have an activity for concrete work.
now total work involved in this activity is 120m3 and the duration is 12 months. So period wise 10m3 work i am going to execute.
To execut this 10m3 of work I need 5kg of cement per month.
So total material required to execute the 120m3 of work in 60kg.
Now my requirment is when I create activity in proj for concrete work, i attach cement as material to this activity and generate the reservation. Against this reservation through MRP material is procured and issused to proj. (this is the process)
While attaching material I need to specify 60kg but system should generate 10kg of reservation every month is this possible???
if so how or suggest me to map this process.
Thanks in advance,
Tushar

Hi,
  If I need to cretate  periodic requirements for a material which is converted into a PR then do I need to assign the material perio-wise?
  what i was thinking if there is any means of triggering a PR for the overall quantity and then splitting the quantity period-wise in the PR.My MM person says no functionality of this kind is available.
  Would the best way-out be to create a manual PR and put the periodic requirements line-item wise?
  Thanks and Regards

Similar Messages

  • Material requirment from Projects

    Hi,
    I have one scenario where the material requirments will come from projects as materials (BOM) are assigned to project builder. After MRP run if there is material components available in free stock, it is n't getting adjusted against material requirments, rather creating new PR for the items. Request you to suggest on this.
    Thanks & Regards,
    Ranjan

    Dear Biplap,
    Any material required for a project and is assigned to a project is generally a special stock, "Q' type.  Basically SAP handles material required for project seperately, Sale order separtely, consignment seperately, vendor seperatly etc. 
    So when u run MRP for the first time related to that project, generally no material will be avl <b>under that project segment</b> and create Planned order / PR as the case may be eventhough there is unrestricted normal stock for that material. SAP MRP will only consider the materials or docs for netting only if it is related to that particular project/sale order.
    If you want to consider the unrestricted stock also then possibly u will have to write a Z program which will convert the normal unrestricted stock into project stock and again rerun MRP on that material to cancell the requirement generated thro the initial MRP run.
    reg
    Kiki
    Award points if this helps

  • Material requirement grouping Project delivery

    Hello,
    We have a scenario wherin Delivery through projects needs to be done for material with MRP grouping. The material is grouped at top level WBS. Once the material comes in stock through procurement cycle at top level WBS the same is transferred to lower level WBS . The problem is that at the time of Delivery from project for MRP grouped material, 'Availability check' does not work and Qty appears blank at the time of delivery. Once MRP group is removed, the qty appears in delivery.

    Hi,
    please read FAQ note 677169 section 3:
    b) Why is availability check not executed in CNS0 ?
       Answer:
       Please check whether availability check is switched off by
       delivery item category (0VLK; indicator 'AvailCkOff').
    c) Why does availability check in CNS0 return different quantitites
       than availability check in network ?
       Answer:
       Availability check is controlled by checking rule and checking
       group. In CNS0 checking rule is hard coded to 'B ' for plant
       stock and 'BE' for individual stock. In network checking rule is
       defined by order control (plant/order type/business func.) and
       might therefore differ from the hard coded checking rule used by
       CNS0.
       Please be aware that also in SD ATP checking rule for delivery is
       hard coded with same values.
       Please check ATP result with transaction CO09.
    Kind regards
    Peter

  • Material procurement as Project stock

    Hi,
    I have assigned a Non Stock Material (N) to WBS activity ---> converted the PR (created for network) to PO --> now i want to do GR for this PO and update the material recieved as Project stock on the correspondign WBS.
    I am using movement type 501Q when doing GR, and i expect that the corresponding WBS should automatically be populated or i should be able to add the WBS manually? but WBS field in MIGO screen when doing GR is greyed out?
    Any pointers to address this will be helpful?
    Thank you.
    Regards,
    Jatinder

    Hi,
    >>>>>>
    But now for one project i dont want to take material from store, but want the material to be supplied by supplier directly at project site, also i dont want to show the material supplied as directly consumed but want to show it first as WBS stock and then do GI to show consumption? how can we achieve this??
    <<<<<<<
    If you are intended to ship directly to site, then change procurement scenario as Drop shipment. In that case material never see the warehouse, what I mean no GR. Hope this make sense.
    for other requirement, discuss with your WM guys who should have fictious GR for that material. In that case you have to use material account assignment as Q (project stock). the only thing is you are not physically bringing material into warehouse but still you have GR for that material.
    Why you want to follow suck kind of routing, directly use drop ship procurement scenario which makes your life easier without any risk. By doing this you encouraging some kind of malpractices in system where users may misuse.
    Any have its your call and take decision accordingly.
    Regards,
    PSR

  • In general what is the time period of the XI projects ?

    Hi All
        Can any one help me what is the time period of the XI Projects (In general)?
        In realtime how the time is managed/Utilized on resources ?
        How the work estimations will be done ? Based on What ?
    Adv...thanks and points
    regards
    ---  Rakesh

    Hi
          This is based on the projects but in general (In addition to above)
          As follows
         In general there are ‘3’ kinds of interfaces
    1)     Easy  ---  2 days (Which will include dev+ document)
         2)  Medium -
    5 days          “           “
    3)     Complex  -
    10 to 12 days  (complex BPMs + Mappings+ document)
          Project full time will purely depends on the  Business (Requirement)
         + No.systems+ No.scenarios
          But in general 4months to 6 months for normal projects
    >> About work already answer given
    I hope this will solve your question
    regards
    -- prasad

  • Changes in material transferred to project structure.

    Hello,
    It is required to track the changes made in material transferred to project structure alongwith User Name. (eg: Deletion of magterial, Incerease/decrease in qty etc)
    In assignments, we can only see the Username of the person who has  made the last change.
    Kindly help.

    Hi Nidhi,
    Please refer to SAP note : 1127691.
    In this note Point 5  CNEX0026 -- EXIT_SAPLCOMK_005 will help you.
    This user exit is used to check if there are any changes done to the material component in the component overview screen or the details screen of the material component.
    Regards,

  • Datasource 2LIS_03_S194 (Material Requirement Planning)

    Hello SDN:
    I need to extract data from the datasource 2LIS_03_S194 (Material Requirement Planning) relevant to me. I know this datasource is LIS and to fill it, I need to run a program RMCBMRP2 to fill set up tables, and this doesnot support Delta update.
    I have one doubt, that for future MRP data Loads will I have to execute this Program every time and do full loads..? OR can I schedule a job to do.? If so, how to schedule a job.?
    Please share your experiences with me.
    Thanks in advance,
    Regards,
    Kalyana Pidugu

    Hi Kalyana- I am also using this same datasource and not sure when to run the program RMCBMRP2 in ECC and what parameters (regarding period/dates) to provide in SE38 while running it. If you have found more info on this can you share with me please?
    Thanks
    Naresh

  • Grouping material requirements of Bottom level WBS

    We are stucked on material requirement planning
    We are assigning the various BOM to level 3 WBS and taking MRP on it  thru MD51.
    The final product which includes all BOMs at bottom level is assigned to level 2 WBS.But while running MRP on level 2 WBS system regenerates the requirements which already part of bottom level BOM. I want to avoid it.
    How shuld I achieve this ?
    Rgds

    Hi Shrikrishna,
                                Strictly speaking the way MD51 is creating demand is correct, its working right. Now coming to your scenario, lets take an example which can assist understand your scenario.
    Step 1:
    I create following materials 
    1 FERT material
    1 HALB material
    1 RAW material
    Step 2:
    I create BOM     HALB --> RAW
                            FERT --> HALB
    Step 3:
    Create routing and assign work centre and activities
    Step 4:
                FERT is your final material.
    Step 5:
                Lets create a project "Projectest" with following structure or requirements
    Project test
    > WBS1  <Set the grouping indicator in WBS basic tab to one 1 Grouping WBS element for all materials>
                      --> IWBS < Individual WBS >
                             -->  Network
                                  --> Cost element
                                       --> FERT < Your final assembly >
                                               5 EA
    Step 6:
                   Run MD51 on Project with 1,3,3,1
                                   You will get replenishments created as below
                                         RAW --> 1 PR --> for procurement of 5 EA
                                         HALB --> 1 PO --> for production of 5 EA
                                         FERT  --> 1 PO --> for Production of 5 EA
    Only one PR,PO's are created since we have set the grouping indicator in Level one WBS there by reduce the number of repleninshment elements created.
    Step 7:
                  Get the RAW into stock (GR 101 Q --> Mvt type)
    Step 8:
                 Create the Production order with ref to Planned order for HALB
                 Issue the stock of RAW to HALB( 261 Q)
                 Confirm the production order
    Step 9:
                 Create the Production order with ref to Planned order for FERT
                 Issue the stock of HALB to FERT (261 Q)
                 Confirm the production order
    By this you will complete the entire cycle.
    In you scenario there is lot of duplications that can be avoided if you try implementing this scenario.
    I hope this example will help fix your issue.
    <<Rewad Poins if Usefull>>
    Thanks and Kind Regards
    Mohan
    Edited by: Mohan Kumar K on Sep 16, 2008 9:03 AM

  • Creating a planned order with error "Material requires configuration"

    Dear All,
    I am facing a problem for creation of a planned order with error "Material requires configuration".
    To follow the note 180317, I change Account Assignment Category to "U" (Unknown).
    However, the system still does display the same error.
    Could you please help provide possible solution for this?
    Regards,
    Phong

    See also the following blog post:
    Configurable planned order for material variants: Exception "53: No BOM explosion due to missing configuration"
    BR
    Caetano

  • Creation Indicator in PR: B Material Requirement planning

    Hi All,
    I am facing an unusal scenario.
    User is claming that PR is getting generated for a material after running the MRP, even there is enough stock.
    I checked material &  I found that MRP type is ND, there is no entry in the planning file for this material.MRP list & stock requirement list of this material is showing nothing. So there is no way that PR will be created automatically via MRP run for this material.
    When I checked one PR for this material, Plant & storage location, creation indicator is showing as B Material Requirement planning.
    Could you please help me that why creation indicator is showing as B>
    I further checked these PRs are created long back when MRP type was V1. Later they changed it to ND.
    How to delete MRP generated PR manually when PO has been created for these PR.
    Regards
    Shilpi
    Edited by: sapmm1234 on Dec 14, 2011 6:10 PM

    As you said; the PR was created long ago by MRP, when it was not ND.
    If it was already converted into a PO, there's no need to delete it, right? If not, just delete it manually.
    In the future, when you change MRP type from a valid type to ND, always remember to do 2 additional things, as the system will not do them automatically:
    1- delete the MRP list
    2- delete any planning elements if they exist, like planned orders and MRP generated PRs.

  • Cost of material charged to project but qty remains in stock

    Dear Gurus,
    I have a scenario, we have project systems PS. We have valuated projects and valuated project stock. Once project is over and if we have material left over, then my client want to charge the cost of the material to the project but he want to keep the stock at zero value in inventory, and issues it next time on zero value.
    I have tried to transfer material using 415 Q, but system does not allow to transfer materaial from valuated project to non-valuated project.
    kindly suggest any solution.

    Dear,
    my client wants to charge the leftover material cost to project but want to keep the qty in stock, so this is why we have a nonvalauted project. otherwise my client projects are valuated. i have not find any solution to charge the cost of material to project from project stock and keep the stock in inventory on zero value. and next time when this leftover is issued it will be issued on zero value.
    hope u have a solution.
    Edited by: Johi Kapoor on Nov 10, 2011 11:57 AM

  • Audit Log is required for Project server

    Hi,
    Audit Log is required for EPM / Project Server 2010 
    Following are the requirements.
    Project Name, Resource Name and Date of Following Events.
    1. Project checked Out By, Date (This is highly important)
    2. Project Checked In By, Date
    3. Project Published By, Date
    4. Project Saved By, Date

    Hi Hachishti,
    Please refer to a recent similar thread with excellent answer from Paul.
    http://social.technet.microsoft.com/Forums/projectserver/en-US/435fbb7a-1c82-419c-b83e-e89419dc66aa/project-server-2010-view-plan-save-history?forum=projectserver2010general
    Hope this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Transfer material from Valuated project non valuated project

    Hi Experts,
    While i am trying to transfer material from Valuated project stock to Non valuated project with T.Code MB1B movement type 415 'Q', I am getting following error.
    WBS element  has different inventory valuation
    Message no. CN769
    Diagnosis
    The project definition for WBS element  only allows the following stock control:
    No project stock
    No project stock with defined valuation M
    ' ' = non-valuated project stock
    'M' = valuated project stock
    System Response
    Account assignment not possible.
    Procedure
    Change the settings for the project stock in the project definition (Control tab) or use a suitable WBS element.
    Kindly suggest me how to trafer material from Non valued project stock to valuated project stock.
    Regards

    Actually, you sohuld not be transferring stock to non-vlauated proejct directly. In case of non-valuated project, stock is never valuated while in case of valuated project it is valuated. So there is basic difference in valuation method. This will create inconistency if you attempt ot transfer it directly.
    You should rather transfer this stock to general stock and then transfer to non-valuated project stock.
    Regards,
    Mahendra

  • Budget is prepared by respective department on basis of material required

    Hello All
    I had a doubts and need help
    If budget is prepared by respective department on basis of material required in the next year. Then how in sap we will able to track in sap.
    Budget can be plan on fund center and commitment item, when client make budget on basis of material and services required then how commitments will be created
    Thanks in advance
    alok

    Hi,
    FM budget objects are indeed fund centres, funds, commitment items, etc. If your client prepares the budget on different level, it has to be mapped to FM objects either inside SAP (via FMDEIRVE startegy) or outside SAP.
    Regards,
    Eli

  • Raw Material Requirement

    Guru
    My Client Wants material requirement plan for finished product
    For Example
    One plate of Size 1000 MM X1000 X 500mm in this sheet He wants the three type finished goods of  X, Y & Z of different
    How to Configure where & is their any cusomation required for this requirement.
    pl advise me for this senior
    Thanks in Advance
    Sudhir

    Dear Sudhir,
    Generally the sheet metals or raw materials which are to be represented in different sized section using one material code will
    be represented as a variable size item R as the itel category while maintaining the BOM for X,Y,Z.
    When creating the BOM of X,Y,Z include this sheet metal with item category as R and quantity as 1 ea or 2 ea as required.
    For this formula's will be maintained.
    Check these links also,
    Variable size Item
    Regards
    Mangalraj.S

Maybe you are looking for

  • One to many mapping

    Having trouble with the following poblem.. specially how to code getChildren??????? Help urgent Create a class called Families which creates a one-to-many mapping of parent name (String) to Child objects. Create any needed member variables and write

  • How to compile and execute lex,yac,c and java programs

    its the 3rd day on my New MacBook pro.. as i just migrated from windows to mac i love to work on this.. The main problem  is i DON't know ....... how to compile and execute 1) lex and yac programs 2) c program 3) java program so please help me THIS i

  • Purchase price different

    Hallow good afternoon all the experts I have made this query and can work in the branch office A, and my copy at the office of the branch B why can not work? His description is No data was found as a result of the selection criteria. if anyone can he

  • Control Flash8 swf movie in Flex 2

    I have a swf (output from OpenOffice, created from a PowerPoint presentation) and i want to control it from Flex 2 (i don't have the .fla file of the swf). Is this possible at all? I can load the swf and display it, but no way of accessing it as a Mo

  • My S4 is unable to connect to the cellular network after the 4.4.2 update failed to install this afternoon.

    I attempted to install the OTA update for 4.4.2, but received an error message that the installation failed. When my phone rebooted it was unable to connect to the cell network and was extremely sluggish. I own an iMac and the S4 is no longer recogni