Person assignment  for activity

Hi All,
I'm looking for  a function  to get the person assignment and update the data.
We are using ECC 6.0 EH4, Does anyone have any idea which function  does  this functionality ?
Please advise,
Amit Yosha

Hi Amit ,
There is a consulting note 543362, which clarifies your questions.
Essentially there are following points:
1. the work center need to linked with HR.
2. Enter the work center for the activity.
3. Maintain the work of the activity and run the scheduling, so that the capacity is determined.
Now you see additional tab 'person assignment' of the activity.
kind regards,
Zhenbo

Similar Messages

  • Create Person & Assign to Activity - CATS

    Hi Experts,
    I need to create persons and assign it to the internal activities in person assignment tab and use for CATS.
    We are not implementing HR module. Please suggest and advise.
    Thanks & Regards,
    Kabir

    Hi Kabir,
    1. You can create person through Mini-HR. T.COde is PA30. you have maintain following ifotypes 0,1,2,6,7,105 & 315. No need of HR module
    2. Create activity type in CO & maintain rate in KP26
    3. Create workcenter and assign person & activity type in it.
    4. Attach this workcenter in Internal activity
    5. Do the workforce planning in CMP2
    6. Book the time in timesheet using CAT2
    7. Transfer the time to PS using T.code CAT5
    Hope, this will help you.
    Regards
    Prabu

  • Msa: contact person selection for activity

    Hello forum,
    I've installed msa50 sp6 and now I want to now, when I creat an activity and select
    a contact person to this activity by search window, is it possible to select more than only one person  (multiselect) or must I for every contact person open the search window and select  the contact person again ?
    Can somebody check this behaviour ?
    Thanks
    Gerd

    Dear,
    Multiple selection is not possible in MSA.
    You can select one contact person at a time
    If you have any concerns please revert back the same
    Amjad

  • PS Modifiy person assignment in activity or subactivity

    Hello,
    I'm searching for a FM ou a table to modifiy person assignments on a PS su-activity. I want to modify the duration on the assignment.
    I found bapi and FM to modify project, network or activity but nothing concerning assignment. Also tried to modify table KEBZ but this is dirty and this does not seem to have effect on the date people are allowed to fill their times.
    Can anyone help me ?
    Thanks,
    Sylvain

    Check the consulting note 543362
    This note explains the steps/configuration node that needs to be in place for workforce planning
    Regards
    Sreenivas

  • Person assignment with workforce planning

    Dear All,
    I plan activity for one day 8 hours & assigned person to activity in CMP2 & distribute work for same day & for same hours,
    when i assign same person with diffrent activity with diffrent project with in CMP2 system not showing any message with same person is assigned same day with diffrent project.
    How same person can work two project with same time,
    Kindly share yours experiance.
    Regards
    Gajjen

    Hi,
    I tested with without person assignment in work center, yes you can assign any person to any project if have capacity but when we distribute work in workforce planning by assignment of person with day & time then same person how can assign to other activity ,because his working hours are fixed,if working time is 8.5 hours & person assign for 8 HR to activity then same person should not work to another activity more than 0.5 hrs,system should not allow.
    May i know Standard SAP allow it or not?
    Regards
    Gajjen

  • Email notification for the Activity Person Assigned

    Hi,
    I have a query from my client. They want to know the possibility of sending an email notification to the Person Assigned to an activity. Once the activity is REL, system should be able to send email (Outlook email or SAP mail) having the task details to the Person Assigned to that activity.
    Any suggestions/inputs are welcome.
    Best Regards,
    Mohammed

    Hi,
    You have to go for a ABAP development that trigger uppon activity REL.
    Thanks & regards,
    SL

  • PS Workforce planning, Person Assignment in internal activity.

    Hello PS colleagues!
    I’m trying to use the workforce planning functions but I can not get the screen for person assignment in the internal activity.
    I have done this, IMG I go to this path:
    Project System -> Structures -> Operative Structures -> Network -> User Interface Settings -> Layout of Activity Detail Screens -> Define layout activity detail screens
    Then I create all tab, I copy the standard to my network profile and there is tab 8, in standard is call ”Admin.” then when I try it out it do not appear in the project, I use project builder.
    Does any one what more I need to do for this to work??
    Please help me out with this.
    Best Regards
    Jose Marin

    Check the consulting note 543362
    This note explains the steps/configuration node that needs to be in place for workforce planning
    Regards
    Sreenivas

  • T.codes to view the list of persons that are assigned to "activity"

    Hi Guru's
    Are there any transaction codes to view the list of persons that are assigned to u201Cactivity - personal assignment tabu201D in the project?
    Regards,
    Bha

    the same you can view from CJ20n , by clicking perticular activity--> click on person assignment tab.
    This can be true for all the netwrok maintenance txn.
    Regards
    Nitin

  • Project- Builder: Person Assignement tab for Activties

    Hi All,
    Pls help on the following:
    1.In the 'Internal' tab for activities, there is a field 'Number' where we can specify the number of capacities required. But there is no validation against this when I actually assign resources to the activity in the 'Person Assignement tab.
    i.e I can assign 5 people for this activity even though I mentioned Number as 1 in the internal tab.
    Is there a way to enforce a validation here?
    2. Resource allocation has two different behaviour when I do through Person Assignment tab and 'WorkForce Planning' screen. Is there any specific reason for this?
    3. If i want to replace the WBS actual dates by the actual dates of activity, I need to go to Edit>Reconcile Dates>Determine Actual Dates in the Project Planning Board. Can I automate this while saving the project?. I checked the user-exits and BADI - PROJECTDEF_UPDATE. But found out that the date fields cannot be updated using these. IS there some other way?
    4. In the Workforce planning: Project View, Can I split the work in the duration based on my working hours from HR? Now I have to manualy do the split.
    Appreciate your response on any of the above doubts.
    Regards,
    Remya.

    Hi remya,
    My reply is limited to point No.3 of your posting.
    SAP's logical construct is such that WBS is more than the sum of activities assigned to it. That is why, system doesn't allow automatic updation of WBS actual dates based on confirmation of all activities assigned to it. Please remeber that the given WBS could have subordinate WBS elements with different statuses  apart from the activities assigned.
    Basic rule is as below:
    You can maintain actual finish date for a WBS only if all the subordinate WBS elements have actual finish dates and all activities assigned to the WBS have status "Confirmed".
    However, when activities are confirmed "Tentative actual finish date" is updated at WBS level which can be subsequently copies as actual dates manually.
    From the above, I hope, it is clear why defaulting of actual finish dates for WBS is not permitted.
    For the remaining issues in your posting I need more time.
    If this clarifies the issue, please acknowledge the same.
    Muraleedharan.R
    091 9880028904

  • Splits (Person Assignment) in Network Activity

    Hello Experts,
    I have planned 10 hrs work in a network activity. After that , In the person assignment tab of Network Activity, I have assigned a person and gave work as 15 hrs.
    When I press enter, I got an information message " The work of all the splits is greater than the work in the operation"
    How can I make this information message as error message? I could not find in the configuration.
    Any thoughts would be appreciated.
    Regards
    Srinivasan Desingh

    Hi Srini,
    Any message if you want to change that from warning or error and vice versa......you have to change  the message category in the customozation of " Define system  message attributes".
    SAP provides these kind of customization for puchasing, process order, inventory and some other function modules.... Unfortunately PS module doesnot have this option.
    But it is possible to do so....with the help of ABAP consultant.
    Here are some of the inputs....
    Goto SE80...ABAP workbench
    Call for Repository browser
    and then enter package and CY and drill down box which is appear in the left side of your screen.
    You can see your message 411 at the right hand part...
    With the help of ABAPer...it is possible to do so...
    Hope it will helpful for some extent.
    Regards
    Vetri

  • Question to assigning Source System for Activation

    We want to assign source system for activation, before business content-InfoObject catalog activation. The steps as follows:
    1.On the Data Warehousing Workbench: Business Content view from the menu choose Edit  Source System Assignment.->This step is ok, no question.
    2. In the Choose source system by default? dialog box select the checkbox in the column Default assignment in the row containing the source systems you need to load data from.->Now we can see BI system as default call DEGCLNT500 displayed, in my case we only connect one R/3 system call DHHCLNT100 to BI system.
    So, the question to that is shoud we select both R/3 source system and BW source system as default or just select R/3 source system as default and dis-select BW source system?
    Which one should we choose, both or only R/3 source system?
    Pls help, thanks!

    Hi hi ni,
    If what you are activating it's going to retrieve data only from R/3, then select R/3 and uncheck BW.
    You can change this whenever you want, if in the future you need bw, before activating, you can change it.
    This doesn't means where is going to get the data from, this is just to look for active (and replicated) datasources to connect to the business content you are activating.
    Hope this helps.
    Regards,
    Diego

  • BAPI to upload Person Assignment data under network activity

    Hello All!
    Can anybody tell me the appropriate BAPI that can upload the data of Person Assignment tab under network activity of Project System(TCode:cj20n)? I.E. data like Split Person Date Time Work Un and others data.
    Thanks in advance.
    Regards.
    Sarbajit

    Hi Majumdar,
    you can find it by running transaction ST05 against CJ20N.
    try bapi-
    BAPI_PROJECT_MAINTAIN
    Regards,
    NaPPy

  • Insufficient privilege when Activating an attribute view (person responsible for package = SYSTEM)

    Insufficient privilege when Activating an attribute view (person responsible for package = SYSTEM)
    SAP HANA Studio
    Version: 1.0.33
    Build id: 201206301604 (363996)
    Playing with the efashion tutorial with HANA Studio.
    I am SYSTEM user by default when starting the studio.
    -Schema created
    -DDL created
    -Data loaded
    -Attribute views created
    Below an extract of the error log:
    <info>Create Attribute View failed: SQL: transaction rolled back by an internal error: insufficient privilege: Not authorized

    Hello Anooj and Sri,
    Thank you for your answers, I really appreciate your inputs.
    So I executed this:
    "GRANT SELECT ON SCHEMA SYSTEM TO _SYS_REPO WITH GRANT OPTION;"
    Under the Studio SQL GUI and I still have the same error when activating my very simple attribute view.
    I have installed a recent HANA + Studio + Client release on my laptop:
      SAP HANA Studio
    Version: 1.0.33
    Build id: 201207050531 (364183)
    And yes, this is a demo and yes I am logged as the SYSTEM user (default user when stating the studio). For now, I dont know how to connect to another user with the studio and I will search the doumentation.
    Below a copy/past of the error msg.
    Internal deployment of object failed;Repository: Encountered an error in repository runtime extension;Internal Error:Deploy Attribute View: SQL: transaction rolled back by an internal error: insufficient privilege: Not authorized (ptime/query/plan_executor/ddl/qx_cube.cc:1514) n
    Create view DDL statement: CREATE COLUMN VIEW "_SYS_BIC"."efashion/ATV_OUTLET_LOOKUP" TYPE JOIN WITH PARAMETERS ( joinIndex = "EFASHION_TUTORIAL"."OUTLET_LOOKUP", joinIndexType = 0, viewAttribute = ('SHOP_ID', "EFASHION_TUTORIAL"."OUTLET_LOOKUP", "SHOP_ID", '', 'default', 'attribute', '', 'efashion/ATV_OUTLET_LOOKUP$SHOP_ID'), viewAttribute = ('SHOP_NAME', "EFASHION_TUTORIAL"."OUTLET_LOOKUP", "SHOP_NAME", '', 'default', 'attribute', '', 'efashion/ATV_OUTLET_LOOKUP$SHOP_NAME'), viewAttribute = ('MANAGER', "EFASHION_TUTORIAL"."OUTLET_LOOKUP", "MANAGER", '', 'default', 'attribute', '', 'efashion/ATV_OUTLET_LOOKUP$MANAGER'), viewAttribute = ('ZIP_CODE', "EFASHION_TUTORIAL"."OUTLET_LOOKUP", "ZIP_CODE", '', 'default', 'attribute', '', 'efashion/ATV_OUTLET_LOOKUP$ZIP_CODE'), viewAttribute = ('CITY', "EFASHION_TUTORIAL"."OUTLET_LOOKUP", "CITY", '', 'default', 'attribute', '', 'efashion/ATV_OUTLET_LOOKUP$CITY'), view = ('V_OUTLET_LOOKUP', "EFASHION_TUTORIAL"."OUTLET_LOOKUP"), defaultView = 'V_OUTLET_LOOKUP', 'REGISTERVIEWFORAPCHECK' = '1' )nVersion: 48n
    Thank you.
    Patrick

  • Person Assignment tab in network activity

    The person assignment tab in internal network acitvity has a daily view. Shows dates for only 1 day at a time
    Can anyone please tell me how to change this view from daily to weekly?

    Hi,
    Pl elaborate , we do not understand the requirement.
    regds,
    Deependra

  • I'm using 3G3 16gb and just upgraded to 4.3.3. Tried activating bluetooth to use Personal Hotspot for my laptop. But the iphone keep searching for devices thou my laptop can detect the phone. Does anyone know how to solve this?

    I'm using 3G3 16gb and just upgraded to 4.3.3. Tried activating bluetooth to use Personal Hotspot for my laptop. But the iphone keep searching for devices thou my laptop can detect the phone. Does anyone know how to solve this?

    Hi NWL1,
    Thanks for the question. If I understand correctly, the iPhone won't update and is stuck. I would recommend that you read this article, it may be able to help you resolve or isolate the issue.
    If you can't update or restore your iPhone, iPad, or iPod touch - Apple Support
    Thanks for using Apple Support Communities.
    Have a great day,
    Mario

Maybe you are looking for

  • Using a tablet PC pen to annotate PDF slides in full screen mode

    I'm using Acrobat 8 Standard on a tablet PC with Win XP Professional SP 3 running. I m using Acrobat to run LaTeX presentations, and am looking for a way to use my tablet PC pen to annotate (underline, circle, etc.) slides in full/screen mode, as is

  • How to insert data into two different lists in sharepoint 2010

    I have a page containing a dropdown list having two departments like IT, HR. If i select HR, one input form will display for filling HR related info, these i need to store in HR list. In the same way for other dept through custom coding. someone help

  • Is it possible to create an internal table with FOX?

    Hi, I have a requirement where I need to call a function module from FOX formula (standard functionality). It would help me if I could pass data to the FM in an internal table. Unfortunately I am not sure if this is somehow possible in FOX. I could c

  • Why is the soundtrack broken in slideshows?

    Hello everyone, I'm burning a PAL DVD with iDVD which contains a movie and two slideshows, which I've done many times before without a problem. Now though, the sound is broken, generally when the picture changes in the slideshows. It just drops out.

  • Partial restore from Cold backup

    Hi, I want to create a copy of our dev database to another server. We have Oracle 10.2.0.4 server running on Solaris 10 OS. This database is @ 120GB in size and has got lots of application data. Now I want to create a copy of this DB without having t