Person assignment tab

Hi,
Iu2019m not able to get person assignment tab for the activity in cj20n.
I have maintained work and workcenter for each activity.
Can any one help me on this, I have checked note 543362 and have maintained the same.
But i dont know what is missing.
Thanks,
Chandru

Hi Chandru
Actually the note 543362 (written by me)  should give you all the information. Anyway double check the following again.
1. Is the flag 'capacity requirement' of network  set?
2. Is the scheduling for network done?
3. Is the work for activity maintained?
4. Which work center is maintained for involved activtiy. Call CR03 for this work center.
  4.1. In work center, in the capacity  tab. Is the formular for field 'Other formular' maintained. Default is SAP008
  4.2. Click of button 'HR assignment', is the HR resource assigned?
If all the checkitems do not help, you can open a customer message to let SAP have a look.
Kind rgards
Zhenbo

Similar Messages

  • How to change the default date in Person assignment tab?

    Hi experts,
    Does anyone know how to change the default date in person assignment tab in cj20n? Currently, the system always take the scheduled finish date to the date of the person assignment tab. Can I change it to the start date?
    Thanks and rgs,
    Michelle

    Hi Michelle,
    Goto SPRO->Project system->Dates->Scheduling->Specify Parameters for Network Scheduling, Here you can control the workforce planning dates.
    Hope this is useful...
    Regards
    Aatish

  • Person Assignment tab in network activity

    The person assignment tab in internal network acitvity has a daily view. Shows dates for only 1 day at a time
    Can anyone please tell me how to change this view from daily to weekly?

    Hi,
    Pl elaborate , we do not understand the requirement.
    regds,
    Deependra

  • Project- Builder: Person Assignement tab for Activties

    Hi All,
    Pls help on the following:
    1.In the 'Internal' tab for activities, there is a field 'Number' where we can specify the number of capacities required. But there is no validation against this when I actually assign resources to the activity in the 'Person Assignement tab.
    i.e I can assign 5 people for this activity even though I mentioned Number as 1 in the internal tab.
    Is there a way to enforce a validation here?
    2. Resource allocation has two different behaviour when I do through Person Assignment tab and 'WorkForce Planning' screen. Is there any specific reason for this?
    3. If i want to replace the WBS actual dates by the actual dates of activity, I need to go to Edit>Reconcile Dates>Determine Actual Dates in the Project Planning Board. Can I automate this while saving the project?. I checked the user-exits and BADI - PROJECTDEF_UPDATE. But found out that the date fields cannot be updated using these. IS there some other way?
    4. In the Workforce planning: Project View, Can I split the work in the duration based on my working hours from HR? Now I have to manualy do the split.
    Appreciate your response on any of the above doubts.
    Regards,
    Remya.

    Hi remya,
    My reply is limited to point No.3 of your posting.
    SAP's logical construct is such that WBS is more than the sum of activities assigned to it. That is why, system doesn't allow automatic updation of WBS actual dates based on confirmation of all activities assigned to it. Please remeber that the given WBS could have subordinate WBS elements with different statuses  apart from the activities assigned.
    Basic rule is as below:
    You can maintain actual finish date for a WBS only if all the subordinate WBS elements have actual finish dates and all activities assigned to the WBS have status "Confirmed".
    However, when activities are confirmed "Tentative actual finish date" is updated at WBS level which can be subsequently copies as actual dates manually.
    From the above, I hope, it is clear why defaulting of actual finish dates for WBS is not permitted.
    For the remaining issues in your posting I need more time.
    If this clarifies the issue, please acknowledge the same.
    Muraleedharan.R
    091 9880028904

  • CJ20N -  person assignment tab data

    hi,
    We need to retrive data from CJ20N -  Person assignment tab details. Please help, from which tables we can get those details...
    Thanks,

    hI,
    In fact I want to get first person name which assignmened, in CJ20N -  "Person Assignment" tab of WBS->network activity
    here is the below table is showing in CJ20N, we have to retrive "Atkinson" name ...please help
                                                                                    Spl    Person      D Date       Time  Work      Un. Duratn  Un. Reqmts      Un.
       1      Atkinson      04.08.2009 00:00     160.0 HR     80.0 DAY     160.00  HR 
       2                         04.08.2009 00:00     261.0 HR     32.6         261.00     
       3                         04.08.2009 00:00                                 0.00     
       4                        04.08.2009 00:00                                 0.00     
       5                        04.08.2009 00:00                                 0.00

  • BAPI to upload Person Assignment data under network activity

    Hello All!
    Can anybody tell me the appropriate BAPI that can upload the data of Person Assignment tab under network activity of Project System(TCode:cj20n)? I.E. data like Split Person Date Time Work Un and others data.
    Thanks in advance.
    Regards.
    Sarbajit

    Hi Majumdar,
    you can find it by running transaction ST05 against CJ20N.
    try bapi-
    BAPI_PROJECT_MAINTAIN
    Regards,
    NaPPy

  • Person assigned to a work center

    Hi,
    We are using work force planning to assign resources to activities. We have some problem with one of the work centres. When we click on the person dropdown box in the personal assignment tab then we would expect to see the individuals that are in the work centre associated with the activity. We can see six persons from project builder and when we checked work center master data we could see only four persons.
    When checked thoroughly, the data at work centre master data is picked from HRP1001 and its showing only 4 persons. At the project level, the data is picked from the same table but initially fetches with work centre as input and then capacity ID as input. Finally it combines the data (6 Persons) and show from CJ20n and its different from the work centre data.
    is this the standard behavior or we missing something
    Regards,
    Laxminarsimha

    I think you have assigned two person at capacity category level for that WC.
    Open your WC  in CJR3 --> Click on capacity header icon -->on new screen click on HRMS link button  ( check no of person assigned here  it should be two )
    With Regards
    Nitin P.

  • Create Person & Assign to Activity - CATS

    Hi Experts,
    I need to create persons and assign it to the internal activities in person assignment tab and use for CATS.
    We are not implementing HR module. Please suggest and advise.
    Thanks & Regards,
    Kabir

    Hi Kabir,
    1. You can create person through Mini-HR. T.COde is PA30. you have maintain following ifotypes 0,1,2,6,7,105 & 315. No need of HR module
    2. Create activity type in CO & maintain rate in KP26
    3. Create workcenter and assign person & activity type in it.
    4. Attach this workcenter in Internal activity
    5. Do the workforce planning in CMP2
    6. Book the time in timesheet using CAT2
    7. Transfer the time to PS using T.code CAT5
    Hope, this will help you.
    Regards
    Prabu

  • Person name was greyed out in Person Assignment

    Hello All,
    For internal activitiy, there was "Person Assignment" tab and there is a list of people who got assigned to the activity. However, some people's names just greyed out and we cannot make any changes to them.
    What are possilbe reasons? How to correct?
    Thanks
    JM

    >
    Aittal Alok wrote:
    > Hi,
    >
    > Against those persons who are greyed out, cost posting has already taken place.
    >
    > regards
    > Alok Mittal
    What kind of cost posting?
    Does posting period matter?

  • Splits (Person Assignment) in Network Activity

    Hello Experts,
    I have planned 10 hrs work in a network activity. After that , In the person assignment tab of Network Activity, I have assigned a person and gave work as 15 hrs.
    When I press enter, I got an information message " The work of all the splits is greater than the work in the operation"
    How can I make this information message as error message? I could not find in the configuration.
    Any thoughts would be appreciated.
    Regards
    Srinivasan Desingh

    Hi Srini,
    Any message if you want to change that from warning or error and vice versa......you have to change  the message category in the customozation of " Define system  message attributes".
    SAP provides these kind of customization for puchasing, process order, inventory and some other function modules.... Unfortunately PS module doesnot have this option.
    But it is possible to do so....with the help of ABAP consultant.
    Here are some of the inputs....
    Goto SE80...ABAP workbench
    Call for Repository browser
    and then enter package and CY and drill down box which is appear in the left side of your screen.
    You can see your message 411 at the right hand part...
    With the help of ABAPer...it is possible to do so...
    Hope it will helpful for some extent.
    Regards
    Vetri

  • Color coding in the "Date" and "Time" field in "Person Assignment"

    Hi,
    What does it mean when the color of the values for the "Date" and "Time" fields under the tab "Person Assignment" on an activity element in the project builder (CJ20N) turn red?
    Regards,
    Petter Kvalvik

    Hi,
    I dont suppose we have any option to achieve this at Query Designer level. Your requirement can be achieved in Workbook,
    Insert text template in one of the cell in your workbook, context menu--properties-Constant Tab----Check Display last Refreshed. Doing this you will get Date and Time of last refreshed data.
    Thanks,
    Vishnu.

  • Requirement assignment tab in Maintenance  Work order

    Hi Gurus,
    I have a query ..I want to know the customizing settings for Requiremnt assignment tab in internal operation tab for internal operations in maintenance work order .
    Thanks ,

    Hi sundar ,
    This Path is available in ECC 603 and we are using ECC6 . so not able to get the Path .
    Anyways Thanks for your Help .
    I have one more query  regarding this:
    When I assign one Resource to Reqmnt assignment tab and give any date of  friday then the date is automatically switches to Monday's date . the Work schedule for that person is from Monday to Friday but then also it shifts the date to Monday .
    Can you please suggest on this .
    thanks !!

  • PS Workforce planning, Person Assignment in internal activity.

    Hello PS colleagues!
    I’m trying to use the workforce planning functions but I can not get the screen for person assignment in the internal activity.
    I have done this, IMG I go to this path:
    Project System -> Structures -> Operative Structures -> Network -> User Interface Settings -> Layout of Activity Detail Screens -> Define layout activity detail screens
    Then I create all tab, I copy the standard to my network profile and there is tab 8, in standard is call ”Admin.” then when I try it out it do not appear in the project, I use project builder.
    Does any one what more I need to do for this to work??
    Please help me out with this.
    Best Regards
    Jose Marin

    Check the consulting note 543362
    This note explains the steps/configuration node that needs to be in place for workforce planning
    Regards
    Sreenivas

  • Person assignment  for activity

    Hi All,
    I'm looking for  a function  to get the person assignment and update the data.
    We are using ECC 6.0 EH4, Does anyone have any idea which function  does  this functionality ?
    Please advise,
    Amit Yosha

    Hi Amit ,
    There is a consulting note 543362, which clarifies your questions.
    Essentially there are following points:
    1. the work center need to linked with HR.
    2. Enter the work center for the activity.
    3. Maintain the work of the activity and run the scheduling, so that the capacity is determined.
    Now you see additional tab 'person assignment' of the activity.
    kind regards,
    Zhenbo

  • PO Account Assignment Tab in ECC - with Split Accounting

    Hello,
    We currently are using Funds and WBS Elements within our SAP system.  When both a fund and a WBS Element are used on one line item within the shopping cart, I am able to see all of the information (fund, wbs element, fund center, cost center, commitment item, etc).  However, after the purchase order is created and transmitted to ECC the "Account Assignment Category" is marked as "X - All aux.acct.assgts." and the account assignment tab only has the following column headers:
    - Sequential Number of Account Assignment
    - Quantity
    - Distribution Percentage in Case of Multiple Account Assgt
    - Cost Center
    - G/L Account Number
    - Order Number
    - Asset Subnumber
    - WBS Element
    - Sales and Distribution Document Number
    - Sales Document Number
    - Delivery Schedule Line Number
    - Unloading Point
    - Goods Recipient/Ship-to Party
    - Deletion Indicator: Purchasing Document Account Assignment
    I can see that the fund is within the EKKN table (Field: BP_GEBER) but for some reason ME23N does not have this field in the Account Assignment tab when the category is "X".  How do I add "Fund" into the Account Assignment tab so that it will be visible within ME23N?
    Thanks,
    Katie

    IMG \ MM \ Purchasing \ Account Assignment \ Maintain Account Assignment Categories
    Select details for AAC 'X' and view field settings below.  Set Funds \ Funds Center to required setting e.g. Display.

Maybe you are looking for

  • MIGO error 'Purchase Order does not contain a confirmation control key'

    Hi, while posting GR to a PO i am getting an error ' Purchase order XXXXXXXXX does not contain a confirmation control key' it is true that i have not defined any confirmation control key in PO, Aknowled rerd checkbox is also not ticked Still why this

  • Using new battery on old 2.16 GHz Intel Core Duo

    I am in a remote location, under a deadling.  My 2.16 GHz Intel Core Duo MacBook Pro battery cable finally went south.  I'm in a studio with half a dozen brand new battery units ... for 2.66 GHz Intel Core i7 MacBook Pro's. Can I use the battery from

  • My location is not listed in keychain

    dear friends I Grievance because I always use Apple system and I am administrator in Arabic MAC forums, but the problem is my State ALGERIA is not listed in the iCloud service because not insert  the telephone number of my location in the Keychain ne

  • How to display ECID in an error page

    Hello everyone, I have a very simple servlet-based application that I am deploying to Oracle Fusion Middleware (version 11.1.1.4). I also have an error page directive in my web.xml that displays a user-friendly page (i.e. "call the helpdesk") when my

  • I restored my ipod touch, and now the touch screen refuses to work

    my ipod touch recently said it needed activation, although I've been using it for 18 months now. When I connected to Itunes, it said it could not read the contents of the Ipod, although it did read the model number and other details. It said to resto